Woodsville Phase 1 D1 and D3 Buildings
by Pharande Promoters and Builders
Gat No. 97 Part, Pimpri Chinchawad (M Corp.), 412105
- Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
Where it is · Gat No. 97 Part, Pimpri Chinchawad (M Corp.)
Area guide
What it's like to buy in Pimpri Chinchawad (M Corp.)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100001127
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Pimpri Chinchawad (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Pimpri Chinchawad (M Corp.) compares.
In Pimpri Chinchawad (M Corp.)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.