Under construction

XRBIA EIFFEL CITY CHAKAN PH2

MahaRERA P52100003059High risk

by XRBIA CHAKAN DEVELOPERS PRIVATE LIMITED

S NO 1438,1449,1447,1448,1450/1,1450/2,1451,1526 P,1527/1,1527/2,1527/3,1440,1441,1443 AND OTHERS, Chakan, 410501

Official record
Mar 2022
Possession
86.8%
Built
46
Complaints
0
Units
High risk
  • 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~1 yr. Originally promised Sept 2020, now proposed Mar 2022 per the RERA filing.
  • 46 RERA complaints. 46 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 86.8%.
  • Promised amenities not started. Kids Play Area is at 0% build with possession due Mar 2022 per the RERA filing.
Satellite view of this address

Where it is · S NO 1438,1449,1447,1448,1450/1,1450/2,1451,1526 P,1527/1,1527/2,1527/3,1440,1441,1443 AND OTHERS, Chakan

Promoter

Builder profile

Builder
XRBIA CHAKAN DEVELOPERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100003059
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally September 2020
Construction
86.8% complete
Units sold
0 of 0

Similar projects in Chakan

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Chakan compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.