Yashone Eternitee Phase 2
by Vilas Javdekar Infinitee Developers Pvt. Ltd.
279/1 Part and 279/2 Part, Maan, 411057
- Behind schedule. Possession is due Jun 2027 but construction is only at 44.6%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Where it is · 279/1 Part and 279/2 Part, Maan
Area guide
What it's like to buy in Maan
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100052676
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 44.6% complete
- Units sold
- 639 of 639
Similar projects in Maan
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Maan compares.
In Maan
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.