High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Satellite view of this address

Where it is · 235/4 and 235/11/1, BHABOLA-BANGALI ROAD

Area guide

What it's like to buy in BHABOLA-BANGALI ROAD

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
VIMAL INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000034120
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2025
Construction
78.8% complete
Units sold
50 of 97