Under construction

YASHWANT PRIDE

MahaRERA P99000020925High risk

by M/s AMEYA BUILDERS & PROPERTY DEVELOPERS

S. NO.4, H. NO. 5/CTS NO 328, S. NO. 5, H. NO. 1/CTS NO. 329, S. NO. 34, H. NO. 2/CTS NO. 331B, Vasai, 401201

Official record
Mar 2020
Possession
90.9%
Built
2
Complaints
0
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession date passed. The proposed possession date (Mar 2020) has passed with construction at 90.9%.

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/s AMEYA BUILDERS & PROPERTY DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000020925
Status
New
Stage
Certificate Signed
Possession
March 2020
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 5 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.