- Possession delayed ~4 yrs. Originally promised Oct 2023, now proposed Oct 2027 per the RERA filing.
Where it is · 265(P),266/1A/1(P),266/1A/2, 266/1B(P),264(P), Khed
Area guide
What it's like to buy in Khed
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100009994
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2027originally October 2023
- Construction
- 32% complete
- Units sold
- 92 of 207
Similar projects in Khed
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Khed compares.
In Khed
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.