High risk
  • Possession delayed ~4 yrs. Originally promised May 2022, now proposed Nov 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. 72 HISSA NO. 4, NANDIVALI GAON

Promoter

Builder profile

Builder
YESU ANAND ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700024758
Status
New
Stage
Certificate Signed
Possession
November 2026originally May 2022
Construction
81.8% complete
Units sold
31 of 68