Under construction
Yogakshema Residency Phase-I
MahaRERA P52000034419High risk
by Superb Maa Infra and Housing LLP
24/2/a and 24/2/b, Panvel, 410221
Post your property hereOwn or renting out a unit in Yogakshema Residency Phase-I? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Panvel come to you.
Dec 2026
Possession
49.5%
Built
0
Complaints
434
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 49.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in Panvel
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Superb Maa Infra and Housing LLP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000034419
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally May 2026
- Construction
- 49.5% complete
- Units sold
- 340 of 434
Similar projects in Panvel
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHREE SAI CORNER
PanvelPoss. March 2027
SAI WORLD CITY PHASE II
PanvelPoss. April 2026
Godrej Golf Side Estate II
PanvelPoss. December 2028
AAKAR 88
PanvelPoss. December 2030
ANANT COMMERZ
PanvelPoss. December 2030
KONNARK ASTRA
PanvelPoss. December 20331 complaint
Adinath Crystal
PanvelPoss. December 2028
Shree Sahayya Prime
PanvelPoss. December 2028
Keep exploring
Where this project sits, who built it, and how Panvel compares.
In Panvel
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.