YOGI BELLEZA
MahaRERA P51700034700High risk
92/12/A, 92/12/B, 92/13, 92/14 92/15 110/9/A/6 110/11 110/13, TEMGHAR, 421302
Post your property hereOwn or renting out a unit in YOGI BELLEZA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TEMGHAR come to you.
Dec 2027
Possession
36.6%
Built
0
Complaints
492
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Area guide
What it's like to buy in TEMGHAR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
YOGI DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700034700
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 36.6% complete
- Units sold
- 215 of 492
Similar projects in TEMGHAR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHIVAM RESIDENCY-PHASE 1
TEMGHAR89.5% builtPoss. December 2026
OM SAI HOME
TEMGHAR87.3% builtPoss. June 2024
ORNATE RISE
TEMGHAR47.7% builtPoss. December 2026
AVANTIKA
TEMGHAR35.3% builtPoss. December 20281 complaint
TALL RESIDENCY
TEMGHAR30.6% builtPoss. December 2028
ROYAL PARK
TEMGHAR19.4% builtPoss. December 2029
KT SKYLIGHT
TEMGHAR19.1% builtPoss. December 2030
Keep exploring
Where this project sits, who built it, and how TEMGHAR compares.
In TEMGHAR
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.