Bellissimo Mulund T2
669 669/1 to 35 670, Kurla, 400081
- Behind schedule. Possession is due Jun 2027 but construction is only at 45.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Where it is · 669 669/1 to 35 670, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51800018893
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally December 2026
- Construction
- 45.9% complete
- Units sold
- 132 of 249
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.