Under construction

BHOSALE EMPIRE

MahaRERA P52100077002High risk

by MORUS DEVELOPERS

CTS NO 106, 107, 109, 110, 111, 113AND 114, KIVALE, 412101

Official record
Apr 2027
Possession
38.6%
Built
0
Complaints
35
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 38.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 106, 107, 109, 110, 111, 113AND 114, KIVALE

Area guide

What it's like to buy in KIVALE

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MORUS DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100077002
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
38.6% complete
Units sold
20 of 35

Similar projects in KIVALE

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how KIVALE compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.