SAMRUDDHI ISHA
CTS NO 1687, 1688 AND 1689, KIVALE, 412101
- Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Dec 2023 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 70.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Where it is · CTS NO 1687, 1688 AND 1689, KIVALE
Area guide
What it's like to buy in KIVALE
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100006794
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2023originally December 2018
- Construction
- 70.9% complete
- Units sold
- 0 of 0
Similar projects in KIVALE
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how KIVALE compares.
In KIVALE
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.