Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2028 per the RERA filing.

Area guide

What it's like to buy in CHARHOLI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
R P PROPERTIES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
RAHUL ARUN NIKAM

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100078307
Status
New
Stage
Certificate Signed
Possession
January 2028originally September 2027
Construction
37.8% complete
Units sold
264 of 543

Similar projects in CHARHOLI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how CHARHOLI compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.