Under construction
DIYA WOODS
MahaRERA P51700021634High risk
PLOT NO 1 SURVEY NO 113 114,116 HISS N0. 1, 7, 1A, TITWALA, 421605
Post your property hereOwn or renting out a unit in DIYA WOODS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in TITWALA come to you.
Jan 2025
Possession
89.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Jan 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Jan 2025) has passed with construction at 89.1%.
Satellite view of this address
Where it is · PLOT NO 1 SURVEY NO 113 114,116 HISS N0. 1, 7, 1A, TITWALA
Promoter
Builder profile
KRISHA ENTERPRISES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700021634
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2025originally December 2022
- Construction
- 89.1% complete
- Units sold
- 0 of 0
Similar projects in TITWALA
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
UMA GALAXY
TITWALA94.1% builtPoss. December 2022
SIDHESHWAR COMPLEX BUILDING 1 A WING
TITWALA90.9% builtPoss. December 2017
SADGURU NAKSHTRA PHASE I
TITWALA90.9% builtPoss. December 2023
ASHOKA HEIGHTS
TITWALA90.9% builtPoss. December 2022
SADGURU NAKSHTRA PHASE II
TITWALA90.9% builtPoss. October 2023
RUSTTAGI AARAMBHA PHASE-III
TITWALA90.9% builtPoss. February 2027
MAMTA 1351
TITWALA83.6% builtPoss. December 2026
RAMDARSHAN RESIDENCY
TITWALA83.2% builtPoss. June 2027
Keep exploring
Where this project sits, who built it, and how TITWALA compares.
In TITWALA
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.