High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 94.1%.
Satellite view of this address

Where it is · Survey No 185, TITWALA

Promoter

Builder profile

Builder
UMIYA ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700002937
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022originally June 2021
Construction
94.1% complete
Units sold
0 of 0

Similar projects in TITWALA

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how TITWALA compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.