The Promise Ledger — Mumbai
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 4,946 projects have pushed their possession date by 3 months or more. The typical slip is 0.3 years; the average is 1.5.
- 53% of the projects still building are already past the date they filed — and another 27% are short of the pace needed to hit it.
- Those slips add up to 3 L buyer-years of extra waiting across 1.9 L homes that were already sold.
Can they still hand over on the date they're selling?
Every under-construction project that discloses both a possession date and a construction percentage, placed by how much time it has left and how much of the build is done. The red line is the pace a site must sustain from here to finish on time — anything below it is being sold on a date its own filing doesn't support.
Swipe the plot sideways for the rest of the timeline.
The end columns are catch-alls: 1,619 projects more than 5 years overdue sit in the first column, and 12 due more than 7 years out sit in the last.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 201728% moved · avg +1.3 yrs
- 201835% moved · avg +2.5 yrs
- 201945% moved · avg +3.5 yrs
- 202047% moved · avg +3.8 yrs
- 202143% moved · avg +4 yrs
- 202241% moved · avg +3.5 yrs
- 202340% moved · avg +3.4 yrs
- 202449% moved · avg +2.5 yrs
- 202557% moved · avg +1.7 yrs
- 202670% moved · avg +0.7 yrs
When a date moves, how far does it move?
Distribution of the 4,946 slips on record. The longest single slip here is 11.3 years.
- 3–12 months2,885
- 1–2 years894
- 2–3 years338
- 3–5 years464
- 5+ years365
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| H RISHABRAJ REALTY | 11 | 100% | 33 · D |
| HGP Community Pvt. Ltd. | 7 | 100% | 81 · A |
| KABRA AND ASSOCIATES | 7 | 100% | 78 · B |
| MAN REALTORS AND HOLDINGS PRIVATE LIMITED | 7 | 100% | 69 · B |
| BALI REALTY LLP | 6 | 100% | 70 · B |
| Modispaces Real Estate Pvt Ltd | 6 | 100% | 78 · B |
| ROMELL REAL ESTATE PRIVATE LIMITED | 6 | 100% | 61 · C |
| MAYFAIR HOUSING | 6 | 100% | 73 · B |
| D. D. ASSOCIATES | 5 | 100% | 52 · C |
| S K DEVELOPERS | 5 | 100% | 71 · B |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Rare Townships Private Limited | 16 | 0% | 50 · C |
| MADHU HARSHAD DOSHI | 7 | 0% | 17 · D |
| SPENTA ENCLAVE PRIVATE LIMITED | 6 | 0% | 23 · D |
| SIDHIVINAYAK CONSTRUCTIONS | 6 | 0% | 85 · A |
| JE AND VEE INFRASTRUCTURE | 6 | 0% | 73 · B |
| SIDDHI REAL ESTATE DEVELOPERS | 5 | 0% | 43 · D |
| Jaykali Developers Private Limited | 5 | 0% | 37 · D |
| SURAJ ESTATE DEVELOPERS LTD | 10 | 10% | 49 · D |
| ELEVATED AVENUE REALTY LLP | 8 | 13% | 87 · A |
| NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED | 7 | 14% | 45 · D |
Selling a date the build pace can't reach
Possession promised within two years, with more construction left than that time can cover at 2.5% a month. Projects reporting 0% are left out — on MahaRERA that is indistinguishable from “not disclosed”. These are the hardest questions to ask before booking.
- NEPTUNE ELEVE WING C · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 2
- VAIBHAV CHOWK SRA CHS LTD · SUNIL MOHAN JOSHI3.6% built, due Dec 2026 · needs ~39 mo, has 2
- INA APARTMENT CO-OPERATIVE HOUSING SOCIETY LIMITED · YASH REALTORS2.3% built, due Dec 2026 · needs ~39 mo, has 2
- Serenity- Bldg 1 · JVPD Properties Private Limited7.3% built, due Nov 2026 · needs ~37 mo, has 1
- Plan I · M/S. Tescon Plan-I LLP7.3% built, due Dec 2026 · needs ~37 mo, has 2
- THE XCLUSIV · Om Omega Shelters7.3% built, due Dec 2026 · needs ~37 mo, has 2
- NEPTUNE ELEVE WING A · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Apr 2027 · needs ~40 mo, has 6
- NEPTUNE ELEVE WING B · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Apr 2027 · needs ~40 mo, has 6
- NEPTUNE ELEVE WING D · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Apr 2027 · needs ~40 mo, has 6
- Anant Nakshatra Tower 1 · Anant Nakshatra Tower 10.9% built, due Apr 2027 · needs ~40 mo, has 6
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- Gadkari Paradise2019 → 2031 +11.3 yrs
- GOKULDHAM2018 → 2028 +10.8 yrs
- AL MARJAAN2018 → 2029 +10.6 yrs
- Integrated Arya2019 → 2029 +10.1 yrs
- AMBER EMPIRE2019 → 2029 +10.1 yrs
- BOUGAIN VILLA - CLUSTER 32021 → 2031 +10 yrs
- SONTERRA STUDIOS2019 → 2029 +9.9 yrs
- RAJ TATTVA PHASE 1 COMMERCIAL2018 → 2027 +9.5 yrs
- Matruchaya CHS Ltd2021 → 2030 +9.5 yrs
- MAULI DESIRE2019 → 2028 +9.4 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 6,721 projects here have a clean record; 1,590 disclose pending litigation and 786 are mortgaged to a lender.
- Wintergreen445 records
- Serenity- Bldg 1392 records
- Ruparel Optima Ph I322 records
- Alta Monte and Signet310 records
- Ruparel Skygreens I272 records
- Hubtown Solaris187 records
- Gaurav Discovery180 records
- Lawns And Beyond - Phase 2, Omkar International District127 records
- Goldcrest Residency - Phase 2118 records
- SHETH MIDORI116 records
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 31 Oct 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.