The Promise Ledger — Maharashtra
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 22,193 projects have pushed their possession date by 3 months or more. The typical slip is 0.3 years; the average is 1.2.
- 55% of the projects still building are already past the date they filed — and another 27% are short of the pace needed to hit it.
- Those slips add up to 10.3 L buyer-years of extra waiting across 7.7 L homes that were already sold.
Can they still hand over on the date they're selling?
Every under-construction project that discloses both a possession date and a construction percentage, placed by how much time it has left and how much of the build is done. The red line is the pace a site must sustain from here to finish on time — anything below it is being sold on a date its own filing doesn't support.
Swipe the plot sideways for the rest of the timeline.
The end columns are catch-alls: 6,219 projects more than 5 years overdue sit in the first column, and 62 due more than 7 years out sit in the last.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 201723% moved · avg +1.5 yrs
- 201830% moved · avg +2.3 yrs
- 201934% moved · avg +3.3 yrs
- 202045% moved · avg +2.4 yrs
- 202138% moved · avg +2.8 yrs
- 202226% moved · avg +2.7 yrs
- 202326% moved · avg +2.9 yrs
- 202430% moved · avg +2.3 yrs
- 202541% moved · avg +1.7 yrs
- 202655% moved · avg +0.7 yrs
When a date moves, how far does it move?
Distribution of the 22,193 slips on record. The longest single slip here is 15.9 years.
- 3–12 months14,364
- 1–2 years3,599
- 2–3 years1,445
- 3–5 years1,689
- 5+ years1,096
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Karnataka Slum Development Board | 37 | 100% | 100 · A+ |
| Rajiv Gandhi Housing Corporation Limited | 23 | 100% | 100 · A+ |
| NIMISH LAXMICHAND PASAD | 14 | 100% | 67 · B |
| Bhavisha Properties | 14 | 100% | 100 · A+ |
| ROMELL REAL ESTATE PRIVATE LIMITED | 13 | 100% | 64 · C |
| H RISHABRAJ REALTY | 11 | 100% | 33 · D |
| GAURAV VISHVANATH AWATI | 11 | 100% | 68 · B |
| Sattva Resi Private Limited | 11 | 100% | 100 · A+ |
| GOVINDA CONSTRUCTION | 10 | 100% | 76 · B |
| SWARA CONSTRUCTION | 10 | 100% | 69 · B |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Rare Townships Private Limited | 16 | 0% | 50 · C |
| Ashdan Developers Private Limited | 16 | 0% | 30 · D |
| TEERTH DEVELOPERS AND TEERTH REALTIES JV | 15 | 0% | 43 · D |
| Pune Projects LLP | 13 | 0% | 20 · D |
| Nirmal Lifestyle (Kalyan) Private Limited | 8 | 0% | 19 · D |
| Sanjivani Integrated Township LLP | 8 | 0% | 38 · D |
| Godrej Skyline Developers Limited | 8 | 0% | 22 · D |
| MADHU HARSHAD DOSHI | 7 | 0% | 17 · D |
| STRAWBERRY CONSTRUCTIONS PVT. LTD. | 7 | 0% | 58 · C |
| RajHeramb Properties | 7 | 0% | 54 · C |
Selling a date the build pace can't reach
Possession promised within two years, with more construction left than that time can cover at 2.5% a month. Projects reporting 0% are left out — on MahaRERA that is indistinguishable from “not disclosed”. These are the hardest questions to ask before booking.
- NEPTUNE ELEVE WING C · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 2
- AMAR INFINITY · AMAR HARISHCHANDRA MANJREKAR0.6% built, due Dec 2026 · needs ~40 mo, has 2
- VAIBHAV CHOWK SRA CHS LTD · SUNIL MOHAN JOSHI3.6% built, due Dec 2026 · needs ~39 mo, has 2
- INA APARTMENT CO-OPERATIVE HOUSING SOCIETY LIMITED · YASH REALTORS2.3% built, due Dec 2026 · needs ~39 mo, has 2
- Venkatesh Pushpakala · SANJAY DNYNOBA JAGTAP1.5% built, due Dec 2026 · needs ~39 mo, has 2
- SADASHIV VISHNU · SADASHIV VISHNU1.5% built, due Dec 2026 · needs ~39 mo, has 2
- VIJAYA COMPLEX · PADMAVATI ENTERPRISES2.7% built, due Dec 2026 · needs ~39 mo, has 2
- VASANT PARK · S S R DEVELOPERS4.5% built, due Jan 2027 · needs ~38 mo, has 2
- MEGH MALHAR · VENUS AND DUSANE DEVELOPERS1.8% built, due Jan 2027 · needs ~39 mo, has 3
- Serenity- Bldg 1 · JVPD Properties Private Limited7.3% built, due Nov 2026 · needs ~37 mo, has 1
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- TRANQUILITY ANNEXE PHASE 22026 → 2041 +15.9 yrs
- INDRADHANU-Phase-52020 → 2035 +15.9 yrs
- GOKULPARK TOWER NO 12018 → 2033 +15 yrs
- SHREE HARIKRISHNA PLAZA2019 → 2032 +12.7 yrs
- Treeline 62019 → 2032 +12.3 yrs
- IMPERIAL HEIGHTS2023 → 2036 +12.3 yrs
- Neuleaf Techd2021 → 2033 +12.3 yrs
- NANDANVAN2016 → 2029 +12.3 yrs
- THE DESTINATION2023 → 2035 +12 yrs
- BLOSSOM GARDEN2019 → 2031 +11.9 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 37,480 projects here have a clean record; 3,950 disclose pending litigation and 2,376 are mortgaged to a lender.
- Wintergreen445 records
- Serenity- Bldg 1392 records
- Ruparel Optima Ph I322 records
- Alta Monte and Signet310 records
- Ruparel Skygreens I272 records
- Hubtown Solaris187 records
- Gaurav Discovery180 records
- VAASTU IMPERIAL Wing A151 records
- Godrej Meadows130 records
- SUBURBIA ESTATE PHASE 1129 records
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 31 Oct 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.