All RERA projects

The Promise Ledger — Pune

Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.

75%
of the 542 completed projects that filed both dates still stand by the possession date they originally committed to.
Market average95 · A+
  • 137 projects have pushed their possession date by 3 months or more. The typical slip is 1.4 years; the average is 1.8.
  • Those slips add up to 8,019 buyer-years of extra waiting across 4,965 homes that were already sold.
542
completed projects in this ledger
571
complaint records across 121 projects
1
recovery warrants on 1 projects
87%
of 14,011 tracked homes sold

Where each year's promises actually went

Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.

Moved the dateHeld the original date
  • 201724% moved
  • 201838% moved
  • 201936% moved
  • 202033% moved
  • 202128% moved
  • 202214% moved
  • 202312% moved
  • 202424% moved
  • 202526% moved
  • 202613% moved

When a date moves, how far does it move?

Distribution of the 137 slips on record. The longest single slip here is 9.6 years.

  • 3–12 months34
  • 1–2 years64
  • 2–3 years17
  • 3–5 years16
  • 5+ years6

Which builders keep the date they filed

Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.

Best kept-date record

Developers with the highest share of possession dates kept
DeveloperProj.KeptScore
MAJESTIQUE HOMES LLP11100%81 · A
Pegasus Properties Pvt. Ltd.5100%91 · A+
M/s. Samarth Builders5100%100 · A+
City Corporation Limited989%82 · A
PANDIT JAVDEKAR ASSOCIATES786%100 · A+

The longest single slips on record

Originally filed date → the date the same registration quotes today.

What buyers did about it

Complaints, misc. applications and recovery warrants disclosed per project. 421 projects here have a clean record; 107 disclose pending litigation and 8 are mortgaged to a lender.

How these numbers are made

Source. Official MahaRERA portal disclosures for every project we track, recomputed 15 Sep 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.

"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.

The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.

Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.

Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.

Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.