The Promise Ledger — Maharashtra
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 694 projects have pushed their possession date by 3 months or more. The typical slip is 1.5 years; the average is 2.
- Those slips add up to 39,164 buyer-years of extra waiting across 19,965 homes that were already sold.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 201722% moved · avg +1.4 yrs
- 201833% moved · avg +1.9 yrs
- 201938% moved · avg +2.6 yrs
- 202025% moved · avg +2.6 yrs
- 202121% moved · avg +2.9 yrs
- 202213% moved · avg +2.4 yrs
- 202312% moved · avg +1.8 yrs
- 202416% moved · avg +1.6 yrs
- 202517% moved · avg +1.1 yrs
- 202616% moved · avg +0.5 yrs
When a date moves, how far does it move?
Distribution of the 694 slips on record. The longest single slip here is 9.6 years.
- 3–12 months183
- 1–2 years282
- 2–3 years90
- 3–5 years88
- 5+ years51
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Tirupati Constructions Co | 11 | 100% | 89 · A |
| SANVO RESORTS PVT. LTD. | 11 | 100% | 60 · C |
| MAJESTIQUE HOMES LLP | 11 | 100% | 81 · A |
| SIDDHIVINAYAK BUILDCON | 8 | 100% | 100 · A+ |
| LAKSHADEEP DEVELOPERS | 8 | 100% | 100 · A+ |
| NNP BUILDCON PVT. LTD. | 8 | 100% | 59 · C |
| ROMA BUILDERS PRIVATE LIMITED | 7 | 100% | 89 · A |
| SHRADDHA LANDMARK PRIVATE LIMITED | 7 | 100% | 100 · A+ |
| Persipina Developers Private Limited | 7 | 100% | 100 · A+ |
| VINOD PREMCHAND CHANDWANI | 7 | 100% | 96 · A+ |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Rare Townships Private Limited | 12 | 0% | 16 · D |
| KEYSTONE REALTORS LIMITED | 5 | 40% | 91 · A+ |
| PRIMESPACE REALTY GROUP | 5 | 40% | 95 · A+ |
| MANTRA BUILDCRAFTS PRIVATE LIMITED | 5 | 40% | 86 · A |
| MANTRA ERECTORS AND BUILDERS LLP | 7 | 57% | 83 · A |
| shree balaji developers | 5 | 60% | 79 · B |
| S K BUILDCON | 5 | 60% | 100 · A+ |
| REGENCY NIRMAN LTD | 8 | 63% | 85 · A |
| Gokhale Constructions | 8 | 63% | 94 · A+ |
| GAYATRI BUILDERS | 6 | 67% | 90 · A+ |
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- Astral Residency2019 → 2028 +9.6 yrs
- SONTERRA STUDIOS2019 → 2029 +9.6 yrs
- AMBAR VILAS2018 → 2027 +9.5 yrs
- FULORA GOLD2019 → 2027 +8.4 yrs
- Bhagat Grandeur2018 → 2027 +8.3 yrs
- Satyam CHS Ltd2018 → 2026 +8 yrs
- Simna Heights / Shantichndra Heights2019 → 2027 +8 yrs
- NISHIGANDH 12019 → 2026 +7.8 yrs
- VIKAS PALAZZO2020 → 2027 +7.5 yrs
- SANGHVI SOLITAIRE2018 → 2026 +7.5 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 2,986 projects here have a clean record; 427 disclose pending litigation and 58 are mortgaged to a lender.
- Wintergreen445 records
- Hubtown Solaris187 records
- Purva Silversand128 records⚠ 1 warrant
- EKTA PARKSVILLE PHASE III125 records
- ICC78 records
- AVANTE71 records
- RUNWAL RESERVE61 records
- BHAGWATI GREENS 355 records⚠ 4 warrants
- Atlanta Heights (A3) - upto 14th Floor53 records
- Balaji Symphony53 records
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 15 Sep 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.