The Promise Ledger — Maharashtra
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 8,625 projects have pushed their possession date by 3 months or more. The typical slip is 1.5 years; the average is 2.2.
- 54% of the projects still building are already past the date they filed — and another 29% are short of the pace needed to hit it.
- Those slips add up to 7.1 L buyer-years of extra waiting across 3.1 L homes that were already sold.
Can they still hand over on the date they're selling?
Every under-construction project that discloses both a possession date and a construction percentage, placed by how much time it has left and how much of the build is done. The red line is the pace a site must sustain from here to finish on time — anything below it is being sold on a date its own filing doesn't support.
Swipe the plot sideways for the rest of the timeline.
The end columns are catch-alls: 6,132 projects more than 5 years overdue sit in the first column, and 61 due more than 7 years out sit in the last.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 201725% moved · avg +1.6 yrs
- 201829% moved · avg +2.4 yrs
- 201934% moved · avg +3.4 yrs
- 202033% moved · avg +3.6 yrs
- 202130% moved · avg +3.8 yrs
- 202221% moved · avg +3.3 yrs
- 202325% moved · avg +3.2 yrs
- 202431% moved · avg +2.3 yrs
- 202544% moved · avg +1.6 yrs
- 202637% moved · avg +0.8 yrs
When a date moves, how far does it move?
Distribution of the 8,625 slips on record. The longest single slip here is 15.9 years.
- 3–12 months2,336
- 1–2 years2,722
- 2–3 years1,229
- 3–5 years1,419
- 5+ years919
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Palava Dwellers Private Limited | 45 | 100% | 42 · D |
| Puranik Builders Limited | 29 | 100% | 45 · D |
| Persipina Developers Private Limited | 26 | 100% | 64 · C |
| SHREE RIDDHI SIDDHI CONSTRUCTIONS | 20 | 100% | 67 · B |
| CAVALCADE PROPERTIES PVT LTD | 19 | 100% | 54 · C |
| Mangesh Dashrath Gaikar | 16 | 100% | 62 · C |
| SWAMI CONSTRUCTIONS | 15 | 100% | 79 · B |
| Arkade Developers Private Limited | 15 | 100% | 53 · C |
| Provident Housing Limited | 15 | 100% | 87 · A |
| Lagoo Apte Developers | 15 | 100% | 70 · B |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| TEERTH DEVELOPERS AND TEERTH REALTIES JV | 15 | 0% | 43 · D |
| Nirmal Lifestyle (Kalyan) Private Limited | 8 | 0% | 19 · D |
| RajHeramb Properties | 7 | 0% | 54 · C |
| MADHU HARSHAD DOSHI | 6 | 0% | 18 · D |
| SPENTA ENCLAVE PRIVATE LIMITED | 6 | 0% | 23 · D |
| Lucina Land Development Limited | 6 | 0% | 0 · D |
| EKTA PARKSVILLE HOMES PVT. LTD. | 6 | 0% | 0 · D |
| PRATHAM YASH BUILDERS | 5 | 0% | 70 · B |
| Shendre and Associates | 5 | 0% | 63 · C |
| VIVA WINNER VENTURE RELATORS LLP | 5 | 0% | 25 · D |
Selling a date the build pace can't reach
Possession promised within two years, with more construction left than that time can cover at 2.5% a month. Projects reporting 0% are left out — on MahaRERA that is indistinguishable from “not disclosed”. These are the hardest questions to ask before booking.
- ROMELL MYRA · ROMELL PROPERTIES PRIVATE LIMITED0.8% built, due Sep 2026 · needs ~40 mo, has 0
- AARYA GLORY APARTMENT · Amit Arvind Thanekar0.9% built, due Dec 2026 · needs ~40 mo, has 3
- THE ADDRESS BUILDING NO.4 · STRAWBERRY CONSTRUCTIONS PVT. LTD.0.9% built, due Dec 2026 · needs ~40 mo, has 3
- Krishna Solitaire - 1 · Krishna Solitaire - 10.3% built, due Dec 2026 · needs ~40 mo, has 3
- EMPIRE TOWER · EKADANTA DEVELOPERS0.7% built, due Dec 2026 · needs ~40 mo, has 3
- NEPTUNE ELEVE WING C · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 3
- NEPTUNE ELEVE WING A · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 3
- NEPTUNE ELEVE WING B · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 3
- NEPTUNE ELEVE WING D · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 3
- Farhan Developers · Bashir Hasan Kirkire0.1% built, due Dec 2026 · needs ~40 mo, has 3
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- TRANQUILITY ANNEXE PHASE 22026 → 2041 +15.9 yrs
- INDRADHANU-Phase-52020 → 2035 +15.9 yrs
- GOKULPARK TOWER NO 12018 → 2033 +15 yrs
- SHREE HARIKRISHNA PLAZA2019 → 2032 +12.7 yrs
- Treeline 62019 → 2031 +12 yrs
- IMPERIAL HEIGHTS2023 → 2035 +12 yrs
- Neuleaf Techd2021 → 2033 +12 yrs
- NANDANVAN2016 → 2028 +12 yrs
- HARIHAR NAGAR ZARI PHASE - I2021 → 2033 +11.8 yrs
- THE DESTINATION2023 → 2035 +11.7 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 34,082 projects here have a clean record; 3,471 disclose pending litigation and 2,287 are mortgaged to a lender.
- Serenity- Bldg 1392 records
- Ruparel Optima Ph I313 records
- Alta Monte and Signet307 records
- Ruparel Skygreens I271 records
- Gaurav Discovery174 records
- VAASTU IMPERIAL Wing A151 records
- SUBURBIA ESTATE PHASE 1129 records
- Lawns And Beyond - Phase 2, Omkar International District127 records
- Goldcrest Residency - Phase 2116 records
- SHETH MIDORI116 records
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 15 Sep 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.