All RERA projects

The Promise Ledger — Pune

Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.

75%
of the 5,600 tracked projects that filed both dates still stand by the possession date they originally committed to.
Market average90 · A+
  • 1,388 projects have pushed their possession date by 3 months or more. The typical slip is 1.4 years; the average is 2.
  • 58% of the projects still building are already past the date they filed — and another 28% are short of the pace needed to hit it.
  • Those slips add up to 1.1 L buyer-years of extra waiting across 58,768 homes that were already sold.
5,600
tracked projects in this ledger
4,856
complaint records across 922 projects
8
recovery warrants on 8 projects
50%
of 3.6 L tracked homes sold

Can they still hand over on the date they're selling?

Every under-construction project that discloses both a possession date and a construction percentage, placed by how much time it has left and how much of the build is done. The red line is the pace a site must sustain from here to finish on time — anything below it is being sold on a date its own filing doesn't support.

Already overdue
2,314 · 58%
past the date in their own filing
Short of the pace
1,107 · 28%
too much left to build in the time
Time in hand
570 · 14%
enough runway at that pace
0%25%50%75%100%4 yrs late2 yrs latedue date+2 yrs+4 yrs+6 yrsTime to the possession date the builder is quoting today →Construction done

Swipe the plot sideways for the rest of the timeline.

1 project428 per cellPace needed to finish on time (2.5% of the build per month)

The end columns are catch-alls: 1,118 projects more than 5 years overdue sit in the first column, and 2 due more than 7 years out sit in the last.

Where each year's promises actually went

Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.

Moved the dateHeld the original date
  • 201725% moved
  • 201830% moved
  • 201932% moved
  • 202036% moved
  • 202126% moved
  • 202227% moved
  • 202325% moved
  • 202442% moved
  • 202556% moved
  • 202643% moved

When a date moves, how far does it move?

Distribution of the 1,388 slips on record. The longest single slip here is 12 years.

  • 3–12 months389
  • 1–2 years523
  • 2–3 years196
  • 3–5 years174
  • 5+ years106

Which builders keep the date they filed

Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.

Best kept-date record

Developers with the highest share of possession dates kept
DeveloperProj.KeptScore
MAJESTIQUE HOMES LLP17100%76 · B
Shubh Housing11100%68 · B
Puranik Buildcon Private Limited10100%34 · D
Astrum Developments Private Limited9100%49 · D
Jindal Mittal Graha Nirman Pvt. Ltd.9100%70 · B
TRISHA DEVELOPERS9100%90 · A+
Speciality Landmarks Private Limited9100%100 · A+
Vilas Javdekar Eco Shelters Private Limited8100%63 · C
NITIN DWARKADAS NYATI8100%59 · C
VIVANTA REALTY8100%76 · B

Most moved dates

Developers with the lowest share of possession dates kept
DeveloperProj.KeptScore
TEERTH DEVELOPERS AND TEERTH REALTIES JV120%43 · D
RajHeramb Properties60%63 · C
Classic Promoters and Builders Private Limited1421%29 · D
Unknown922%68 · B
SWASTIK INFRA729%68 · B
Palchin Real Estates Private Limited729%44 · D
KONARK ASSOCIATES633%64 · C
Niraj Kumar Associates Pvt Ltd633%58 · C
Garve Developers and Promoters838%79 · B
Manjari Housing Projects LLP838%24 · D

Selling a date the build pace can't reach

Possession promised within two years, with more construction left than that time can cover at 2.5% a month. Projects reporting 0% are left out — on MahaRERA that is indistinguishable from “not disclosed”. These are the hardest questions to ask before booking.

  • AMAR INFINITY · AMAR HARISHCHANDRA MANJREKAR0.6% built, due Dec 2026 · needs ~40 mo, has 3
  • MORELLA PHASE II · Buchade Patil Developers4.5% built, due Dec 2026 · needs ~38 mo, has 3
  • Trimurti Spaces · Bridgestone Landmarks LLP4.5% built, due Dec 2026 · needs ~38 mo, has 3
  • GANGA BHAGYODAY TOWER · Legends County Landmark Pvt Ltd7.4% built, due Dec 2026 · needs ~37 mo, has 3
  • SUMAN · Amol Ajit Ravetkar8.2% built, due Dec 2026 · needs ~37 mo, has 3
  • ARENA CONSTRUCTIONS · ARENA CONSTRUCTIONS13.6% built, due Nov 2026 · needs ~35 mo, has 2
  • AVANTIKA · Ranjekar Realty LLP10.9% built, due Dec 2026 · needs ~36 mo, has 3
  • SATYA RESIDENCY · MAKARAND PRABHAKAR WARUDKAR9.1% built, due Jan 2027 · needs ~36 mo, has 4
  • Shivangan · R M Developers Pune15.8% built, due Nov 2026 · needs ~34 mo, has 2
  • SILVER TOUCH · Silver Touch Developers4.5% built, due Apr 2027 · needs ~38 mo, has 7

The longest single slips on record

Originally filed date → the date the same registration quotes today.

What buyers did about it

Complaints, misc. applications and recovery warrants disclosed per project. 4,677 projects here have a clean record; 803 disclose pending litigation and 545 are mortgaged to a lender.

How these numbers are made

Source. Official MahaRERA portal disclosures for every project we track, recomputed 15 Sep 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.

"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.

The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.

Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.

Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.

Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.