Sept 2020
Possession
78.2%
Built
0
Complaints
0
Units
High risk
  • Litigation pending (10). MahaRERA's litigation disclosure lists 10 pending cases against this project.
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 78.2%.
Satellite view of this address

Where it is · 74 Part, 107 Part, 110 Part and 114 Part, Marunji

Area guide

What it's like to buy in Marunji

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100002682
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
78.2% complete
Units sold
0 of 0

Similar projects in Marunji

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Marunji compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.