High risk
  • Possession delayed ~2 yrs. Originally promised Aug 2019, now proposed Feb 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Feb 2021) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Feb 2021 per the RERA filing.
Satellite view of this address

Where it is · 55, Marunji

Area guide

What it's like to buy in Marunji

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
VISION DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100002472
Status
Ongoing
Stage
Certificate Signed
Possession
February 2021originally August 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Marunji

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Marunji compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.