Under construction

LODHA ETERNIS SERENA C

MahaRERA P51800020147High risk

by LODHA DEVELOPERS LIMITED

CTS No.67, 67/1, 74, 75, 75/1 TO 14, 78, 80 PART ONE ONLY OF VILLAGE MULGAON, Andheri, 400093

Official record
Dec 2023
Possession
83.6%
Built
3
Complaints
0
Units
High risk
  • Litigation pending (18). MahaRERA's litigation disclosure lists 18 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 83.6%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2023 per the RERA filing.

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
LODHA DEVELOPERS LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800020147
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
83.6% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.