RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 12 of 61
- DEVAKI COMPLEX7.9 yr overdueDILIP DHARMAJI WAVHAL · Alefata (N.V.), PuneP52100009441· 23.6% built· 1 complaint
- Vrundavan Homes Wing A7.9 yr overduePrapti Spaces · Alandi Rural, PuneP52100005873· 81.4% built
- ORCHID RESIDENCES7.9 yr overdueH.K.PUJARA BUILDERS · Andheri, Mumbai SuburbanP51800004540· 90.9% built
- Sai Kunj Phase 27.9 yr overdueShree Saidatta Associates · Chikhali, PuneP52100011033· 90.9% built
- LABH SHRIVALLI7.9 yr overdueLABHARTI INFRASTRUCTURE · Andheri, Mumbai SuburbanP51800012182· 84.5% built
- KALPATARU APARTMENT7.9 yr overdueS.G.CONSTRUCTION · Roha Ashtami (M Cl), RaigarhP52000014265· 39.1% built
- Nirman Ajinkyatara7.9 yr overdueNIRMAN DEVELOPERS · Ambegaon Budruk, PuneP52100002423· 72% built· 1 complaint
- BHOSALE MARIGOLD7.9 yr overdueLEENA ARJUN GARAD · Ulawe, RaigarhP52000012668· 90.9% built
- GURU ASHISH7.9 yr overdueSHREE GURUKRUPA VENTURES LLP · Thane, ThaneP51700006406· 90.9% built
- SIDDHATANU RESIDENCY7.9 yr overdueSiddhatanu Enterprises · Dapoli Camp, RatnagiriP52800004878· 50% built
- JP RADIANCE7.9 yr overdueJAGDISHPRASAD HANUMNMAL SHARMA · Hingna, NagpurP50500001509· filed Dec 2017 → now Dec 2018· 90.9% built
- PAVILLION RESIDENCY7.9 yr overdueAPEX DEVELOPERS · Mahalunge, PuneP52100006615· 63.6% built
- Palazzio7.9 yr overdueSpenta Builders Private Limited · Kurla, Mumbai SuburbanP51800002414· filed Dec 2017 → now Dec 2018· 90.9% built· 15 complaints
- SHIVALAY RESIDENCY7.9 yr overdueRAJU GHANSHYAM PURSWANI · Varasoli, RaigarhP52000006833· 46.4% built
- INDRAPRASTHA7.9 yr overdueVARDHAMAN BUILDCON · Kusgaon Bk. (CT), PuneP52100011073· 47.3% built
- PEARL RESIDENCY7.9 yr overdueSHREE SAMARTH DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100004979· 61.5% built
- SHARDA HEIGHTS7.9 yr overdueNARENDRA JAGDISHPRASAD AGARWAL · Andheri, Mumbai SuburbanP51800006585· 90.9% built
- KABRA PARADISE7.9 yr overdueKABRA ESTATE AND INVESTMENT CONSULTANTS · Andheri, Mumbai SuburbanP51800000684· 90.9% built
- Atulya Shubh Vastu7.9 yr overdueATULYA TOWNSHIP BUILDCOM PVT LTD · Aatgaon Station, ThaneP51700011737· 10% built
- KALYAN SAMRUDDHI7.9 yr overdueKALYAN TOLL INFRASTRUCTURE LTD · DHRUVA NAGAR, NashikP51600011079· 90.9% built
- RIVERA ESTATES7.9 yr overdueOmega Constructions · Khalapur, RaigarhP52000010090· 41.8% built· 1 complaint
- VEDANT PINAKIN7.9 yr overdueVEDANT BUILDERS · MANJARI Bk, PuneP52100009780· 65.5% built
- Samyak Residency7.9 yr overdueSahebrao Dagdu Kharat · Near Chitale Bandhu Shop, PuneP52100015334· 81.8% built
- SENROOFS PHASE - II7.9 yr overduePIONEER HOUSING · Kurla, Mumbai SuburbanP51800008478· 65.6% built· 2 complaints
- GURUSMARAN7.9 yr overdueKushal Dattaram Mahadik · Dhamandivi, RatnagiriP52800009501· 90.9% built
- SPRINGS PLAZA7.9 yr overdueSHAKTI CORPORATION · NIBM, PuneP52100012202· 66.4% built
- GREEN PARADISE7.9 yr overdueCREATIONPROPERTIES · Sangli Miraj Kupwad (M Corp.), SangliP53100003467· 38.2% built
- CHINTAMANI COMPLEX7.9 yr overdueCHINTAMANI ASSOCIATES · Baramati (M Cl), PuneP52100009269· 90.9% built
- SHANTAI RESIDENCY7.9 yr overdueJSJ BUILDERS AND DEVELOPERS · Haveli, PuneP52100003599· 36.8% built
- KOMAL ORCHID7.9 yr overdueKISHAN HOLARAM ADWANI · WADALA, NashikP51600008588· 90.9% built
- Aadinath Complex Bldg No 1 and 27.9 yr overdueChamunda Developers · Palghar East, PalgharP99000012472· 90.9% built
- KESHAR LAXMI RESIDENCE PHASE 17.9 yr overdueSHREE CONSTRUCTIONS · Pimpri Chinchawad (M Corp.), PuneP52100013932· filed Dec 2017 → now Dec 2018· 90.9% built
- RAI S HERITAGE D Wing7.9 yr overdueRAI RESIDENCY Private Limited · Kalyan, ThaneP51700009044· 54.5% built
- INSIGNIA7.9 yr overdueGaikwad Girme Properties · Pune City, PuneP52100001248· 90.9% built
- RAJVEE PARK7.9 yr overdueVitthal Purushottam Sarap · Malkapur (CT), AkolaP50100013464· 38.5% built· 1 complaint
- Tarangana Nakshatra7.9 yr overdueTarangana Nakshatra · Hadapsar, PuneP52100008669· 49.3% built
- SATYAM IMPERIAL HEIGHTS7.9 yr overdueSATYAM BUILDERS AND DEVELOPERS · Thane, ThaneP51700004307· 90.9% built
- STARGAZE7.9 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · Bavadhan BK, PuneP52100009722· 90.2% built· 1 complaint
- JAYSHREE APARTMENTS PHASE I7.9 yr overdueARCHWAY PROPERTIES · NEW SADASHIV PETH, PuneP52100005789· 90.9% built
- Navpad Nidhi7.9 yr overdueNavpad Realtors · Palghar, PalgharP99000007326· 90.9% built
- Paradise7.9 yr overdueOm Sai Riddhi Siddhi Developers · Thane, ThaneP51700008580· 84.5% built
- The Residences7.9 yr overdueVaijanath Realtors LLP · Kalyan, ThaneP51700010368· 72.7% built
- Sun Aura7.9 yr overdueMittal Vastushilp LLP · Haveli, PuneP52100000302· 81.8% built
- ADINATH ENCLAVE7.9 yr overdueADINATH CONSTRUCTION · Kopargaon (M Cl), AhmednagarP52200013374· 33.6% built
- GULMOHAR PLAZA7.9 yr overdueSUNIL UTTAMRAO FURDE · Residential, SolapurP52600007621· 90.9% built
- VARDHAMAN HOMES7.9 yr overdueJAY AMBE DEVELOPERS · Ambarnath, ThaneP51700006153· 42.7% built
- Ishan Heights7.9 yr overdueShree Construction Builders and Developers · Saptarshi mala, AhmednagarP52200015230· 90.9% built
- Tai-Nana Sadan7.9 yr overdueShree Samarth Developers · Kalyan, ThaneP51700002666· 39.1% built
- GANESH ORCHID7.9 yr overdueEKDANTA NEST LLP · Haveli, PuneP52100004941· 45.5% built
- ROHAN ABHILASHA BUILDING E7.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000832· 90.7% built· 3 complaints
- TATHASTU7.9 yr overdueBALASAI ASSOCIATES · Mawal, PuneP52100001658· 81.8% built
- VENU ENCLAVE7.9 yr overdueOM SAI BUILDER & DEVELOPERS · Nagpur (M Corp.), NagpurP50500010162· 81.8% built
- Pramukh Sneh Phase 27.9 yr overduePramukh Realty · Near Empress Mall, Dadra & Nagar HaveliP49600000001· 90.9% built
- Rajendra Jhaveri Residence7.9 yr overdueUsha Developers · Borivali, Mumbai SuburbanP51800005957· 54.1% built
- Shri Sai Palace7.9 yr overdueAbhijit Madhukar Jagtap · Saswad Rural, PuneP52100005801· 16.7% built
- Constructing 45 T/s EWS on S.No.42-B at Ujalaiwadi, Kolhapur7.9 yr overduePune Housing and Area Development Board Pune · Ujalaiwadi (CT), KolhapurP53000005353· 6.1% built
- Cosmos Classique7.9 yr overdueConcorde Builders · Patlipada, ThaneP51700004457· 64.6% built
- PRIDE PHOENIX BUILDING B1-B27.9 yr overdueABAD ESTATE AOP · Chikalthana, AurangabadP51500000331· 90.9% built
- SHRIHARI RESIDENCY7.9 yr overdueVIJAYA INFRAVENTURES · NEAR LIONS CONVENT, YavatmalP51000014550· 73.1% built
- RAI PARADISE7.9 yr overdueRAI RESIDENCY Private Limited · Kalyan, ThaneP51700012449· 80% built
- SILVER ARCADE7.9 yr overdueSIDDHIVINAYAK ENTERPRISES · Thane, ThaneP51700009261· 90.9% built
- SAI SAGAR7.9 yr overdueSAI INFRA · Ulawe, RaigarhP52000006739· 68.2% built
- BLISS7.9 yr overdueGAURAV ASSOCIATES · Pune (M Corp.), PuneP52100008905· 72.7% built
- AKSHA VRUNDAVAN7.9 yr overdueAKSHA ENTERPRISES · Chikhali Bk., PuneP52100011335· 90.9% built
- Tapasya7.9 yr overdueKotibhaskar Builders · Sangli Miraj Kupwad (M Corp.), SangliP53100006819· 90.9% built
- LIGHTHALL D WING7.9 yr overdueGamma Constructions Pvt Ltd · Kurla, Mumbai SuburbanP51800002737· 90.9% built
- Palladium Exotica Phase- II- D7.9 yr overduePalladium Developers ·P52100004221· 81.8% built
- NAVALAKHA RITZ7.9 yr overdueNAVALAKHA CHORADIYA ASSOCIATES ·P52100002664· filed May 2018 → now Dec 2018· 95.5% built
- SHREE SHYAM7.9 yr overdueKALPESH CHHAGANBHAI AJAGIYA · Panchvati, NashikP51600007475· 90.9% built
- ONE CORNER7.9 yr overdueONE PROPERTIES · Kolhapur (M Corp.), KolhapurP53000004976· filed Dec 2017 → now Dec 2018· 77.3% built
- DEGAONKAR APARTMENT7.9 yr overduePRASAD PRAKASH DEGAONKAR · NORTH KASABA PETH, SolapurP52600014611· 81.4% built
- Vighnaraj Apartment7.9 yr overdueShri Samarth Builders & Developers · Ratnagiri (M Cl), RatnagiriP52800002303· 90.9% built
- Zion7.9 yr overdueSai Mahaavir Developers · Panvel, RaigarhP52000001426· 90.9% built
- TULIP GREEN7.9 yr overdueTushar Mohanrao Khatavkar · Kolhapur (M Corp.), KolhapurP53000012333· 90% built
- MARVEL ARCO B BUILDING7.9 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Hadapsar, PuneP52100008708· 75.9% built· 4 complaints
- Skyways Sereno7.9 yr overduePranam Associates · LOHGAON, PuneP52100002552· 85.8% built
- Royal Palm7.9 yr overdueTabeer Properties · Khode Nagar, NashikP51600010474· 90.9% built
- SOLITAIRE HIGHWAY7.9 yr overdueAAKAR REALTORS · VASAI, PalgharP99000012069· 81.8% built
- AVIGHNA RESIDENCY7.9 yr overdueKonark Shakti Group of Companies · Malad East, Mumbai SuburbanP51800011421· 90.9% built
- Atria Business Center7.9 yr overdueAtria Developers · Baramati (M Cl), PuneP52100001547· 81.8% built
- ERASALI DIVINE7.9 yr overdueA A THAIUP ALI ABDUL MADINA · Uran, RaigarhP52000005380· 72.7% built
- BAYVIEW HEIGHTS7.9 yr overdueHIND CONSTRUCTION · Ward GNorth, Mumbai CityP51900012124· 90.9% built
- Aayush Park II7.9 yr overdueEarnest and Shah Ventures · Varale, PuneP52100000222· 81.8% built
- NEMINATH ASSOCIATES7.9 yr overdueNeminath Associates · Andheri, Mumbai SuburbanP51800004460· filed Dec 2017 → now Dec 2018· 90.9% built
- NINE STAR RESIDENCY KRITIKA7.9 yr overdueYOGESH BIDYE · MAKANE, PalgharP99000009956· 50.5% built
- VIRANGULA CHS LTD7.9 yr overdueRISHABRAJ HOUSING · Borivali, Mumbai SuburbanP51800004450· 85.9% built
- BALAJI RESIDENCY COMPLEX7.9 yr overdueDev Builders and Developers · Hedutane, RaigarhP52000003419· 90.6% built
- Ozarde Complex7.9 yr overdueOnkar Developers · Baramati (M Cl), PuneP52100009428· 80% built
- Shantiniketan Wing B17.9 yr overdueAnmol Associates · Kalyan, ThaneP51700004738· 87.2% built
- BLUE MOON7.9 yr overduePRECISION REALTY · SHINDE CHOWK, SolapurP52600000497· 26.4% built
- Modispaces Doyle7.9 yr overdueModispaces Real Estate Pvt Ltd · Borivali, Mumbai SuburbanP51800006618· 90.9% built
- SAMET SIKAR MAHAL7.9 yr overdueKothari Construction Company · Borivali, Mumbai SuburbanP51800010946· 90.9% built
- Swapnalok Nagari Building no. 34,35,36,377.9 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100001827· 90.9% built
- Sai Pearl Phase 17.9 yr overdueSSD PROMOTERS AND BUILDERS · Pimpale Saudagar, PuneP52100001207· 89.2% built
- THE RESIDENCES7.9 yr overdueOXFORD GOLF AND RESORTS PRIVATE LIMITED · Lavale, PuneP52100003843· 56.4% built· 1 complaint
- SONTERRA RESIDENCES7.9 yr overdueJAISONS PROPERTIES LLP · Mulshi, PuneP52100004313· filed Dec 2017 → now Dec 2018· 55% built
- NILANJAN SHRI7.9 yr overdueBY BUILDERS & DEVELOPERS · DRUVA NAGAR, NashikP51600005856· 90.9% built
- UNIQUE PLAZA7.9 yr overdueUNIQUE PROPERTIES · Vanvaswadi, SataraP52700011400· 67.3% built· 1 complaint
- SAPTASHRUNGI APARTMENT7.9 yr overduePRADEEP RATAN PATIL · Chikhale, RaigarhP52000012255· 88.6% built
- RATAN LUXURIA RATAN ANNEX7.9 yr overdueSHRI NAKODA ENTERPRISES · Ward ABCD, Mumbai CityP51900002984· 77.9% built
- OM RESIDENCY APPARTMENT7.9 yr overdueSIDDHIVINAYAK BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600012992· 90.9% built
- Mauli Residency7.9 yr overdueMauli Enterprises · Panvel, RaigarhP52000007675· 90.9% built
- ROHAN ABHILASHA BUILDING C7.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000483· 90.9% built
- Ozarde Residency7.9 yr overdueOnkar Developers · Baramati (M Cl), PuneP52100007697· 80% built
- Baitul Zubeeda Apartment7.9 yr overdueSIMConstructions · Lanja (CT), RatnagiriP52800008171· 62.7% built
- RAUNAK DELIGHT7.9 yr overdueUNNATHI ASSOCIATES · Thane, ThaneP51700002037· 90.9% built
- Oro Vista7.9 yr overdueSuresh Malpani & Associates · Pune City, PuneP52100006256· filed Dec 2017 → now Dec 2018· 90.9% built
- Mittal Enclave7.9 yr overdueSealink Construction Co. Pvt. Ltd. · Vasai-Virar City (M Corp), PalgharP99000012403· 90.9% built
- MELANGE RESIDENCES - PHASE I7.9 yr overdueRAMA SYNERGY SPACES · Hinjawadi Phase III, PuneP52100002877· 91.8% built· 1 complaint
- SAI SHRUSHTI HEIGHTS-B47.9 yr overdueSAI SHRUSHTI ENTERPRISES · Thane, ThaneP51700000450· 63.6% built
- VRUNDAVAN7.9 yr overdueSHRI LAXMI BALAJI DEVELOPERS · charholi kh, PuneP52100008543· 90.9% built
- YASHWANT RESIDENCY7.9 yr overdueSHREE SAI GANESH ENTERPRISES · Manda, ThaneP51700014382· 59.1% built
- Mahaveer Residency7.9 yr overdueYashodhan Associates · Pune (M Corp.), PuneP52100004257· filed Dec 2017 → now Dec 2018· 89.4% built· 3 complaints
- Panvelkar Crown7.9 yr overdueRahul Vijay Panvelkar · Ambarnath, ThaneP51700000598· 90.9% built
- BALAJI INFINITY7.9 yr overdueBalaji Infinity · Baner, PuneP52100004356· 90.9% built· 1 complaint
- NIRMAN VIVA7.9 yr overdueNIRMAN HOMES · Ambegaon Budruk, PuneP52100006918· 56.4% built
- SHARAYU CLASSIC7.9 yr overdueANIL GULABRAO PAWAR · Pune City, PuneP52100001503· 63.6% built
- CLOUD 117.9 yr overdueSAINATH DEVELOPERS · charholi kh, PuneP52100007087· 90.9% built
- VAIJNATH7.9 yr overduePRAKASH LELE CONSTRUCTION · Kalyan, ThaneP51700005444· 40.5% built
- ROHAN ABHILASHA BUILDING A7.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000471· 88.8% built· 3 complaints
- Windermere Phase 17.9 yr overdueVascon Engineers Ltd · Koregaon ParkP52100003865· 89.5% built
- Ekaaksh7.9 yr overdueNaman Associates · Pune City, PuneP52100005372· filed Mar 2018 → now Dec 2018· 90.9% built
- SABARI ASHVILLE7.9 yr overdueSABARI JANI ASSOCIATES · Kurla, Mumbai SuburbanP51800003066· filed Dec 2017 → now Dec 2018· 99.9% built· 1 complaint
- Kalpawriksha Cooperative Housing Society Limited7.9 yr overdueRELCON REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800002502· 90.9% built
- OM SRUSHTI DARSHAN7.9 yr overdueVINAYAK DEVELOPERS · THANE KHOPAT, ThaneP51900009084· 90.9% built
- MANSAROVAR7.9 yr overdueRK CONSTRUCTION · Ambarnath, ThaneP51700008427· 90.9% built· 3 complaints
- Ekunj Residency7.9 yr overdueMadhuban Infracon and Developers · Pune (CB), PuneP52100002630· 81.8% built
- URJA RESIDENCY7.9 yr overdueURJA BUILDERS AND DEVELOPERS · KHODE MALA, NashikP51600014599· 71.8% built
- VAIBHAV HEIGHTS II7.9 yr overdueVAIBHAV WAREHOUSING · Butibori, NagpurP50500004136· 59.1% built
- HINGNA CITY7.9 yr overdueVIDARBHA BUILDERS · HINGNA BUS STOP, NagpurP50500004473· 77.3% built
- PARSHURAM VEDANT7.9 yr overdueRAM KRISHNA HARI ENTERPRISES · Ambarnath(M Cl), ThaneP51700007493· 50.9% built
- M AND M COUNTY7.9 yr overdueM & M Infrasolutions Pvt. Ltd. · Nashik (M Corp.), NashikP51600011825· 83.2% built
- Karan Suncoast7.9 yr overdueKaran Developers · Bavadhan BK, PuneP52100000474· 87.7% built
- KOTESHWARI HERITAGE7.9 yr overduePDDEVELOPERS · Murud Janjira (M Cl), RaigarhP52000008481· 67.7% built
- KONAARK LAKESHORE7.9 yr overdueIDA INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500006586· 90.9% built
- RAUNAK CITY SECTOR II - B77.9 yr overdueRAUNAK CORPORATION · Kalyan, ThaneP51700006182· 90.9% built
- GURU AANGAN7.9 yr overdueFSK BUILDERS & DEVELOPERS PRIVATE LIMITED · Ulawe, RaigarhP52000010422· 35.5% built
- ONELLA-27.9 yr overdueNimhan Associates · Sus, PuneP52100007329· 56% built
- SUKHKARTA 17.9 yr overdueIMAGE BUILDERS · Khopoli, RaigarhP52000010590· 47.7% built
- GOURI SHARDA7.9 yr overdueSHANKAR SADU MHATRE · Panvel, RaigarhP52000007381· 32.7% built
- Lifescapes Ambar7.9 yr overdueRohan Developers Pvt. Ltd. · Ward GSouth, Mumbai CityP51900001899· 90.9% built· 27 complaints
- GANGADHAR NAGAR A WING7.9 yr overdueONKAR NIVRUTTI MAHALE HUF · Nashik, NashikP51600013925· 55.5% built
- SAI HIRA CLASSIQUE7.9 yr overdueSAI ASHTAVINAYAK INFRA · Pimpri Chinchawad (M Corp.), PuneP52100011756· 50.5% built
- INFINITE GALAXY7.9 yr overdueINFINITE STAR REALTY PVT LTD · Kasarsai, PuneP52100010340· 49% built
- PRABHAT URBANE7.9 yr overdueH.M. ENTERPRISE · Andheri, Mumbai SuburbanP51800002059· 90.9% built
- PEARL BELLEZA7.9 yr overdueCHEMBUR HOTELS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001897· 77.7% built
- ROMELL SHRADDHA7.9 yr overdueSHRADDHA SHIVSHAKTI DEVELOPERS · Borivali, Mumbai SuburbanP51800001420· 90.9% built
- Nakshatra7.9 yr overdueKrishnaraj Developers · Kasar Amboli, PuneP52100006627· 88.2% built
- OSTWAL HEIGHT - 57.9 yr overdueSHREE OSTWAL BUILDERS LTD · Thane, ThaneP51700008433· 90.9% built
- OM HEIGHTS7.9 yr overdueVISION ASSOCIATES · Nashik (M Corp.), NashikP51600011955· 90.9% built
- Sun Sapphire7.9 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · -, PuneP52100001938· 85.2% built
- Gopalkrupa7.9 yr overdueLAGOO APTE · Haveli, PuneP52100003479· 81.8% built
- Tembhurni Prime City Mall - Wing - A - GF And FF - Phase - A17.9 yr overdueDhariwal And Chhoriya Buildcon Pvt Ltd · Tembhurni, SolapurP52600006058· filed Jun 2018 → now Dec 2018· 90.9% built
- SAI NIWAS7.9 yr overdueMEDAPARAMPIL GANGADHARAN SADASHIVAN · Bamandongri, RaigarhP52000011554· 9.1% built
- JALAL MANSION7.9 yr overdueMARYAM ENTERPRISES · Kalyan-Dombivali (M Corp.), ThaneP51700010284· 44.5% built
- Vertical Oriana Phase I7.9 yr overdueVertical Infra · Mundhwa, PuneP52100003700· 51.5% built· 1 complaint
- Platinum7.9 yr overdueSilver Enterprises · Thane, ThaneP51700001981· 81.8% built
- Shree Ganesh Residency7.9 yr overdueAV Associates · TALEGAON, PuneP52100005787· 90.9% built
- Sunshine Phase II7.9 yr overdueSTAR DEVELOPERS · Vasai, PalgharP99000003797· filed Dec 2017 → now Dec 2018· 63.6% built
- MULTAN HEIGHTS7.9 yr overdueS D BHALERAO CONSTRUCTIONS PVT LTD · Andheri, Mumbai SuburbanP51800012470· 90.9% built
- KRISHNA HARMONY7.9 yr overdueRADHE KRISHNA BUILDERS · Karanjade, RaigarhP52000003078· 81.8% built
- Yashada Residency7.9 yr overdueAgresar Construction · Daund, PuneP52100002610· 37.2% built
- Pankaj Height7.9 yr overdueM/S Volition Investments Private Limited · Ward ABCD, Mumbai CityP51900003718· 85.5% built
- Tirupati Garden Phase III7.9 yr overdueRIDDHI SIDDHI CONSTRUCTIONS · Bhagur (M Cl), NashikP51600008472· 90.9% built
- QUEENSLAND7.9 yr overdueMOTI UDHARAM PANJABI · Moshi-Boradewadi, PuneP52100001606· 86.5% built
- Mittal Enclave Mittal Centre Shopping B-37.9 yr overdueSealink Construction Co. Pvt. Ltd. · Vasai, PalgharP99000005104· 72.7% built
- Shree Madhusudan CHSL7.9 yr overdueSpark Builders & Infra Projects Pvt Ltd · Andheri, Mumbai SuburbanP51800005040· filed Dec 2017 → now Dec 2018· 90.9% built
- Kush Sapphire7.9 yr overdueKush Buildcon LLP · Andheri, Mumbai SuburbanP51800007193· 90.9% built
- KOTHARI CHAMBERS7.9 yr overdueNITIN DAYALAL KOTHARI · Nashik, NashikP51600006974· 89.1% built
- SHREE SUMITRA APARTMENTS7.9 yr overdueSHREE MAHALAKSHMI CONSTRUCTIONS · Borivali, Mumbai SuburbanP51800011651· 38.8% built
- SHAHS GOVIND APARTMENT PHASE I7.9 yr overdueSHAH BUILDERS AND DEVELOPERS · NEAR RENUKA MATA MANDIR, NashikP51600007197· 72.7% built
- TULIP RESIDENCY7.9 yr overdueBRRIGHT REALTORS · Palghar, PalgharP99000002162· filed Mar 2018 → now Dec 2018· 90.9% built
- Shhraddha Ellegance Building C7.9 yr overdueShhraddha Properties · Bale, SolapurP52600000708· 90.9% built
- SUBHADRA APARTMENT7.9 yr overdueSPM UNIQUE CONSTRUCTION · Dhamandivi, RatnagiriP52800005997· 37.5% built
- AMI CHSL7.9 yr overdueMEHTA GROUP · Borivali, Mumbai SuburbanP51800008106· 72.7% built
- DHUNDIRAJ7.9 yr overdueHERAMB CONSTRUCTION · Parnaka, ThaneP51700007802· 90.9% built
- SIDDHIVINAYAK GARIMA7.9 yr overdueSIDDHIVINAYAK HOMES · Panvel, RaigarhP52000001125· 89.1% built
- SIMRAN COMPLEX7.9 yr overdueF & R DEVELOPERS · MAHAD, RaigarhP52000012954· 66.4% built· 1 complaint
- SHASHWAT PARK -PHASE II -Z4B7.9 yr overdueSHASHWAT HOMES · Badlapur (M Cl), ThaneP51700005512· 74.5% built
- NEETA NIWAS CHSL7.9 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800006436· 90.9% built
- TIERRA7.9 yr overdueTERRA PROPERTY · WAGHOLI, PuneP52100006109· 90.9% built
- SONAI PARK7.9 yr overdueRELIVE INFRASTRUCTURE · SONAI TEMPAL, PuneP52100010027· 65.5% built
- PRATIKSHA7.9 yr overdueIVSS INFRASTRUCTURES · SUGAT NAGAR, NagpurP50500012077· 66.8% built
- DIVYA SHANTI7.9 yr overdueAnand Properties · Sus, PuneP52100006485· 90.9% built
- OASIS ROYALE7.9 yr overdueMAGESTIC PREMISES PRIVATE LIMITED · Thane, ThaneP51700002717· 44.1% built
- MANAS VASUDHA7.9 yr overdueM/S SHREE MANAS DEVELOPRS · Thane, ThaneP51700003568· 82.7% built
- FUTURE GOLD7.9 yr overdueFUTURE HOMES DEVELOPERS · Thane, ThaneP51700007006· 90.9% built
- VINAYAK SAI RESIDENCY47.9 yr overdueSAI BUILT CON · Pen (M Cl), RaigarhP52000001360· 80% built
- LOTUS COURT7.9 yr overdueBORA HOSPITALITY LLP · panchwati, NashikP51600002017· 70.9% built
- SHREE HARI RESIDENCY7.9 yr overdueM/s SHREE ODHAV DEVELOPERS · Kalyan, ThaneP51700004461· filed Jun 2018 → now Dec 2018· 90.9% built
- Anusaya Heights7.9 yr overdueJaimakk Infra · Karanjade, RaigarhP52000000651· 90.9% built
- SHUBHANGAN PHASE I7.9 yr overdueVenkateshwara Gangotree Associates · Pirangut, PuneP52100004294· 86.4% built
- GURU CHAYA7.9 yr overdueYogesh Ramakant Mahaddalkar · Kalambaste, RatnagiriP52800011087· 51.8% built
- Whitespring7.9 yr overdueCCI PROJECTS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800002287· 99.2% built· 10 complaints
- SHREE GANESH APARTMENT7.9 yr overdueSAFFRON DEVELOPERS · Ulawe, RaigarhP52000006424· 36.4% built
- VISHWASHANTI7.9 yr overdueVISHWATAMAK ASSOCIATES · DIGHIP52100004268· 81.8% built
- Durvankur Apartment7.9 yr overdueVinayak Developers · Haveli, PuneP52100000784· 81.8% built
- Varad Vinayak Vrundavan7.9 yr overdueOM SAI DEVELOPERS · CHARHOLI, PuneP52100013217· 38.2% built
- HARI KIRAN7.9 yr overdueKARDA BUILDCON PRIVATE LIMITED · VIHITGAON, NashikP51600000349· 90.9% built
- SHREESAMARTH APARTMENT7.9 yr overdueSHREEYOG PROPERTIES · WADALA SHIWAR, NashikP51600000748· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.