RERA projects past their possession deadline
11,767 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 3 of 59
- Seawood Harmony8.6 yr overdueGeo Builders · Thane, ThaneP51700005814· 90.9% built
- Western India Mill8.6 yr overdueMHADA · Ward FSouth, Mumbai CityP51900000025· 90.9% built
- PRATHMESH PARK8.6 yr overdueSAKAR GROUP · Nashik, NashikP51600012881· 90.9% built
- SHUBHAM RESIDENCY8.6 yr overdueBHARAT SHRIKANT TIBREWALA · WAGHOLI, PuneP52100008724· 81.8% built
- VIVA AAKANKSHA COMPLEX PHASE 18.6 yr overdueVIVA AAKANKSHA BUILDERS & DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000007383· 77.5% built
- Tulsi Sapphire8.6 yr overdueSHREE MAHAVIR DEVELOPERS · Ulawe, RaigarhP52000001395· 90.9% built
- STAR BUILDERS AND DEVELOPERS8.6 yr overdueSTAR BUILDERS & DEVELOPERS · Vasai, PalgharP99000005302· 90.9% built
- CHINTAMANI8.6 yr overdueKALYANI VILAS · Pune City, PuneP52100012978· 72.7% built
- Lakshmi Gopal Nivas8.6 yr overdueGUND AND PETHE ASSOCIATES · Peth, PuneP52100005259· 77.3% built
- Prasad Nagar8.6 yr overduePrasad Construction · Aurangabad (M Corp.), AurangabadP51500006151· 90.9% built
- RAJVEER HEIGHTS C WING8.6 yr overdueSHRI DATTASAI DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000013241· 81.8% built
- SIDDHIVINAYAK HOMES8.6 yr overdueRAM VASDEV BATHIJA · Panvel, RaigarhP52000010894· 90.9% built
- SAMARTH ANNEX8.6 yr overdueOM SAI BUILDCON · Nashik (M Corp.), NashikP51600006646· 81.8% built
- Trimity Ashwa8.6 yr overdueTrimity Constructions · Kasarwadavali, ThaneP51700007057· 72.7% built
- ROHAN ISHAN WING A 5 TO 11 FLOOR8.6 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Mulshi, PuneP52100000816· 90.9% built
- RUDRANSH8.6 yr overdueSPA JAIN REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800004422· 90.9% built
- THE ATLANTIS8.6 yr overdueDHANYA CONSTRUCTION · Ulawe, RaigarhP52000009741· 89.1% built
- Orchard8.6 yr overdueShiv Parvati Developers · Hadapsar, PuneP52100006525· 81.8% built
- Priya Girish Vihar CHS Ltd8.6 yr overdueAmeya Developers · Kurla, Mumbai SuburbanP51800006961· 90.9% built
- SAI PEARL8.6 yr overdueSHREE DEVELOPERS · Karanjade, RaigarhP52000003239· 99.1% built
- AMBER ELITE8.6 yr overdueADHAR LAND DEVELOPERS PVT. LTD. · AMBEGAON Bk, PuneP52100003416· 90.9% built
- BHOSALE ORCHID8.6 yr overdueBHOSALE LAND DEVELOPERS · Ulawe, RaigarhP52000012681· 90% built
- Samarth Raghukul8.6 yr overdueM/S VIRTUE ENTERPRISES · Ward GNorth, Mumbai CityP51900007414· 71.8% built
- Vishwa Prestige8.6 yr overduePatki-Joshi Engineers and Contractors Pvt. Ltd. · Kolhapur (M Corp.), KolhapurP53000001706· 81.8% built
- KRISHNA NIWAS8.6 yr overdueSHREE KRISHNA HOMES PVT LTD · Kurla, Mumbai SuburbanP51800008073· 90.9% built
- CONST OF 586 EWS 234 MIG TENAMENTS ON LAND BEARING CTS NO 1 C 1 1 BORIVALI WEST MUMBAI 678.6 yr overdueMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Borivali, Mumbai SuburbanP51800008549· 90.9% built
- Padmaansh8.6 yr overduePadmakar Shripad Joshi · Pimpri Chinchawad (M Corp.), PuneP52100010250· 90.9% built
- Mid Town8.6 yr overdueAvirat Ventures · Pimpri Chinchawad (M Corp.), PuneP52100008137· 90.9% built
- SUYOG8.6 yr overdueMADHAV BHALCHANDRA PARANJAPE · Kalyan, ThaneP51700010683· 81.8% built
- IRA C BUILDING PHASE 28.6 yr overdueM/S MAJESTIQUE MANTRA INCORPORATION · UNDRI, PuneP52100002163· 90.9% built
- CROWN EUREKA8.6 yr overdueASGARALI HUSEINIBHAI CONTRACTOR · Panvel, RaigarhP52000012036· 90.9% built
- Shridhar Residency8.6 yr overdueAadi Developers · Karanje Tarf Satara (CT), SataraP52700004938· 64.5% built
- THE CUBE8.6 yr overdueAIM KAPADE CREATORS · Kolhapur (M Corp.), KolhapurP53000001448· 90.9% built
- SUNNY DEVELOPERS8.6 yr overdueSUNNY DEVELOPERS · Nashik, NashikP51600008674· 96.4% built
- SUKHSAGAR NX8.6 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012739· 81.8% built
- GURUDEV RANADE SAHANIWAS8.6 yr overdueVARADKRIPA DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100001998· 77.3% built
- ISHIKA PRIDE8.6 yr overdueNilam suryawanshi · Shahunagar (CT), SataraP52700007670· 81.8% built· 1 complaint
- SHRIKRISHNA ENCLAVE DUPLEX PHASE 18.6 yr overdueSHRIKRISHNA INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500002555· 88.6% built
- Suresh smruti8.5 yr overduePrasad Prabhakar Waghdhare · Rahataghar, RatnagiriP52800004093· 90.9% built
- Bajrang8.5 yr overdueNarsibhai Mavjibhai Mavani · Nashik (M Corp.), NashikP51600011049· 90.9% built
- TANIA PLANET8.5 yr overdueFRENTANIA REALTOUCH BUILDERS PRIVATE LIMITED · Vasai, PalgharP99000008261· 73.6% built
- Arron Complex Phase 18.5 yr overdueArron Builders and Developers · Palghar, PalgharP99000006677· 86.4% built
- J.P. business Plaza8.5 yr overdueD.G.T. Developers · Shirur, PuneP52100012741· 90.9% built
- KEDAR RESIDENCY8.5 yr overdueSHASHIKALA RAMCHANDRA SALUNKHE · Sangli Miraj Kupwad (M Corp.), SangliP53100003176· 90.9% built
- SAI AANGAN8.5 yr overdueSAIJYOTBUILDERS&DEVELOPERS · Ulawe, RaigarhP52000003244· 90.9% built
- PALAVA - ELITE - A to J8.5 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000125· 78.2% built· 3 complaints
- Vizion Galaxy A8.5 yr overdueVIZION CONSTRUCTION · Junnar, PuneP52100004006· 90.9% built
- ONYX APARTMENT - REDEVELOPMENT OF KUNFAYAKUN CHSL BUILDING8.5 yr overdueReFAB CONSTRUCTION (INDIA) PVT. LTD. · Borivali, Mumbai SuburbanP51800007695· 68.7% built
- MAHADEV CORNER8.5 yr overdueMAHADEV CONSTRUCTION · Nashik, NashikP51600008031· 90% built
- Pragati Greenwoods8.5 yr overduePragati Construction · Waksai, PuneP52100008279· 89.1% built
- P SQUARE PHASE 18.5 yr overdueVIJAY CONSTRUCTION NX · Haveli, PuneP52100004354· 60% built
- Saptagiri8.5 yr overdueSaptagiri Developers · Nanded Waghala (M Corp.), NandedP51100002999· 86.4% built
- AATREYA REGENCY8.5 yr overdueHARSHALI ANOOP DESHPANDE · Wanadongri (CT), NagpurP50500003312· 55.3% built
- BHOOMI PRIDE8.5 yr overdueMEHTA DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000008331· 90.9% built
- RAJ RESIDENCY8.5 yr overdueVastu Developers and Promotors · Talegaon Dabhade (M Cl), PuneP52100013370· 90.9% built
- SWARAJ8.5 yr overdueRAMAN BABASO KHAMKAR · Patas, PuneP52100007657· 78.2% built
- ARIHANT PARK PHASE -38.5 yr overdueMADAN NEMICHAND BAFANA · Supa, AhmednagarP52200003497· 90.9% built
- Garva Residency-B28.5 yr overdueGarva Developers Pvt Ltd · Warse, RaigarhP52000004481· 43.2% built
- SHREEJI RESIDENCY8.5 yr overdueSHREE HARI DEVELOPER · Panvel, RaigarhP52000004504· 90.9% built
- Ramdev Villa8.5 yr overdueRamdev Villa · Thane, ThaneP51700006067· 90.9% built
- PALAVA LAKESIDE I TO O8.5 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000410· 78.2% built· 5 complaints
- Gold Coast8.5 yr overdueA SQUARE CONSTRUCTION · Alibag, RaigarhP51800002294· 90.9% built
- Lodha Fiorenza8.5 yr overdueLODHA DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800000195· 90.9% built· 5 complaints
- OM SAI TOWERS8.5 yr overdueD A CONSTRUCTION · Ambarnath(M Cl), ThaneP51700011648· 44.5% built
- Shri Sai8.5 yr overdueSai Ram Builders and Developers · Shirur, PuneP52100010822· 77.7% built
- TORNA APARTMENT8.5 yr overdueRAJMUDRA CONSTRUCTION PVT LTD · Borivali, Mumbai SuburbanP51800009548· 90% built
- Swastik Laxmi8.5 yr overdueSwastik Construction · Palghar, PalgharP99000009764· 90.9% built
- ROYAL BELLEZA8.5 yr overdueANANDKUMAR HARIDAS SONI · Ulawe, RaigarhP52000006588· 90.9% built
- OM PALACE8.5 yr overdueMADHUSUDAN SITARAM JUNNARKAR · Borivali, Mumbai SuburbanP51800007960· 90.9% built
- VASTU SHILP DEVELOPERS8.5 yr overdueVASTU SHILP DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000009007· 89.8% built
- SIDDHIVINAYAK PRIDE8.5 yr overdueSAGAR DILIP RUKARI · MANJARI Bk, PuneP52100000491· filed Dec 2017 → now Feb 2018· 83.6% built
- SAI DURGA HILLS8.5 yr overdueSAI DURGA DEVELOPERS · Bopele, RaigarhP52000003811· 84.5% built
- OMKAR DEEP8.5 yr overdueOMKAR BUIDCON · Nashik (M Corp.), NashikP51600007514· 90.9% built
- SHRI SHRI SAGAR8.5 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012595· 81.8% built
- MAHAVIR ANANT8.5 yr overdueRAHUL PUKHRAJ SINGHVI · Ulawe, RaigarhP52000012352· 90.9% built
- ROYAL ORCHID8.5 yr overdueBALAJI BUILDCON · Upnagar, NashikP51600006397· 70.5% built
- SUCHIT SQUARE8.4 yr overdueIMPRESSIONS · Kalyan, ThaneP51700008664· 90.8% built
- Zubeda Imam Ahmed Bharmal Appartment8.4 yr overdueAAMIRBAHAUDDIN · BHIWANDI, ThaneP51700014694· 55.9% built
- SKY POINT PHASE I B AND C WING8.4 yr overdueShubh Enterprises · Mundhawa, PuneP52100007993· 86.4% built
- SUMUKH8.4 yr overdueBhalchandra Vinayak Wadnerkar · Mumbai City, Mumbai CityP51900004420· 90.9% built· 1 complaint
- KOYANA CONDOMINIUM8.4 yr overdueK J REALTORS · Kothrud, PuneP52100008222· 69% built
- MAHAKALI HIGHTS PHASEII8.4 yr overduePRAVIN DNYANESHWAR MALI · Kavathe Mahankal, SangliP53100007151· 81.8% built
- Prathamesh Residency8.4 yr overdueSiddhivinayak Developers · CHARHOLI, PuneP52100002315· 85.5% built
- Dynasty8.4 yr overdueShiv Enterprises · Pimpri Chinchawad (M Corp.), PuneP52100009988· 90.9% built· 3 complaints
- Shalini Vilas Terraces8.4 yr overdueSHRI SAGAR BUILDERS AND DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000003571· 90.9% built
- Sanghvi Shells8.4 yr overdueMukesh Shantilal Sanghvi · Baner, PuneP52100002539· 72.7% built
- Anandgriha- Phase I8.4 yr overdueKACHHI PROPERTIES · Satara, SataraP52700009557· 89.1% built
- ANGAN RESIDENCY8.4 yr overduePRITHVI BUILDERS & DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100013172· 76.4% built
- SIDDHIVINAYAK TOWER8.4 yr overdueSIDDHIVINAYAK DEVELOPERS · Vasai, PalgharP99000012579· 81.6% built
- Aashirwad Complex8.4 yr overdueSaukhyam Constructions · Nachane (CT), RatnagiriP52800009508· 90.9% built· 2 complaints
- SAI AARADHYA8.4 yr overdueM/S PILLARS INDIA CONSTRUCTIONS · Ulawe, RaigarhP52000010167· 58.5% built
- Shubharambh8.4 yr overdueNIRMAN RESIDENCY · Dehu Road (CB), PuneP52100008363· 63.6% built
- SUWARNALAY8.4 yr overdueNATH ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100012078· 58.6% built
- construction of 26 shops and 03 halls at khat road Bhandara8.4 yr overdueMHADA(Nagpur Board) · Bhandara (M Cl), BhandaraP50600012640· 81.8% built
- Samruddhi Park Phase 28.4 yr overdueSANTOSH MACHINDRA SHINDE · Ahmadnagar (M Corp.), AhmednagarP52200011133· 25% built
- SHUBHANGAN8.4 yr overdueS.H.ENTERPRISE · Vasai, PalgharP99000010435· 90.7% built
- Star Woods Phase I8.4 yr overdueVaishnavi Space Creator · Tathwade, PuneP52100007153· 50% built
- MARBLE ARCH8.4 yr overdueSHINING SUN CONSTRUCTIONS · Panvel, RaigarhP52000013234· 98.2% built· 1 complaint
- YASHWANT NAGAR PLUS8.4 yr overdueNAMRATA MARK VENTURES · Varale, PuneP52100012929· 90.5% built
- Riddhish Residency8.4 yr overdueDamle Gandhe LLP · Baner, PuneP52100009314· 41.2% built
- SALASAR ASHISH8.4 yr overdueSALANGPUR REALTY · Thane, ThaneP51700011018· 90.9% built
- SADASHIV PURAM8.4 yr overdueSATYABHAMA DEVELOPERS · Ambarnath(M Cl), ThaneP51700010168· 90.9% built
- DURVESH APARTMENT8.4 yr overdueUNITED BUILDERS AND DEVELOPERS · Sawantwadi (M Cl), SindhudurgP52900014380· 90.9% built
- BHAGYALAXMI PLAZA8.4 yr overdueDHEERAJ ADINATH NASALAPURE · Sangli Miraj Kupwad (M Corp.), SangliP53100007892· 47.3% built
- Royal Arcade8.4 yr overdueNitin Sudhakar Talathi · Khed (M Cl), RatnagiriP52800002546· 90.9% built
- SAMRUDDHI PRIDE8.4 yr overdueSAMRUDDHI BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600006644· 81.8% built
- Tulsi Developers8.4 yr overdueTulsi Developers · Nanded Waghala (M Corp.), NandedP51100005078· 98.4% built
- Construction of 20 MIG flats on S.No.42,60 at Nari, Nagpur8.4 yr overdueMHADA (Nagpur Board) · Nagpur (M Corp.), NagpurP50500006157· 90.9% built
- MILAP CO-OPERATIVE HOUSING SOCIETY8.4 yr overdueGOLDEN EYECON · Andheri, Mumbai SuburbanP51800001191· 90.9% built
- JUBILATION8.4 yr overdueAAKANKSSHA ASSOCIEATES · WAGHOLI, PuneP52100007279· 90.9% built
- AAI PRASAD8.4 yr overdueVASANT NIVRUTTI NARWADE · Pimpalgaon (CT), YavatmalP51000011716· 81.8% built
- MONICA CORNER8.4 yr overdueMONICA CONSTRUCTION & BUILDERS · Hadapsar, PuneP52100011180· 77.3% built
- VISION WOODS 1 PHASE 18.4 yr overdueSHUBBAN REALTORS · Jambhul, PuneP52100012489· 87.2% built
- srishtee spaces Phase I8.4 yr overdueSRISHTEES Preet Homes · Pimpale Saudagar, PuneP52100003753· 72.7% built
- LONI CENTRAL8.4 yr overdueRDBANKARREALITY · Loni Bk., AhmednagarP52200002916· 90.9% built
- Hayaat Garden8.4 yr overdueM M Enterprises · Vasai, PalgharP99000006530· 81.8% built
- MINT MAGNA HOUSING LLP8.4 yr overdueMint Magna Housing LLP · Ward GSouth, Mumbai CityP51900007234· 81.8% built
- CHANDRA AVENUE8.4 yr overdueCHANDRA REALITY · Shirur, PuneP52100006420· 89.1% built
- ONKARSIDDHI8.4 yr overdueTHAKKAR AND ASSOCIATES · Sangli Miraj Kupwad (M Corp.), SangliP53100006492· 81.8% built
- DATTAKRUPA HEIGHTS8.4 yr overdueDHANANJAY DAMODHAR DAREKAR · Pimpri Chinchawad (M Corp.), PuneP52100005110· 72.7% built
- Siddhivinayak Arcade Bldg48.4 yr overdueSIDDHIVINAYAK DEVELOPERS · Vasai, PalgharP99000010820· 80.5% built
- ShriLaxmi Chambers8.4 yr overdueSudhir Tulshiram Thakre · Chandrapur (M Cl), ChandrapurP50900010597· 90.9% built
- Eisha Erica D Bldg8.4 yr overdueEISHA VASTU CONSTRUCTION · Dhayari (Part), PuneP52100003882· 84.6% built· 1 complaint
- ABM HOMES8.4 yr overdueABM ASSOCIATES ·P52100008869· 54.5% built
- SOHAM PRATHAMESH8.4 yr overdueSOHAM BUILDERS · Deulwadi, RaigarhP52000012015· 51.4% built
- GAJANAN PALACE8.4 yr overdueSHREE GAJANAN BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500002858· 90.9% built
- George Developers ELITE8.4 yr overdueGeorge Developers · Nagpur (M Corp.), NagpurP50500010620· 89.1% built
- Sukruti Elite8.4 yr overdueSukruti Constructions · Nashik (M Corp.), NashikP51600010612· 90.9% built
- PRIME NEW HORIZON8.4 yr overduePRASHANT CHANDRAKANT BHOIR · Pen (M Cl), RaigarhP52000004080· 79.5% built
- Jeevan Kanchan Co-Operative Housing Society Ltd.8.4 yr overdueShri Krishna Chaitanya Enterprises · Andheri, Mumbai SuburbanP51800000014· 90.9% built
- sAI PLAZA8.4 yr overduesAI CONSTRUCTIONS AND DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000011414· 75.5% built
- AROHI APARTMENT8.3 yr overdueNEW AKSHARA CONSTRUCTION · Nashik (M Corp.), NashikP51600008837· 90.9% built
- MEGHDOOT RESIDENCY8.3 yr overdueMILAN INTERBUILT PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800003357· 90.9% built
- Seven Eleven Regency8.3 yr overdueSeven Eleven Construction Private Limited · Mira-Bhayandar (M Corp.), ThaneP51700010338· 90.9% built
- Skyline wealthspace Wing C2 3 to 8 floors8.3 yr overdueSymphony · Kurla, Mumbai SuburbanP51800004870· 90.9% built
- Three Jewels -Shops8.3 yr overdueSnowflower Properties Private Limited · Kondhwa, PuneP52100007533· 72.7% built
- SHREE UMA SHANKAR APARTMENT8.3 yr overdueSHREE SAI AASHRAY DEVELOPERS · Badlapur (M Cl), ThaneP51700005680· 90.9% built
- ESPERENZA8.3 yr overdueSPLENDOUR REALTORS INDIA PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800008847· 99.1% built
- Rajal - Frances CHS Ltd8.3 yr overdueNisar Properties Private Limited · Borivali, Mumbai SuburbanP51800001672· 90.9% built
- BLOSSOM8.3 yr overdueSIDDHIVINAYAK ASSOCIATES · Varale, PuneP52100011032· 90.9% built
- WATERS EDGE PHASE IV8.3 yr overdueOM SAGAR DEVELOPERS · PIMPLE NILAKH, PuneP52100001678· 90.9% built
- THAIS RESIDENCY8.3 yr overdueMERCHANT CONSTRUCTIONS PVT. LTD. · Andheri, Mumbai SuburbanP51800011454· filed Dec 2017 → now Mar 2018· 70.5% built· 6 complaints
- HARI SPARSH II8.3 yr overdueDHARAN INFRA-EPC LIMITED · Bhagur Rural, NashikP51600000119· 69.1% built
- SANSKRUTI8.3 yr overdueSHREE SAI VENKATESH DEVELOPERS · Haveli, PuneP52100003985· 90.9% built
- Deccan Hills Bungalow Scheme8.3 yr overdueC.K. Constructions · Danewadi, KolhapurP53000006061· 85.4% built
- Malwani West View CHS LTD8.3 yr overdueMalwani West View CHS LTD · Borivali, Mumbai SuburbanP51800012895· 90.9% built
- SAI NAND8.3 yr overdueJ J TECHNOCRATS · Thane, ThaneP51700003217· 90.9% built
- YAMUNA NIWAS AND PARK ROW BUNGLOW8.3 yr overdueSHRI SAI CONSTRUCTION · Nashik, NashikP51600013332· 81.8% built
- SWAMI VIHAR8.3 yr overdueHARSHAL MADHAV SHELKE · Daund, PuneP52100012043· 90.9% built
- SHEWALE PARK8.3 yr overdueSHEWALE & SONS · Haveli, PuneP52100012654· 81.9% built
- SAURABH APARTMENT8.3 yr overdueTARACHAND HASTIMAL CHHAJED · Bopele, RaigarhP52000012557· 78.6% built
- PRAMUKH PARADISE8.3 yr overduePRAMUKH DEVELOPERS · Panvel, RaigarhP52000004384· 90.9% built
- CVII8.3 yr overduePARDIS CONSTRUCTION LLP · Kurla, Mumbai SuburbanP51800011608· 90.9% built
- SHRUTI PRESTIGE B WING8.3 yr overdueM/S. SHRUTI DEVELOPERS · AMBEGAON Bk, PuneP52100004965· 81.8% built
- OM VAJRESHWARI PARK8.3 yr overdueSHREE JAGDAMBA DEVELOPERS · Daund, PuneP52100011524· 90.9% built
- AASTHA RESIDENCY8.3 yr overdueYASH BUILDCON · Nashik (M Corp.), NashikP51600010855· 90.9% built
- Crescent Bay - T1 - 40, 41 floors8.3 yr overdueL&T Parel Project LLP (JV with ORDPL) · Ward FSouth, Mumbai CityP51900008032· 50% built
- KUNAL RESIDENCY8.3 yr overdueKUNAL BUILDERS AND DEVELOPERS · Mhasrul, NashikP51600003606· 90.9% built
- Om Shrinivas Apartment8.3 yr overdueShriniwas Developers · Badlapur (M Cl), ThaneP51700013518· 64.5% built
- URJA RESIDENCY8.3 yr overdueANITA BHAUSAHEB KAD · Pune (M Corp.), PuneP52100008634· 88.2% built· 1 complaint
- JAI SANTOSHI MATA HEIGHTS8.3 yr overdueRAJIV THAKUR & ASSOCIATES · DOMBIVLI, ThaneP51700012270· 77.3% built
- SOMANI RESIDENCY8.3 yr overdueNITIN PRABHUDAS SOMANI · Punawale, PuneP52100002216· 65% built
- NIRMITI LIFESPACE8.3 yr overdueNIRMITI LIFESTYLE · Nashik, NashikP51600008064· 81.8% built
- AADITYA MALHAR8.3 yr overdueVAKRATUND REALITIES · Pimpri Chinchawad (M Corp.), PuneP52100010158· 99.8% built· 1 complaint
- VENKATESH GRAFFITI PHASE - 78.3 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100014978· 81.8% built
- Suvidha CHS Ltd8.3 yr overdueAmi & Monika Developers · Kurla, Mumbai SuburbanP51800004792· 80.9% built
- Earth Baug8.3 yr overdueEarth Baug · Ward ABCD, Mumbai CityP51900002761· filed Dec 2017 → now Mar 2018· 81.8% built
- DEVKI PLAZA8.3 yr overduePOWER INFRA DEVELOPERS · Panvel, RaigarhP52000009782· 76.4% built
- Rohit Palms8.3 yr overdueRohit Infra · Pimpri Chinchawad (M Corp.), PuneP52100002481· 90.9% built
- Olive Phase II8.3 yr overdueBlue Skky Builders & Promoters · WAGHOLI, PuneP52100012332· 90.9% built
- BALAJI REGENCY8.3 yr overdueK.M.S. PROMOTERS & BUILDERS · Talegaon Dabhade (M Cl), PuneP52100005120· 90.9% built
- RUSHABH INDUSTRIAL ESTATE8.3 yr overdueRUSHABH ENTERPRISES · Vasai-Virar City (M Corp), PalgharP99000009026· 61.8% built
- Shree Swami Samarth Heights8.3 yr overdueAvani Realtors & Developers · Nachane (CT), RatnagiriP52800009106· 62.7% built
- CLASSIC RESIDENCY8.3 yr overdueCLASSIC CONVENTURE · Uran, RaigarhP52000002944· 75.9% built
- Kesarban8.3 yr overdueAmbrosial Developers Private Limited · Andheri, Mumbai SuburbanP51800001181· 90.9% built
- ZEN APARTMENTS8.3 yr overdueBHOLENATH DEVELOPERS LTD. · Kurla, Mumbai SuburbanP51800002227· 90.9% built
- Sadguru Residency8.3 yr overdueSADGURU INFRA · Ambarnath, ThaneP51700004161· 90.9% built
- SARATHI RESIDENCY8.3 yr overdueSEEMA VIJAY NIKAM · Bhiwandi, ThaneP51700005507· 90.9% built
- M/s Rohan Associates8.3 yr overdueROHAN ASSOCIATES · Vasai-Virar City (M Corp), PalgharP99000013458· 81.8% built
- Rachanaa Solitaire8.3 yr overdueRACHANAA REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800002008· 90.9% built
- SHREYAS VILLA8.3 yr overdueVINODRAI PREMJIBHAI TRAPASIA · Karanjade, RaigarhP52000010176· 90.9% built
- Irene8.3 yr overdueColosseum Developers Pvt.Ltd. · Hadapsar, PuneP52100000313· 90.9% built
- Malwani Asha Jeevan CHS LTD8.3 yr overdueMalwani Asha Jeevan CHS LTD · Borivali, Mumbai SuburbanP51800012990· 90.9% built
- LAMER RESIDENCY8.3 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000002060· 90% built
- SHRAVANAM RESIDENCY8.3 yr overduePRADEEP NARAYAN PAWAR HUF · Aanandwali, NashikP51600009252· 90.9% built
- M/s. Shubham Karoti Complex Phase - I8.3 yr overdueM/s. Shubham Karoti Enterprises · Badlapur (M Cl), ThaneP51700005284· 65.9% built
- CROSSROADS8.3 yr overdueSHREE RAVIRAJ PASHANKAR DEVELOPERS · Wakad, PuneP52100007186· 56.2% built
- BELLA VITA8.3 yr overdueMALKANI PROPERTIES · WAGHOLI, PuneP52100000783· 90.9% built
- BHAKTI PARK B WING8.3 yr overdueBHAKTI CORPORATION · Badlapur (M Cl), ThaneP51700011425· 71.8% built· 1 complaint
- Maheshwari Bhuvan8.3 yr overdueEndemic Realtors Pvt. Ltd. · Mumbai City, Mumbai CityP51900007980· 90.9% built
- DIVYARAJ VALUEHOMES - BLDG C & D8.3 yr overdueDIVYARAJ REAL ESTATE SERVICES LLP · Palghar, PalgharP51800002045· 81.8% built
- DAFFODILS AVENUE PHASE 28.3 yr overduePENTAGON SHREEMANGAL VISHHRAM VENTURES · Somatane, PuneP52100010781· 88.2% built
- SAI ANCHIT8.3 yr overdueVANDANA PRASHANT PINGLE · Karanjade, RaigarhP52000009263· 66.7% built
- YAMUNA ROW BUNGLOW8.3 yr overdueSHRI SAI CONSTRUCTION · Nashik, NashikP51600012798· 81.8% built
- Ramdev Vaayu8.3 yr overdueManoj Motaji Purohit · Thane, ThaneP51700010095· 82.7% built
- PADMAVATI ENCLAVE PHASE 28.3 yr overdueJuzer Firoz Stovewalla · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000028· 61.6% built
- SAI LEELA8.3 yr overdueSAI CONSTRUCTIONS · Haveli, PuneP52100006938· 81.8% built
- SHEEL MARIE CHS8.3 yr overduePUSHPAK REALTY DEVELOPERS · Ward GSouth, Mumbai CityP51900011549· 69.5% built
- SKYLINE CORNER8.3 yr overdueSKYLINE DEVELOPERS · Karanjade, RaigarhP52000007766· 90.9% built
- New Mahavir Darshan Chsl8.3 yr overdueLMP GROUP · Borivali, Mumbai SuburbanP51800012191· 54.1% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.