RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 3 of 61
- VARAD VASTU8.9 yr overdueSHARAD KHARADE · Hinjavadi (CT), PuneP52100013534· 81.8% built
- MALPANI SAFFRON BUILDING NO 28.9 yr overdueGIRIRAJ ENTERPRISES · Nashik (M Corp.), NashikP51600008125· 72.7% built· 3 complaints
- BHAGIRATHI VAIBHAV8.9 yr overdueM/S VAIBHAV DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500010547· 75.5% built
- SARA PARIVARTAN - SECTOR E8.9 yr overdueJagrutsara Structures LLP · Sawangi, AurangabadP51500001935· 89.1% built
- Ozone Residency B wing8.9 yr overdueWestcoastrealty · Alibag, RaigarhP52000007382· 90.9% built
- Platinum Square Phase 18.9 yr overdueVascon Engineers Ltd · Vimannagar, PuneP52100001434· 86.8% built
- OM PARADISE B AND C WING8.9 yr overdueS K BUILDCON · KIWALE, PuneP52100002744· 72.7% built
- SHARVARI WINDGATES, PHASE-I8.9 yr overdueADINATH DEVELOPERS · Punawale, PuneP52100006771· 72.7% built
- Agastya Corporate Park-Wing A8.9 yr overduePRL AGASTYA PRIVATE LIMITED · Mumbai City, Mumbai CityP51900003903· 69.5% built
- Welkin Star8.9 yr overdueWELKIN DEVELOPERS · ULAWE, RaigarhP52000011234· 90.9% built
- LAXMI NARAYAN8.9 yr overdueSIDDHIVINAYAK DEVELOPERS ·P52100006320· 90.9% built
- K City Centre8.9 yr overdueKharde Patil Enterprises · Kopargaon (M Cl), AhmednagarP52200013594· 80% built
- GOKULDHAM APPARTMENT8.9 yr overdueSHREE BALAJI BUILDERS AND DEVELOPERS · NASHIK, NashikP51600009696· 90.9% built
- DATTUSAI COMPLEX BUILDING NO 28.9 yr overdueSAIRAJ ENTERPRISES · DOMBIVLI, ThaneP51700013185· 90% built
- GREEN ACRE8.9 yr overdueFARAZ ASLAM MULLA · Deolali (CB), NashikP51600005270· 89.1% built
- VINAYAK HEIGHTS8.9 yr overdueR R BUILDERS & DEVELOPERS · Talegaon Dabhade (R), PuneP52100010646· 90.9% built
- AMOGH8.9 yr overdueBhalchandra Vinayak Wadnerkar · Mumbai City, Mumbai CityP51900002599· 90.9% built
- SAPPHIRE BLISS8.9 yr overdueRAJESH BIJLANI · Panvel, RaigarhP52000009941· 72.7% built
- PARIJAT BUILDING A8.9 yr overdueSHRI VENKATESH SHARADA INFRACON · AMBEGAON, PuneP52100005323· 81.8% built· 4 complaints
- DHARTI HILLS8.9 yr overdueKRISHNA ENTERPRISES · Ambarnath(M Cl), ThaneP51700012074· 90.9% built
- VIVA VEDANTA - BLDG NO. 28.9 yr overdueVIVA HOMES PRIVATE LIMITED · Vasai, PalgharP99000007076· 90.9% built
- Swapneel Phase 28.9 yr overdueM/S Waman Constructions · Pimpri Chinchawad (M Corp.), PuneP52100003744· 90.9% built
- KAKADE RESIDENCY8.9 yr overdueBMK PROPERTIES PRIVATE LIMITED · Talegaon Dabhade (M Cl), PuneP52100004336· 81.8% built
- JP ENIGMA8.9 yr overdueJaiprakash Gurdasmal Khushalani · Nagpur (M Corp.), NagpurP50500013221· 90.9% built
- SWASTIK MUHURTAM8.9 yr overdueSWASTIKCONSTRUCTION · Mahalunge, PuneP52100007639· 90.9% built
- Bhoomi Vijay Apartment8.9 yr overdueNarayan Jankiram Deshpande · Nashik, NashikP51600012879· 74.5% built
- Shubham Siddhi8.9 yr overdueShubham Realtors · Wadagaon (CT), PuneP52100008013· 81.8% built
- SOLITAIRE8.9 yr overdueVENUS SASCON DEVELOPERS · Pune (M Corp.), PuneP52100003846· 72.7% built
- POONAM PALASH8.9 yr overdueSUMIT JAWAHARLAL JAIN · Vasai, PalgharP99000013226· 81.5% built· 1 complaint
- CORE8.9 yr overdueAHURA BUILDERS · Pune (M Corp.), PuneP52100013229· 90.9% built
- New Shiv Shubham8.9 yr overdueWaghandCompany · Nashik Road, NashikP51600013437· 90.9% built
- CROWN EUREKA8.9 yr overdueASGARALI HUSEINIBHAI CONTRACTOR · Panvel, RaigarhP52000012036· 90.9% built
- Shridhar Residency8.9 yr overdueAadi Developers · Karanje Tarf Satara (CT), SataraP52700004938· 64.5% built
- THE CUBE8.9 yr overdueAIM KAPADE CREATORS · Kolhapur (M Corp.), KolhapurP53000001448· 90.9% built
- SUNNY DEVELOPERS8.9 yr overdueSUNNY DEVELOPERS · Nashik, NashikP51600008674· 96.4% built
- SUKHSAGAR NX8.8 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012739· 81.8% built
- GURUDEV RANADE SAHANIWAS8.8 yr overdueVARADKRIPA DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100001998· 77.3% built
- ISHIKA PRIDE8.8 yr overdueNilam suryawanshi · Shahunagar (CT), SataraP52700007670· 81.8% built· 1 complaint
- SHRIKRISHNA ENCLAVE DUPLEX PHASE 18.8 yr overdueSHRIKRISHNA INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500002555· 88.6% built
- Suresh smruti8.8 yr overduePrasad Prabhakar Waghdhare · Rahataghar, RatnagiriP52800004093· 90.9% built
- Bajrang8.8 yr overdueNarsibhai Mavjibhai Mavani · Nashik (M Corp.), NashikP51600011049· 90.9% built
- KEDAR RESIDENCY8.8 yr overdueSHASHIKALA RAMCHANDRA SALUNKHE · Sangli Miraj Kupwad (M Corp.), SangliP53100003176· 90.9% built
- TANIA PLANET8.8 yr overdueFRENTANIA REALTOUCH BUILDERS PRIVATE LIMITED · Vasai, PalgharP99000008261· 73.6% built
- Arron Complex Phase 18.8 yr overdueArron Builders and Developers · Palghar, PalgharP99000006677· 86.4% built
- J.P. business Plaza8.8 yr overdueD.G.T. Developers · Shirur, PuneP52100012741· 90.9% built
- SAI AANGAN8.8 yr overdueSAIJYOTBUILDERS&DEVELOPERS · Ulawe, RaigarhP52000003244· 90.9% built
- OM PALACE8.8 yr overdueMADHUSUDAN SITARAM JUNNARKAR · Borivali, Mumbai SuburbanP51800007960· 90.9% built
- Ramdev Villa8.8 yr overdueRamdev Villa · Thane, ThaneP51700006067· 90.9% built
- TORNA APARTMENT8.8 yr overdueRAJMUDRA CONSTRUCTION PVT LTD · Borivali, Mumbai SuburbanP51800009548· 90% built
- ONYX APARTMENT - REDEVELOPMENT OF KUNFAYAKUN CHSL BUILDING8.8 yr overdueReFAB CONSTRUCTION (INDIA) PVT. LTD. · Borivali, Mumbai SuburbanP51800007695· 68.7% built
- Garva Residency-B28.8 yr overdueGarva Developers Pvt Ltd · Warse, RaigarhP52000004481· 43.2% built
- AATREYA REGENCY8.8 yr overdueHARSHALI ANOOP DESHPANDE · Wanadongri (CT), NagpurP50500003312· 55.3% built
- PALAVA - ELITE - A to J8.8 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000125· 78.2% built· 3 complaints
- MAHADEV CORNER8.8 yr overdueMAHADEV CONSTRUCTION · Nashik, NashikP51600008031· 90% built
- VASTU SHILP DEVELOPERS8.8 yr overdueVASTU SHILP DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000009007· 89.8% built
- Swastik Laxmi8.8 yr overdueSwastik Construction · Palghar, PalgharP99000009764· 90.9% built
- Lodha Fiorenza8.8 yr overdueLODHA DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800000195· 90.9% built· 5 complaints
- Vizion Galaxy A8.8 yr overdueVIZION CONSTRUCTION · Junnar, PuneP52100004006· 90.9% built
- ROYAL BELLEZA8.8 yr overdueANANDKUMAR HARIDAS SONI · Ulawe, RaigarhP52000006588· 90.9% built
- SHREEJI RESIDENCY8.8 yr overdueSHREE HARI DEVELOPER · Panvel, RaigarhP52000004504· 90.9% built
- BHOOMI PRIDE8.8 yr overdueMEHTA DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000008331· 90.9% built
- P SQUARE PHASE 18.8 yr overdueVIJAY CONSTRUCTION NX · Haveli, PuneP52100004354· 60% built
- Gold Coast8.8 yr overdueA SQUARE CONSTRUCTION · Alibag, RaigarhP51800002294· 90.9% built
- RAJ RESIDENCY8.8 yr overdueVastu Developers and Promotors · Talegaon Dabhade (M Cl), PuneP52100013370· 90.9% built
- OM SAI TOWERS8.8 yr overdueD A CONSTRUCTION · Ambarnath(M Cl), ThaneP51700011648· 44.5% built
- PALAVA LAKESIDE I TO O8.8 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000410· 78.2% built· 5 complaints
- Shri Sai8.8 yr overdueSai Ram Builders and Developers · Shirur, PuneP52100010822· 77.7% built
- SWARAJ8.8 yr overdueRAMAN BABASO KHAMKAR · Patas, PuneP52100007657· 78.2% built
- Saptagiri8.8 yr overdueSaptagiri Developers · Nanded Waghala (M Corp.), NandedP51100002999· 86.4% built
- Pragati Greenwoods8.8 yr overduePragati Construction · Waksai, PuneP52100008279· 89.1% built
- ARIHANT PARK PHASE -38.8 yr overdueMADAN NEMICHAND BAFANA · Supa, AhmednagarP52200003497· 90.9% built
- SIDDHIVINAYAK PRIDE8.8 yr overdueSAGAR DILIP RUKARI · MANJARI Bk, PuneP52100000491· filed Dec 2017 → now Feb 2018· 83.6% built
- SAI DURGA HILLS8.8 yr overdueSAI DURGA DEVELOPERS · Bopele, RaigarhP52000003811· 84.5% built
- OMKAR DEEP8.7 yr overdueOMKAR BUIDCON · Nashik (M Corp.), NashikP51600007514· 90.9% built
- SHRI SHRI SAGAR8.7 yr overdueSagar Constructions · Nashik (M Corp.), NashikP51600012595· 81.8% built
- MAHAVIR ANANT8.7 yr overdueRAHUL PUKHRAJ SINGHVI · Ulawe, RaigarhP52000012352· 90.9% built
- ROYAL ORCHID8.7 yr overdueBALAJI BUILDCON · Upnagar, NashikP51600006397· 70.5% built
- SUCHIT SQUARE8.7 yr overdueIMPRESSIONS · Kalyan, ThaneP51700008664· 90.8% built
- Dynasty8.7 yr overdueShiv Enterprises · Pimpri Chinchawad (M Corp.), PuneP52100009988· 90.9% built· 3 complaints
- SUMUKH8.7 yr overdueBhalchandra Vinayak Wadnerkar · Mumbai City, Mumbai CityP51900004420· 90.9% built· 1 complaint
- SAI AARADHYA8.7 yr overdueM/S PILLARS INDIA CONSTRUCTIONS · Ulawe, RaigarhP52000010167· 58.5% built
- Sanghvi Shells8.7 yr overdueMukesh Shantilal Sanghvi · Baner, PuneP52100002539· 72.7% built
- Shubharambh8.7 yr overdueNIRMAN RESIDENCY · Dehu Road (CB), PuneP52100008363· 63.6% built
- MAHAKALI HIGHTS PHASEII8.7 yr overduePRAVIN DNYANESHWAR MALI · Kavathe Mahankal, SangliP53100007151· 81.8% built
- SIDDHIVINAYAK TOWER8.7 yr overdueSIDDHIVINAYAK DEVELOPERS · Vasai, PalgharP99000012579· 81.6% built
- KOYANA CONDOMINIUM8.7 yr overdueK J REALTORS · Kothrud, PuneP52100008222· 69% built
- SUWARNALAY8.7 yr overdueNATH ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100012078· 58.6% built
- SKY POINT PHASE I B AND C WING8.7 yr overdueShubh Enterprises · Mundhawa, PuneP52100007993· 86.4% built
- Shalini Vilas Terraces8.7 yr overdueSHRI SAGAR BUILDERS AND DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000003571· 90.9% built
- Anandgriha- Phase I8.7 yr overdueKACHHI PROPERTIES · Satara, SataraP52700009557· 89.1% built
- construction of 26 shops and 03 halls at khat road Bhandara8.7 yr overdueMHADA(Nagpur Board) · Bhandara (M Cl), BhandaraP50600012640· 81.8% built
- Aashirwad Complex8.7 yr overdueSaukhyam Constructions · Nachane (CT), RatnagiriP52800009508· 90.9% built· 2 complaints
- Zubeda Imam Ahmed Bharmal Appartment8.7 yr overdueAAMIRBAHAUDDIN · BHIWANDI, ThaneP51700014694· 55.9% built
- Samruddhi Park Phase 28.7 yr overdueSANTOSH MACHINDRA SHINDE · Ahmadnagar (M Corp.), AhmednagarP52200011133· 25% built
- Prathamesh Residency8.7 yr overdueSiddhivinayak Developers · CHARHOLI, PuneP52100002315· 85.5% built
- ANGAN RESIDENCY8.7 yr overduePRITHVI BUILDERS & DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100013172· 76.4% built
- MARBLE ARCH8.7 yr overdueSHINING SUN CONSTRUCTIONS · Panvel, RaigarhP52000013234· 98.2% built· 1 complaint
- Star Woods Phase I8.7 yr overdueVaishnavi Space Creator · Tathwade, PuneP52100007153· 50% built
- YASHWANT NAGAR PLUS8.7 yr overdueNAMRATA MARK VENTURES · Varale, PuneP52100012929· 90.5% built
- SHUBHANGAN8.7 yr overdueS.H.ENTERPRISE · Vasai, PalgharP99000010435· 90.7% built
- Riddhish Residency8.7 yr overdueDamle Gandhe LLP · Baner, PuneP52100009314· 41.2% built
- SALASAR ASHISH8.7 yr overdueSALANGPUR REALTY · Thane, ThaneP51700011018· 90.9% built
- Royal Arcade8.7 yr overdueNitin Sudhakar Talathi · Khed (M Cl), RatnagiriP52800002546· 90.9% built
- BHAGYALAXMI PLAZA8.7 yr overdueDHEERAJ ADINATH NASALAPURE · Sangli Miraj Kupwad (M Corp.), SangliP53100007892· 47.3% built
- SADASHIV PURAM8.7 yr overdueSATYABHAMA DEVELOPERS · Ambarnath(M Cl), ThaneP51700010168· 90.9% built
- SAMRUDDHI PRIDE8.7 yr overdueSAMRUDDHI BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600006644· 81.8% built
- DURVESH APARTMENT8.7 yr overdueUNITED BUILDERS AND DEVELOPERS · Sawantwadi (M Cl), SindhudurgP52900014380· 90.9% built
- Construction of 20 MIG flats on S.No.42,60 at Nari, Nagpur8.6 yr overdueMHADA (Nagpur Board) · Nagpur (M Corp.), NagpurP50500006157· 90.9% built
- Tulsi Developers8.6 yr overdueTulsi Developers · Nanded Waghala (M Corp.), NandedP51100005078· 98.4% built
- MILAP CO-OPERATIVE HOUSING SOCIETY8.6 yr overdueGOLDEN EYECON · Andheri, Mumbai SuburbanP51800001191· 90.9% built
- JUBILATION8.6 yr overdueAAKANKSSHA ASSOCIEATES · WAGHOLI, PuneP52100007279· 90.9% built
- AAI PRASAD8.6 yr overdueVASANT NIVRUTTI NARWADE · Pimpalgaon (CT), YavatmalP51000011716· 81.8% built
- VISION WOODS 1 PHASE 18.6 yr overdueSHUBBAN REALTORS · Jambhul, PuneP52100012489· 87.2% built
- MONICA CORNER8.6 yr overdueMONICA CONSTRUCTION & BUILDERS · Hadapsar, PuneP52100011180· 77.3% built
- srishtee spaces Phase I8.6 yr overdueSRISHTEES Preet Homes · Pimpale Saudagar, PuneP52100003753· 72.7% built
- LONI CENTRAL8.6 yr overdueRDBANKARREALITY · Loni Bk., AhmednagarP52200002916· 90.9% built
- Eisha Erica D Bldg8.6 yr overdueEISHA VASTU CONSTRUCTION · Dhayari (Part), PuneP52100003882· 84.6% built· 1 complaint
- SOHAM PRATHAMESH8.6 yr overdueSOHAM BUILDERS · Deulwadi, RaigarhP52000012015· 51.4% built
- GAJANAN PALACE8.6 yr overdueSHREE GAJANAN BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500002858· 90.9% built
- sAI PLAZA8.6 yr overduesAI CONSTRUCTIONS AND DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000011414· 75.5% built
- ShriLaxmi Chambers8.6 yr overdueSudhir Tulshiram Thakre · Chandrapur (M Cl), ChandrapurP50900010597· 90.9% built
- Jeevan Kanchan Co-Operative Housing Society Ltd.8.6 yr overdueShri Krishna Chaitanya Enterprises · Andheri, Mumbai SuburbanP51800000014· 90.9% built
- PRIME NEW HORIZON8.6 yr overduePRASHANT CHANDRAKANT BHOIR · Pen (M Cl), RaigarhP52000004080· 79.5% built
- Sukruti Elite8.6 yr overdueSukruti Constructions · Nashik (M Corp.), NashikP51600010612· 90.9% built
- CHANDRA AVENUE8.6 yr overdueCHANDRA REALITY · Shirur, PuneP52100006420· 89.1% built
- Hayaat Garden8.6 yr overdueM M Enterprises · Vasai, PalgharP99000006530· 81.8% built
- George Developers ELITE8.6 yr overdueGeorge Developers · Nagpur (M Corp.), NagpurP50500010620· 89.1% built
- MINT MAGNA HOUSING LLP8.6 yr overdueMint Magna Housing LLP · Ward GSouth, Mumbai CityP51900007234· 81.8% built
- DATTAKRUPA HEIGHTS8.6 yr overdueDHANANJAY DAMODHAR DAREKAR · Pimpri Chinchawad (M Corp.), PuneP52100005110· 72.7% built
- ONKARSIDDHI8.6 yr overdueTHAKKAR AND ASSOCIATES · Sangli Miraj Kupwad (M Corp.), SangliP53100006492· 81.8% built
- Siddhivinayak Arcade Bldg48.6 yr overdueSIDDHIVINAYAK DEVELOPERS · Vasai, PalgharP99000010820· 80.5% built
- ABM HOMES8.6 yr overdueABM ASSOCIATES ·P52100008869· 54.5% built
- GOLDEN PALM APARTMENT8.6 yr overdueRaka and Baheti Associates · Devlai, AurangabadP51500001812· 86.4% built
- SHREYAS VILLA8.6 yr overdueVINODRAI PREMJIBHAI TRAPASIA · Karanjade, RaigarhP52000010176· 90.9% built
- SHREE SAI8.6 yr overdueSHREE SAI DEVELOPERS · Karanje Tarf Satara (CT), SataraP52700012765· 68.2% built
- GAGAN NULIFE PHASE 18.6 yr overdueGAGAN LIFESPACE · Kamshet, PuneP52100009642· 81.8% built· 7 complaints
- Om Shrinivas Apartment8.6 yr overdueShriniwas Developers · Badlapur (M Cl), ThaneP51700013518· 64.5% built
- EASTERN ROYALE8.6 yr overdueKate Moze Associates · LOHGAON, PuneP52100013009· 81.8% built
- BHUVI VRUNDAVAN - 18.6 yr overdueBhuvi Landmarks LLP · Kumbhefal, AurangabadP51500003772· 81.8% built
- SMITAL AVENUE8.6 yr overdueD. L. BUILDERS PVT. LTD. · Mira-Bhayandar (M Corp.), ThaneP51700010363· 86.4% built
- Deccan Hills Bungalow Scheme8.6 yr overdueC.K. Constructions · Danewadi, KolhapurP53000006061· 85.4% built
- ADARSH NIVARA8.6 yr overdueMEENA PRAKASH JAIN · Choupatty Karanja, AhmednagarP52200001520· 64.2% built
- ATHARVA PLAZA8.6 yr overdueD G ASSOCIATES · Pune (M Corp.), PuneP52100008518· 81.8% built
- AKSHAY COUNTY8.6 yr overdueSHREE PROPERTIES · Pune City, PuneP52100005138· 56.4% built
- CHARMS MEADOWS PHASE I8.6 yr overdueCHARMS PRIDE · Asangaon (CT), ThaneP51700010110· 90.5% built· 3 complaints
- KUNAL RESIDENCY8.6 yr overdueKUNAL BUILDERS AND DEVELOPERS · Mhasrul, NashikP51600003606· 90.9% built
- ROYAL PRIDE8.6 yr overdueROYAL BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000002329· 90.9% built
- LAMER RESIDENCY8.6 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000002060· 90% built
- Irene8.6 yr overdueColosseum Developers Pvt.Ltd. · Hadapsar, PuneP52100000313· 90.9% built
- Varun Residency8.6 yr overdueVARUN RESIDENCY · nakashtrawadi, AurangabadP51500007831· 73.2% built
- BLUE SAPPHIRE8.6 yr overdueBLUEBERRY DEVELOPERS · Somatane, PuneP52100007703· 90.9% built
- NIRAVANA ENCLAVE8.6 yr overdueJAGDISH LAKHMICHAND MOHINANI · Neral, RaigarhP52000001635· 90.9% built
- SHRINIVAS HEIGHTS8.6 yr overdueVYANKTESH VASANT DESHPANDE · SAWANTWADI, SindhudurgP52900006630· 30.3% built
- PRANAV APARTMENT8.6 yr overdueAARYA DEVELOPERS · Palghar, PalgharP99000004490· 90.9% built
- SHREE MANGALMURTI8.6 yr overdueSHIVAM UNIVERSAL · Kalyan, ThaneP51700002559· 80% built
- BHAKTI PARK B WING8.6 yr overdueBHAKTI CORPORATION · Badlapur (M Cl), ThaneP51700011425· 71.8% built· 1 complaint
- B-1 Mukta Heights8.6 yr overduePRAVIN SAKHARAM PATIL · Thane, ThaneP51700010086· 76.4% built
- PRECIOUS HARMONY8.6 yr overdueM/s Soham Construction · Badlapur (M Cl), ThaneP51700006810· 90.9% built
- Nayana Niwas8.6 yr overdueH.D.Associates · Borivali, Mumbai SuburbanP51800004622· 60% built
- VRINDAVAN HEIGHT8.6 yr overdueSHIVSAI BUILDCON · Nashik, NashikP51600008519· 90.9% built
- SHEWALE PARK8.6 yr overdueSHEWALE & SONS · Haveli, PuneP52100012654· 81.9% built
- CHARMS HEIGHTS PHASE-I B1-B48.6 yr overdueCharms Developers · Titwala, ThaneP51700002055· 90.9% built· 2 complaints
- Esquire Homes - B8.6 yr overdueEsquire Realtors · Panvel, RaigarhP52000012887· 90.9% built
- SHREE GANESH TOWER - UNIT D8.6 yr overduePOLITE DEVELOPERS · MOSHI, PuneP52100005276· 90.9% built
- MADHUMALTI APARTMENT B WING8.6 yr overdueSHREE DATTA ENTERPRISES · Belavli, ThaneP51700014710· 81.8% built
- PARMAR NAKSHTRA8.6 yr overdueSHREE AMBIKA ESTATES AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500012797· 68.2% built
- RUSHABH INDUSTRIAL ESTATE8.6 yr overdueRUSHABH ENTERPRISES · Vasai-Virar City (M Corp), PalgharP99000009026· 61.8% built
- Sai Darshan Type C8.6 yr overdueDINESH SADANAND BARI · Dahanu (M Cl), PalgharP99000005978· 52.7% built
- SHELTON B8.6 yr overduePatel Construction co · Andheri, Mumbai SuburbanP51800002799· 72.7% built
- SKYLINE-II-MHADA8.6 yr overdueUNIQUE SHANTI NEMINATH DEVELOPERS LLP · Thane, ThaneP51700004954· 96.5% built
- Sukh Vastu8.6 yr overdueA V Bhat Builders Pvt Ltd · Haveli, PuneP52100005379· 90.9% built· 3 complaints
- Antheia C18.6 yr overdueMahindra Lifespace Developers limited · Haveli, PuneP52100000217· 81.8% built
- New Mahavir Darshan Chsl8.6 yr overdueLMP GROUP · Borivali, Mumbai SuburbanP51800012191· 54.1% built
- GULRAJ HEIGHTS8.6 yr overdueM/S NEETA DEVELOPER · Kurla, Mumbai SuburbanP51800009977· 90% built
- Vasant Paradise8.6 yr overdueShri Vasant Developers · Karjat, RaigarhP52000011025· 80% built
- Samarth Samruddhi8.6 yr overdueMandar Madhukar Karandikar · Pen (M Cl), RaigarhP52000007981· 43.2% built
- SWAMI VIHAR8.6 yr overdueHARSHAL MADHAV SHELKE · Daund, PuneP52100012043· 90.9% built
- Navshya Elite8.6 yr overdueDhruv Developers · Aanandwali, NashikP51600009682· filed Dec 2017 → now Mar 2018· 81.8% built
- TIRUPATI HIEGHTS8.6 yr overdueSHRI TIRUPATI REALTY · Bhiwandi, ThaneP51700006941· 79.1% built
- S S PARK IST PHASE8.6 yr overdueS S DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500012611· 84.1% built
- GENESIS8.6 yr overdueTODAY PRACHAR REALTY · Panvel, RaigarhP52000002114· 90.9% built
- Siddharth Apartment8.6 yr overdueRohan Gruh Nirman · Badlapur (M Cl), ThaneP51700013427· 60.9% built
- SHREE RAM8.6 yr overdueRACHANAA · Kurla, Mumbai SuburbanP51800001464· 90.9% built
- Sanvi Arcade8.6 yr overdueSantosh Dattatraya Kalkutgi · Solapur (M Corp.), SolapurP52600004936· 43.2% built
- SHANTAI HERITAGE8.6 yr overdueVINOD TUKARAM ADASKAR · Haveli, PuneP52100007237· 90.9% built
- PRABHU SPARSH8.6 yr overduePACIFIC HOUSING CORPORATION · Nashik, NashikP51600006443· 90.9% built
- Lamer Solitaire8.6 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000004491· 89.1% built
- SOLANKAR8.6 yr overdueZIRALE PATIL DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100005879· 80% built
- JANAI MALAI RESIDENCY8.6 yr overdueA AND A VENTURE · Kodoli (CT), SataraP52700014050· 62.7% built
- MAYUR VIHAR APARTMENT8.6 yr overdueHERAMB BUILDERS AND DEVELOPERS · Gadhinglaj, KolhapurP53000013377· 83.6% built
- PALAVA VIENTO A to D8.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000342· 81.8% built· 3 complaints
- Elanza8.6 yr overdueA R Constructions · Ward GSouth, Mumbai CityP51900000604· 81.8% built
- Ashok Nirvaan Villa 438.6 yr overdueTruewin Realty Limited · Lonavala (M Cl), PuneP52100009630· 81.8% built
- Gyan Kutir8.6 yr overdueSungreens Corp · Borivali, Mumbai SuburbanP51800006548· 90.9% built
- ABHISHEK PLAZA8.6 yr overdueAJAYSINH VITTHALRAO DESAI PROMOTERS AND DEVELOPER · Sykes Extension, KolhapurP53000001964· filed Dec 2017 → now Mar 2018· 81.8% built
- AMRUT YOG8.6 yr overdueSAVITA BUILDERS AND DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000007065· 72.9% built
- AADITYA HEIGHTS8.6 yr overdueANAND DEVELOPERS · Pune (M Corp.), PuneP52100001408· 49.1% built
- Skyline wealthspace Wing C2 3 to 8 floors8.6 yr overdueSymphony · Kurla, Mumbai SuburbanP51800004870· 90.9% built
- THAIS RESIDENCY8.6 yr overdueMERCHANT CONSTRUCTIONS PVT. LTD. · Andheri, Mumbai SuburbanP51800011454· filed Dec 2017 → now Mar 2018· 70.5% built· 6 complaints
- A-2 MARIGOLD8.6 yr overdueMUKTA DEVELOPERS · Thane, ThaneP51700003734· 84.5% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.