RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 5 of 61
- Malwani Sea View CHS LTD8.6 yr overdueMalwani Sea View CHS LTD · Borivali, Mumbai SuburbanP51800012674· 90.9% built
- Sanvi Arcade8.6 yr overdueSantosh Dattatraya Kalkutgi · Solapur (M Corp.), SolapurP52600004936· 43.2% built
- Vasundhara Prime8.6 yr overdueVasundhara Prime · Narsoba Nagar, SataraP52700002041· 81.8% built
- Lamer Solitaire8.6 yr overdueLAMER DEVELOPERS · Panvel, RaigarhP52000004491· 89.1% built
- UNITY GARDEN8.6 yr overdueUNITY LAND DEVELOPERS · Palghar, PalgharP99000007688· 51.4% built
- S S PARK IST PHASE8.6 yr overdueS S DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500012611· 84.1% built
- NIRMITI LIFESPACE8.6 yr overdueNIRMITI LIFESTYLE · Nashik, NashikP51600008064· 81.8% built
- VENKATESH RESIDENCY8.6 yr overdueTIRUPATI BUILDERS AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500003513· 87.3% built
- SHIVKRUPA8.6 yr overdueANANT ARJUN MADHAVI · Thane, ThaneP51700013028· 36.4% built
- SHYAM VIHAR8.6 yr overdueKRISHNA DEVELOPERS · KATRAJ, PuneP52100012911· 81.8% built
- Anushree Apartment8.6 yr overdueRavi Mahajan ( HUF ) · Nashik, NashikP51600003905· 90.9% built
- PALAVA VIENTO A to D8.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000342· 81.8% built· 3 complaints
- GOLDEN NEST8.6 yr overdueAZIZ MEHBOOB BAGWAN · Baramati (M Cl), PuneP52100006554· 72.7% built
- SHRADDHA ORCHID AVENUE8.6 yr overdueSHRADDHA LANDMARK PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800012384· filed Dec 2017 → now Apr 2018· 89.5% built· 1 complaint
- OM APPARTMENT8.6 yr overdueVijay Kashinath Chilekar · Ratnagiri, RatnagiriP52800004555· 63.6% built
- Shaswat Residency8.6 yr overdueShaswat Realty · Kurla, Mumbai SuburbanP51800008668· 44.5% built
- Kalyani Classic8.6 yr overdueBhagwan pandurang Ghadge · Aurangabad (M Corp.), AurangabadP51500006528· 63.6% built
- UNITY RESIDENCY8.6 yr overdueDHANRAJ BHAGWANSING KHOT · Junnar, PuneP52100001016· 86.4% built
- VISION WOODS 1 PHASE II8.5 yr overdueSHUBBAN REALTORS · Jambhul, PuneP52100007352· filed Mar 2018 → now Apr 2018· 87.2% built
- SAI VISHWA8.5 yr overdueEKNATH BHAU SHINDE · Rajuri, PuneP52100003169· 90.5% built
- Priyadarshan8.5 yr overdueGangotree Greenbuild · Kothrud, PuneP52100003716· 90.9% built
- UMIYA ARCADE WING A AND B8.5 yr overdueUMIYA CONSTRUCTION COMPANY · Titwala, ThaneP51700002949· 60.9% built
- INDRAYANIIRA8.5 yr overdueSAUBHAGYA DEVELOPERS · PUNE NASHIK HIGHWAY, PuneP52100014863· 72.7% built
- Nidhi Palace8.5 yr overdueBhagawati Construction · Palghar, PalgharP99000004975· 50% built
- RATTAN GALAXY8.5 yr overdueRATTAN PROPERTIES AND PROJECTS PRIVATE LIMITED · Ambarnath, ThaneP51700003240· 83.6% built
- SHRADDHA HEIGHTS8.5 yr overdueSHRADDHA CONSTRUCTIONS · Thane, ThaneP51700008034· 39.5% built
- LODHA BELMONDO SAWGRASS B8.5 yr overdueLodha Developers Limited · Gahunje, PuneP52100000221· 81.8% built
- Yashwin Jeevan8.5 yr overdueVilas Javdekar & Sanjeevani Developers LLP · Sus, PuneP52100000011· 90.9% built
- SARASWATI CASTLE8.5 yr overdueBHUMIKA DEVELOPERS · Kalyan, ThaneP51700004428· 75.9% built
- Ujwal Paradise8.5 yr overdueUjwal Fine Homes · Dhayari (Part), PuneP52100000768· 90.9% built
- GAJANAN KRUPA8.5 yr overdueGAJANAN DEVELOPERS · Nashik, NashikP51600005519· 90.5% built
- AMRUTYOG HOMES8.5 yr overdueDARRVESH ASSOCIATES · PUNE, PuneP52100014551· 25.5% built
- Sai Crystal8.5 yr overdueShraddha Corporation · Ambarnath(M Cl), ThaneP51700012359· filed Dec 2017 → now Apr 2018· 90.9% built
- THE REGENT PARK8.5 yr overdueKAMDHENU INFRASTRUCTURE · PUNE, PuneP52100003421· filed Mar 2018 → now Apr 2018· 92.9% built
- SUMMERSET8.5 yr overdueNEO HOUSING AND INFRASTRUCTURE DEVELOPMENT LIMITED · Borivali, Mumbai SuburbanP51800008467· filed Dec 2017 → now Apr 2018· 88.6% built
- Mellorea8.5 yr overdueNirman Developers · Pimpri Chinchawad (M Corp.), PuneP52100012994· 77.3% built
- PADMAPRABHA CO OP HSG SOCIETY8.5 yr overdueSHREE MAHAVEER ENTERPRISES · SHIRGAON BADLAPUR, ThaneP51700015031· 90.9% built
- Rajesh Presidency8.5 yr overdueSAI SHRI HOME MAKERS · Ulawe, RaigarhP52000011010· 88.2% built· 4 complaints
- BALAJI HEIGHTS8.5 yr overdueSHREE BALAJI REALITY · Thane, ThaneP51700004645· 90.9% built
- DHAVLGIRI8.5 yr overduePERFECT BUILDERS · Ambarnath(M Cl), ThaneP51700012227· 53.3% built
- SANJAY VILLA8.5 yr overdueSAI DUTTA ENGINEERS & BUILDERS · Tasgaon (M Cl), SangliP53100005772· 72.7% built
- Const.378 LIG,331MIG,154HIG T.8.5 yr overduePune Housing and Area Development Board Pune · Haveli, PuneP52100009644· 98.5% built· 1 complaint
- ARIHANT COMPLEX8.5 yr overdueINDRANEEL SHANTARAM TAMBE · Otur, PuneP52100014213· 52.7% built
- THARWANI SOLITAIRE PHASE I8.5 yr overdueANIL HARDASMAL THARWANI · Kalyan, ThaneP51700005630· 60.4% built
- SHUBH AARAMBH8.5 yr overduePACIFIC CONSTRUCTION & DEVELOPERS · Badlapur (M Cl), ThaneP51700012478· 50% built
- SHASHWAT SANKUL8.5 yr overdueSAI SMARAN CONSTRUCTION · Bopele, RaigarhP52000007561· 68.6% built
- GAYATRI PARK8.5 yr overdueVIKRAM BUILDERS · Thane, ThaneP51700010528· filed Dec 2017 → now Apr 2018· 90.9% built· 1 complaint
- Trimurti8.5 yr overdueSugee Developers Pvt Ltd · Ward GNorth, Mumbai CityP51900004360· 90.9% built
- Imperial Classic8.5 yr overdueStar Builders · Vasai, PalgharP99000000898· 50% built
- JAI GOPI KRISHNA CHSL8.5 yr overdueNav Durga Construction Company · Kurla, Mumbai SuburbanP51800006482· filed Dec 2017 → now Apr 2018· 90.9% built
- THARWANI ARIANA PHASE II8.5 yr overdueANIL HARDASMAL THARWANI · Ambarnath, ThaneP51700006127· 51.8% built
- SHIV DRISHTI8.5 yr overdueSHIVKRUPA ENTERPRISES · Karanjade, RaigarhP52000003991· 77.7% built
- Walchand Nagar - 28.5 yr overduePRAKASH HAMIRMAL JAIN · Thane, ThaneP51700009826· 56.4% built
- Desai Enclave8.5 yr overduePrakash Vasudev Desai · Chiplun (M Cl), RatnagiriP52800013051· 89.1% built
- DLH METROVIEW8.5 yr overdueDEV LAND & HOUSING PRIVATE LIMITED · ANDHERI WEST, Mumbai SuburbanP51800005170· 81.8% built· 1 complaint
- SHIV ASHIRWAD8.5 yr overdueSHIVKRUPA ENTERPRISES · Karanjade, RaigarhP52000010827· 72.5% built
- KALPATARU APPARTMENT8.5 yr overdueVIVEK NARENDRAKUMAR CHAWARE · Bhilkheda, WashimP50200013517· 77.3% built
- Harshail Dhanuka Residency8.5 yr overdueHARSHMAAN CONSTRUCTION · Andheri, Mumbai SuburbanP51800000368· 81.8% built
- STATUS POINT8.5 yr overdueJOSHI ZAWAR DEVELOPERS & BUILDERS · Haveli, PuneP52100001237· filed Dec 2017 → now Apr 2018· 90.9% built
- AASHA RESIDENCY8.5 yr overduePITER SHAMUWEL GHATAGE · Miraj, SangliP53100015072· 21.4% built
- TULSI CORNER8.5 yr overdueMAHADEV LIFESPACES · Ulawe, RaigarhP52000003668· 80.9% built
- PALAVA VISTA A to D8.5 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000395· 81.8% built· 3 complaints
- SKY HEIGHTS8.5 yr overduePRAY DEVELOPERS · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000040· 90.9% built
- PARVATI AVENUE8.5 yr overdueR D Realtors · Panvel, RaigarhP52000005819· 90.9% built
- Pushpak8.5 yr overdueA R Constructions · Karanjade, RaigarhP52000001781· 90.9% built
- VANKVANIS BLISS8.5 yr overdueRahul Suresh Vankvani · Ulawe, RaigarhP52000011609· 3.6% built
- SEA STAR8.5 yr overdueRAJESH AND DSOUZA ASSOCIATES · Ulawe, RaigarhP52000011974· 86.8% built· 4 complaints
- KRISHNA PARADISE8.5 yr overdueKRISHNA BUILDER AND DEVELOPERS · Kasar Amboli, PuneP52100005062· 64.5% built
- RIDDHI SIDDHI TOWER A BUILDING8.5 yr overdueR R LUNKAD BUILDERS AND PROMOTERS · CHARHOLI, PuneP52100002304· 90.9% built
- EXCELLENCE RESIDENCY8.5 yr overdueEXCELLENCE INFRA · Panvel, RaigarhP52000005743· 69.1% built
- REDEVELOPMENT OF SBI EMPLOYEES KANCHAN MRIG CHS LTD.8.5 yr overdueR R CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800003186· 90.9% built
- PARADISE PARK8.5 yr overdueCREATIONPROPERTIES · Sangli Miraj Kupwad (M Corp.), SangliP53100003197· 50% built
- SKYLARK8.5 yr overdueGROUP FOUR DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000010097· 87.7% built
- BUILDARCH OLIVE8.5 yr overdueBUILDARCH LAND DEVLOPERS PVT. LTD. · Ward GNorth, Mumbai CityP51900011900· filed Dec 2017 → now May 2018· 72.7% built
- Sai Pooja8.5 yr overdueValse Gholap Associates · Ambegaon, PuneP52100013314· 72.7% built
- PRABHAT APPARTMENT8.5 yr overdueAB DEVELOPERS · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000005· 53.6% built
- Arihant Complex8.5 yr overdueAdya Constructions · Gandhi Nagar, SolapurP52600014946· 72.7% built
- SABHARI CO-OP HSG SOCIETY8.5 yr overdueSHUBHAM ENTERPRISES · ULWE, RaigarhP52000010782· 90.9% built
- Ekadanta8.5 yr overdueKelkar Developers · Pune (M Corp.), PuneP52100001006· 90.9% built
- BHOSALE DAFFODIL8.5 yr overdueBHOSALE HOMES · Ulawe, RaigarhP52000005903· 75.5% built
- RAVI DARSHAN8.5 yr overdueRAVI DEVELOPERS · Badlapur (M Cl), ThaneP51700011461· 66.4% built
- SAMARTH HEIGHTS8.5 yr overdueSAMARTH VASTUPURTI · Aurangabad (M Corp.), AurangabadP51500012554· 78.6% built
- NEEL VIHAR WING-B8.4 yr overdueNeel Gagan Developers · Nagpur (M Corp.), NagpurP50500008240· 90.9% built
- WEEKENDER BIRDS VIEW8.4 yr overdueNAMRATA DEVELOPERS PVT. LTD · Talegaon Dabhade (M Cl), PuneP52100001626· 90.9% built
- 219 Boat Club8.4 yr overdueMERINT DEVELOPERS PVT LTD · Mumbai City, Mumbai CityP51900010179· 84.5% built
- NILGIRI8.4 yr overdueSHIVAM DEVELOPER · Ambarnath, ThaneP51700003872· 72.7% built
- SAMARTH SRUSHTI8.4 yr overdueSWAMI SAMARTH DEVELOPERS · Wadagaon (CT), PuneP52100012037· 89.5% built
- GLORIS RESIDENCY8.4 yr overdueSahakar Developers · Borivali, Mumbai SuburbanP51800003895· 90.9% built
- RIDDHI SIDDHI8.4 yr overdueMotilal Laxminarayan Construction Pvt. Ltd. · Kolhapur (M Corp.), KolhapurP53000003011· 98.8% built
- LAKSHMI RESIDENCY8.4 yr overdueBABASAHEB NEMGONDA PATIL · Sangli Miraj Kupwad (M Corp.), SangliP53100008264· 46.8% built
- SHRI CHATRAPATI SHIVAJI MAHARAJ VYAPARI SANKOOL8.4 yr overdueBORSE BROTHERS ENGINEERS AND CONTRACTORS PRIVATE LIMITED · Dhule (M Corp.), DhuleP49800009159· 67.3% built
- SILICON TOWER8.4 yr overdueSHREE RADHAKRISHNA DEVELOPER · Ambarnath, ThaneP51700004184· 51.8% built
- Shams Enclave8.4 yr overdueZhakirhussain Shamshuddin Bargir · Morewadi (CT), KolhapurP53000009172· 86.4% built
- Gagangiri Arcade8.4 yr overdueAKRUTI ASSOCIATES · Kalyan, ThaneP51700003151· 84.8% built
- SAI VIHAR PHASE -28.4 yr overdueMANGALMURTI CONSTRUCTIONS · Ahmadnagar (M Corp.), AhmednagarP52200006014· 54.5% built
- SURYA RESIDENCY8.4 yr overdueSURYAPUTRA DEVELOPERS · Junnar, PuneP52100012477· 90.9% built
- SAINATHVILLA Phase II8.4 yr overdueSainath Builders & Developers · Sundarwadi, AurangabadP51500011537· 93% built
- NANDRAJ NAGARI TYPE E8.4 yr overdueSWARAJ DEVELOPERS · Badlapur (M Cl), ThaneP51700009908· 81.8% built
- Kohinoor Apartment8.4 yr overduePATRICK FRANCIS ALMEIDA · Vasai, PalgharP99000008551· 90.9% built
- CRYSTAL PALLAZO8.4 yr overdueSAURABH CONSTRUCTION · Vasai, PalgharP99000009609· 90.9% built
- Anand Sagar Enclave8.4 yr overdueVPA Developers · Kalyan, ThaneP51700002701· 54.5% built
- KASTURI NAGAR8.4 yr overdueSKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD. · Gotal Panjari, NagpurP50500002773· 70.1% built
- 64 LIG, 80 MIG, 16HIG and 20 Shops at Sr. No. 491, Res. No. 23 Part, Vengurla, Dist. Sindhudurg8.4 yr overdueMAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY · Andheri, Mumbai SuburbanP51800002323· 69.3% built
- MOTIRAM PRIVILEGE8.4 yr overdueVANITA ENTERPRISES · Ambarnath, ThaneP51700003347· 90.9% built
- SAI NIRMAL APPARTMENT8.4 yr overdueSAMRUDDHI CONSTRUCTION · Nashik, NashikP51600004394· 47.7% built
- Parijat Plaza Type B8.4 yr overdueM/s Parijat Constructions · Badlapur (M Cl), ThaneP51700010993· 80% built
- PEARL HAZELINE8.4 yr overdueCHANDIWALA ENTERPRISES · Andheri, Mumbai SuburbanP51800003301· 90.9% built
- NAKSHTRA PLAZA8.4 yr overdueSHARVARI BUILDERS & DEVELOPERS · Pen (M Cl), RaigarhP52000011253· 50% built
- Ratnagiri Residency8.4 yr overdueAAKAR CONSTRUCTIONS AND DEVELOPERS · Nachane (CT), RatnagiriP52800014049· 90.9% built
- SHRIKRISHNA HERITAGE8.4 yr overdueSHRIKRISHNA VENTURES · Palghar, PalgharP99000009732· 48.2% built
- Building C - D8.4 yr overdueShreenath Constructions · Aurangabad (M Corp.), AurangabadP51500009104· 90.9% built
- Unnati8.4 yr overdueSangeet Changediya · Prabhat Road, PuneP52100014558· 88.6% built
- PRAMUKH DARSHAN8.4 yr overduePRAMUKH ENTERPRISES · Dhamote, RaigarhP52000010357· 90.9% built
- kasturi Apt8.4 yr overdueShruti Shripad Kulkarni · NARHE, PuneP52100001009· 99.5% built· 2 complaints
- TROPICAL LAGOON - 4 -JACARANDA8.4 yr overdueSOHAM ESTATES · Thane, ThaneP51700008485· 64.1% built· 23 complaints
- KOOL BREEZE PHASE II8.4 yr overdueABHISHEK SHELTERS LTD · Badlapur (M Cl), ThaneP51700010400· 84.5% built
- Shivkripa Residency8.4 yr overdueRohit Developers · Thane, ThaneP51700010093· 77.3% built
- Mahavir Solitaire8.4 yr overdueInfinity Construction Co. · Kurla, Mumbai SuburbanP51800000404· 78.6% built
- BHARAT RESIDENCY8.4 yr overdueSHIVSAI BUILDERS & DEVELOPERS · KLAYAN, ThaneP51700010262· 51.4% built
- LIBERTY NIWAS8.4 yr overdueSHRISHTI BUILDCON · Nashik, NashikP51600003961· 90.9% built
- OM SAI VIHAR8.4 yr overdueJai Mahalaxmi Enterprises · Manda, ThaneP51700003493· 87.3% built
- SAI SHRUSTI8.4 yr overdueSAI ENTERPRISES · Mahad (M Cl), RaigarhP52000008583· 60% built
- Malhar Heights8.4 yr overdueNavnath Baban Gawali · Haveli, PuneP52100012854· 27.9% built
- PRATIMA8.4 yr overdueKARBHARI UTTAMRAO MANTE · Baner, PuneP52100013630· 90.9% built
- AARADHYA RESIDENCY8.4 yr overdueM S GROUP · Zadgaon CT, RatnagiriP52800004581· 60.9% built
- SATU AURA8.4 yr overdueSATU REALTY · Palghar, PalgharP99000009278· 90.9% built
- VARAD RESIDENCY8.4 yr overdueGAJANAN MORESHWAR NILAWAR · Chandrapur (M Cl), ChandrapurP50900009833· 90.9% built
- Snehsparsh8.4 yr overduePushkar Realty · Bhor, PuneP52100011416· 41.8% built
- OM SAVAI NIKETAN8.4 yr overdueSAGAR SUPER STRUCTURES PRIVATE LIMITED · BADLAPUR, ThaneP51700009373· 73.6% built
- GUNDECHA ASTA PHASE I8.4 yr overdueAnaya Infrastructure Pvt. Ltd. · Andheri, Mumbai SuburbanP51800001504· 88.6% built
- SAI PLANET8.4 yr overdueM K ASSOCIATES · Punawale, PuneP52100003320· 90.9% built
- BLUE KEY REALTYS ESCALATE8.4 yr overdueBlue Key Realty · Ulawe, RaigarhP52000003043· 70.6% built
- Vizion Galaxy C8.4 yr overdueVIZION CONSTRUCTION · Junnar, PuneP52100005061· 90.9% built
- Ganesh Park8.4 yr overdueGanesh Developers & Company · AMBEGAON Bk, PuneP52100003030· 44% built
- Kute Sukhvastu8.4 yr overdueKailas Developers And Builders · near PCMC school, PuneP52100007440· 81.8% built
- Venkatesh Joynest Phase 28.4 yr overdueSHREE VENKATESH GROUP · Haveli, PuneP52100000990· 90.9% built
- Plot No 888.4 yr overdueJitesh Bhawarlal Jain · Borivali, Mumbai SuburbanP51800006523· 87.3% built
- Kai. Abasaheb R R Patil Vyapari Sankul8.4 yr overdueBORSE BROTHERS ENGINEERS AND CONTRACTORS PVT LTD · Dhule (M Corp.), DhuleP49800007544· 67.3% built
- BHOSALE TULIP8.4 yr overdueBHOSALE GROUP · Ulawe, RaigarhP52000012566· 78.2% built
- SUKOOL8.4 yr overdueSHREE SIDDHIVINAYAK CONSTRUCTION · Talegaon Dabhade (M Cl), PuneP52100008373· 64.5% built
- DNYANRAJ APPARTMENT8.4 yr overdueNitiraj Vijay Ovhal · Pimpri Chinchawad (M Corp.), PuneP52100011505· 90.9% built
- SHREE MAHALAKSHMI PARK BUILDING NO 18.4 yr overdueSHREE MAHALAXMI HOME MAKERS · Dhamote,Neral, RaigarhP52000010984· 90.9% built
- VEDANT PARK8.4 yr overduePRASAD BABANRAO ANDHALE · Ahmadnagar (M Corp.), AhmednagarP52200008876· 86.4% built
- Hillside Apartment8.4 yr overduePratik Chandrakant Bhide · Talegaon Dabhade (M Cl), PuneP52100011572· 87.8% built
- SAI KANISHK PHASE I8.4 yr overdueOm Sai Infra & Om Sai Group · Thane, ThaneP51700006847· filed Dec 2017 → now May 2018· 90% built· 11 complaints
- KRISHNAI PLAZA8.4 yr overdueNitin Shamrao Patil · Haveli, PuneP52100014765· 97.3% built
- NAKSHATRA RESIDENCY8.4 yr overdueJMD GROUP BUILDERS & DEVELOPERS · Chiplun (M Cl), RatnagiriP52800009936· 62.7% built
- Braj Paradise8.4 yr overdueBraj Developer · Palghar, PalgharP99000006122· 61.8% built
- ASTER A WING RUCHA VATIKA8.4 yr overdueMILAN HOUSING COMPLEX PVT. LTD. · Titwala, ThaneP51700005590· 60.5% built
- Astavinayak Apartment8.4 yr overdueM/s RAJ RIDDHI ASSOCIATES · Palghar, PalgharP99000013684· 40.5% built
- Amrutvel Greens Phase I8.4 yr overdueErande Bhave Associates · Haveli, PuneP52100008225· 68.1% built· 2 complaints
- GLOBAL ARENA8.4 yr overdueDDPL GLOBAL INFRASTRUCTURE PVT. LTD. · Vasai, PalgharP99000006463· filed Mar 2018 → now May 2018· 90% built· 1 complaint
- ROHAN LEHER 2 WING F G H I J8.4 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune (M Corp.), PuneP52100000705· 90.9% built
- GRACE GILGAL8.4 yr overdueSHAJAN RAPPAI VARIKKASSERY · Nagpur (M Corp.), NagpurP50500006343· 84.1% built
- Aadhar Apartment8.4 yr overdueGIRDHAR DHARAMSIBHAI RATHOD · NAGPUR, NagpurP50500015627· 81.8% built
- ASHWA ANNEX8.4 yr overdueASHWAMEDH CONSTRUCTION · Thane, ThaneP51700002512· 90.9% built
- NILKANTH8.4 yr overdueKALPAK DEVELOPERS · kalmath, SindhudurgP52900007897· 81.8% built
- BHUVANESHWAR PLAZA8.4 yr overdueOM BUILDERS · Bhuwaneshwar (CT), RaigarhP52000010401· 80% built
- Vastushilp Exotica8.4 yr overdueM/s Vastushilp Realtors · Shahupuri (CT), SataraP52700002706· 64.1% built
- HARIDEEP SQUARE8.4 yr overdueHARIDEEP DEVELOPERS · Nashik (M Corp.), NashikP51600010848· 90.9% built
- SANJIRI RESIDENCY8.4 yr overdueZUBAIR HAJI BASHIR ASHRAFI · Nagpur (M Corp.), NagpurP50500014322· 15.5% built· 1 complaint
- SHIVSHANKAR KALASH8.4 yr overdueSURESH SHIVSHANKAR SHARMA · Navi Mumbai Panvel Rigardh (CT), RaigarhP52000010959· 90.9% built
- LEENA APARTMENT8.4 yr overdueHeramb Developers · Ambarnath(M Cl), ThaneP51700012362· 50% built
- BORIVALI SAHAKAR NIKETAN8.4 yr overdueAMAR ENTERPRISES · Borivali, Mumbai SuburbanP51800011527· 69.5% built· 1 complaint
- SAI PLATINA8.4 yr overdueSHREE SAI ESTATES · Pimpri Chinchawad (M Corp.), PuneP52100007233· 90.9% built
- JUGAI GARDENS8.4 yr overduePRASHANT MANOHAR DINGANKAR · Rahataghar, RatnagiriP52800006258· 90.9% built
- Virtej Apartment8.4 yr overdueVirtej Virdhaval Ghag · Savarde, RatnagiriP52800008808· 56.4% built
- OM RISHIKESH CHS Ltd8.4 yr overdueRiddhi Siddhi Enterprises · Ambarnath, ThaneP51700005679· 87.3% built
- LAXMI VILLA8.4 yr overdueLAXMIDEVI DEVELOPERS · Borivali, Mumbai SuburbanP51800002675· 90.9% built
- V3 VINAMRA8.4 yr overdueV3 INNOVATORS · MANJARI Bk, PuneP52100004156· 56.8% built
- A WING B WING8.4 yr overdueVISHWATMAK REALTORS LLP · Haveli, PuneP52100005796· 63.6% built
- TANOAK8.4 yr overdueM/s Vanita Developers · Pimpri Chinchawad (M Corp.), PuneP52100006742· 69.1% built
- IDEAL EMBARK8.4 yr overdueTHE IDEAL CONSTRUCTION · SANEGURUJI KOLHAPUR, KolhapurP53000000132· 90.9% built
- Silver Mist C, D Building8.4 yr overdueNIRMAN BUILDCON · LOHGAON, PuneP52100002817· 90.9% built
- Kate pride8.4 yr overdueSagar Mahadev Kate · Jalochi, PuneP52100009632· 90.9% built
- KRISHNA VIHAR8.4 yr overdueKRISHNA SPACE · Bhiwandi, ThaneP51700005020· 90.9% built
- NANDHA RESIDENCY8.4 yr overdueAMIT C THAKUR · Haveli, PuneP52100012200· 90.9% built
- NAMRATA RESIDENCY8.4 yr overdueUTTAM NAGESH ARAGE · Sangli Miraj Kupwad (M Corp.), SangliP53100004879· 81.8% built
- AZAD NAGAR SHUBHAM CHSL8.4 yr overduePRATHAMESH KRUPA BUILDCON PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800006313· filed Dec 2017 → now Jun 2018· 72.7% built
- SAI KAMAL8.4 yr overdueOM SAI KAMAL BUILDERS AND DEVELOPERS · Waluj Mahanagar 1, AurangabadP51500007461· 90.9% built
- SHIVDHARA8.4 yr overdueGEETA BUILDCON · Adgaon, NashikP51600010746· 78.2% built
- Raj Nirman8.4 yr overdueFERRO BUILD · Borivali, Mumbai SuburbanP51800003531· 55.5% built
- Playtor Paud A8.4 yr overduePLAYTOR PAUD LANDMARKS PRIVATE LIMITED · Mulshi, PuneP52100001798· 81.8% built· 1 complaint
- ENIGMA8.4 yr overdueEMERGING LANDMARK REALTY LLP · LOHGAON, PuneP52100014485· 52.2% built
- IMPERIAL TOWER8.4 yr overdueAG CONSTRUCTIONS · MOHAMMADWADI, PuneP52100003986· 54.5% built
- VEDANT8.4 yr overdueMANDAR VASANT DEVARE ·P52100011775· 72.7% built
- Aditi Plaza8.4 yr overdueChintamani Construction · Ambarnath, ThaneP51700001865· 90.9% built
- Sai Sahavas Phase II8.4 yr overdueSai Sampada Lifespaces Private Limited · Halval, SindhudurgP52900008783· 77.3% built
- GLITTERATI8.4 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · Pimpri Chinchawad (M Corp.), PuneP52100006257· 37.4% built
- SILVER OAK8.4 yr overdueAnand Properties · Pimpri Chinchawad (M Corp.), PuneP52100000045· 90.9% built
- DAHLIA8.4 yr overdueHorizon Shelters · Pune (M Corp.), PuneP52100005715· filed Dec 2017 → now Jun 2018· 80% built
- SIDDHIVINAYAK HIGHTS8.4 yr overdueSAI DEVELOPERS · Sangole (M Cl), SolapurP52600014499· 82.8% built
- METRO JAZZ8.4 yr overdueBalaji Realty · mumbay pune expres highway, PuneP52100004070· 88.6% built
- MERIDEAN ASSOCIATES8.4 yr overdueMERIDEAN ASSOCIATES · Kurla, Mumbai SuburbanP51800003813· filed Dec 2017 → now Jun 2018· 81.8% built
- Sarthak Shantiban8.4 yr overdueSarthak & Shanti Associates · NARHE, PuneP52100001780· 81.8% built
- IMPERIAL GOLD8.4 yr overdueUDAYSINH LAXMAN BHUJBAL · Kothrud, PuneP52100010201· 90.9% built
- Antheia A48.4 yr overdueMahindra Lifespace Developers limited · Haveli, PuneP52100000210· 90.9% built
- OLIVE8.4 yr overdueDINSHA BUILDERS AND DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700008260· 56.8% built
- SND SIGNATURE8.4 yr overdueS N DAMANI INFRA PRIVATE LIMITED · ULWE, RaigarhP52000008586· 90.9% built
- HARI VATIKA8.4 yr overdueDHARAN INFRA-EPC LIMITED · SANSARI, NashikP51600000220· 74.5% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.