All RERA projects
🏗️
Under construction

Puneet Kanchanganga Phase One Floor 0 to Floor 25

MahaRERA P51700011319High risk

by Puneet Developers

211 Hissa No 5, Thane, 400606

Official record
Dec 2020
Possession
90.9%
Built
3
Complaints
0
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 211 Hissa No 5, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Thane (Ghodbunder belt)Mid-income

A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Puneet Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700011319
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally December 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.