All RERA projects
🏗️
Under construction

Puneet Sanjivani Phase 1 Floor 0 to Floor 16

MahaRERA P51800015397High risk

by Puneet Developers

CTS no 351 PT, Kurla, 400083

Official record
Dec 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Satellite view of this address

Where it is · CTS no 351 PT, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Puneet Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800015397
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.