Under construction
RELIABLE UTKARSH C , D WING
MahaRERA P99000008640High risk
by RELIABLE PRISM CONSTRUCTION CO.
S.No.155,pt-1, VASAI, 401208
Post your property hereOwn or renting out a unit in RELIABLE UTKARSH C , D WING? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in VASAI come to you.
Jul 2022
Possession
42.5%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jun 2019, now proposed Jul 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 42.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2022 per the RERA filing.
Satellite view of this address
Where it is · S.No.155,pt-1, VASAI
Promoter
Builder profile
RELIABLE PRISM CONSTRUCTION CO.
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000008640
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2022originally June 2019
- Construction
- 42.5% complete
- Units sold
- 0 of 0
Similar projects in VASAI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
DEEP SKY F WING
VASAIPoss. December 2028
AAI CHANDIKA HILLS
VASAI99.9% builtPoss. September 2026
CANARY-WING C
VASAI91% builtPoss. July 2027
KAILASH TOWER
VASAI90.9% builtPoss. December 20245 complaints
ORNATE HEIGHTS PHASE I
VASAI90.5% builtPoss. February 2027
ROYAL RESIDENCY
VASAI89.5% builtPoss. December 2025
BLOSSOM
VASAI88.4% builtPoss. April 2028
ASMI ENCLAVE
VASAI86.4% builtPoss. April 2027
Keep exploring
Where this project sits, who built it, and how VASAI compares.
In VASAI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.