Rustomjee Virar Avenue L1-L2 and L4 Wing K
by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
pt of Avenue L1 L2 L4 being pt of larger layout being sy no 5 5B 5D 5F 5G of village Dongre, Avenue L4, 401303
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 50%.
- Promised amenities not started. Landscaped Garden, Sports / Jogging are at 0% build with possession due Sept 2024 per the RERA filing.
Where it is · pt of Avenue L1 L2 L4 being pt of larger layout being sy no 5 5B 5D 5F 5G of village Dongre, Avenue L4
Area guide
What it's like to buy in Avenue L4
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000020235
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2024originally September 2023
- Construction
- 50% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Avenue L4 compares.
In Avenue L4
The developer
Research