High risk
  • Possession delayed ~1 yr. Originally promised Mar 2026, now proposed Jul 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · 52,52/1TO52/26, Borivali

Promoter

Builder profile

Builder
Gurukrupa Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Space Moulders

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800034270
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2026
Construction
90.6% complete
Units sold
69 of 219

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.