High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 0%.
  • Promised amenities not started. Gymnasium, Landscaped Garden are at 0% build with possession due Jun 2025 per the RERA filing.
Satellite view of this address

Where it is · 871-3-1-1 PLOT NO 6-7-10-11, OPP GAJANAN MAHARAJ MANDIR

Area guide

What it's like to buy in OPP GAJANAN MAHARAJ MANDIR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHREEJI INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SUMIT KUMATH K KUMAT

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51600030248
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
0% complete
Units sold
0 of 33

Keep exploring

Where this project sits, who built it, and how OPP GAJANAN MAHARAJ MANDIR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.