High risk
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 55.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2018 per the RERA filing.
Satellite view of this address

Where it is · 71/1/4 Plot No 12 and 13, Varale

Area guide

What it's like to buy in Varale

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MANAS DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100004755
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018originally December 2017
Construction
55.4% complete
Units sold
0 of 0

Similar projects in Varale

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Varale compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.