Vaarivana Phase A - 1
by Sanjivani Integrated Township LLP
Part of Gat No 339, 342, 343, 361, 362, 363, 364, 365, 366, 367, 371, 372, 373, 374, 375, 376, 377, 378, 379, 380, 424 of village Aadhe, Urse, 410506
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Mortgaged to a lender (₹275 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹275 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
Where it is · Part of Gat No 339, 342, 343, 361, 362, 363, 364, 365, 366, 367, 371, 372, 373, 374, 375, 376, 377, 378, 379, 380, 424 of village Aadhe, Urse
Area guide
What it's like to buy in Urse
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100018391
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2025
- Construction
- 79.3% complete
- Units sold
- 276 of 284
Similar projects in Urse
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Urse compares.
In Urse
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.