Under construction

Vaarivana Phase B-1

MahaRERA P52100050520High risk

by Sanjivani Integrated Township LLP

Part of Gat No-130, 131, 132, 133, 134, 135, 136, 137, 138, 139, 140, 141, 142, 143, 144, 146, 153, 156 of village-Urse & Part of Gat No-409, 410, 411 of Village-Aadhe, Mawal, 410506

Official record
Mar 2027
Possession
37.8%
Built
1
Complaints
73
Units
High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • Mortgaged to a lender (₹275 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹275 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 37.8%.
Satellite view of this address

Where it is · Part of Gat No-130, 131, 132, 133, 134, 135, 136, 137, 138, 139, 140, 141, 142, 143, 144, 146, 153, 156 of village-Urse & Part of Gat No-409, 410, 411 of Village-Aadhe, Mawal

Area guide

What it's like to buy in Mawal

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Sanjivani Integrated Township LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100050520
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
37.8% complete
Units sold
46 of 73

Similar projects in Mawal

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mawal compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.