High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.1%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2020 per the RERA filing.
Satellite view of this address

Where it is · GAT NO 124-PART - OLD 121 , Mulshi

Promoter

Builder profile

Builder
M/S. AVIOR MAJESTIQUE PROPERTIES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100001569
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
90.1% complete
Units sold
0 of 0

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mulshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.