Under construction
VANALIKA
MahaRERA P52100001569High risk
by M/S. AVIOR MAJESTIQUE PROPERTIES
GAT NO 124-PART - OLD 121 , Mulshi, 412108
Post your property hereOwn or renting out a unit in VANALIKA? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mulshi come to you.
Sept 2020
Possession
90.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.1%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2020 per the RERA filing.
Satellite view of this address
Where it is · GAT NO 124-PART - OLD 121 , Mulshi
Promoter
Builder profile
M/S. AVIOR MAJESTIQUE PROPERTIES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100001569
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 90.1% complete
- Units sold
- 0 of 0
Similar projects in Mulshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PLOT NO. B-01 TO B-21 VIVA,PIRANGUT,PUNE
MulshiPoss. November 2026
Ecoville Iris
MulshiPoss. December 2019
Estrella, Viva, Pirangut
MulshiPoss. April 20271 complaint
Blue Ridge-The Promenade
MulshiPoss. December 20301 complaint
Kekarav Phase II
MulshiPoss. March 2028
Kekarav Phase III
MulshiPoss. December 2026
THE COVE
MulshiPoss. January 2028
Kohinoor Westview Reserve
MulshiPoss. December 20282 complaints
Keep exploring
Where this project sits, who built it, and how Mulshi compares.
In Mulshi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.