VANALIKA - PARADISE - PHASE - III-3A
by M/S. AVIOR MAJESTIQUE PROPERTIES
GAT NO. 124 -PART, PAUD ROAD, 412108
- Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.
Where it is · GAT NO. 124 -PART, PAUD ROAD
Area guide
What it's like to buy in PAUD ROAD
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P52100019038
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2024
- Construction
- 90.9% complete
- Units sold
- 162 of 166
Similar projects in PAUD ROAD
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how PAUD ROAD compares.
In PAUD ROAD
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.