- Possession delayed ~9 yrs. Originally promised Dec 2023, now proposed Dec 2032 per the RERA filing.
Where it is · NEW 377/1-7 OLD 684/1-7 NEW 212/3PT-3PT-2-4-5 OLD 553/3 PT/3PT 2-4-5 , Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The city's northern value frontier, densifying fast.
- Growth drivers:
- Metro 9 extension, spillover from Borivali pricing.
- Who buys here:
- First-time buyers stretching for a 1–2 BHK.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700003994
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2032originally December 2023
- Construction
- 42.3% complete
- Units sold
- 2 of 28
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.