RERA projects past their possession deadline
11,767 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 20 of 59
- Shreemanyogi6.6 yr overdueMORNING STAR REALITIES · Pimpri Chinchawad (M Corp.), PuneP52100002250· filed Dec 2018 → now Dec 2019· 86.4% built
- AARIV EXOTICA6.6 yr overdueIK ONKAR CONSTRUCTIONS · BALEWADI, PuneP52100009605· 84.5% built
- HIra Heights6.6 yr overdueMayura Promoters And Developers Pvt. Ltd. · Solapur (M Corp.), SolapurP52600003853· 90.9% built
- SAVALI TOWER6.6 yr overduesavali developers · OPP RELIANCE PETROL PUMP SASVAD, PuneP52100015927· 49.1% built
- Morphic Arham6.6 yr overdueMorphic Developers · Mukundnagar, PuneP52100003108· filed Jun 2018 → now Dec 2019· 90.9% built
- RAKHI TOWER PHASE 16.6 yr overdueWESTERN DEVELOPMENTS · Borivali, Mumbai SuburbanP51800005504· 80.7% built· 1 complaint
- KUL Utsav Phase I -Building F6.6 yr overdueKumar Builders · Pune, PuneP52100009849· 90.9% built
- Morya Residency Phase II6.6 yr overdueABHAY LAXMANRAO KULKARNI · Jalna (M Cl), JalnaP51400002209· 90.9% built
- SHIVDARSHAN APARTMENT6.6 yr overdueSAHYADRI BUILDCON · Nashik (M Corp.), NashikP51600010151· 90.9% built
- GIRIRAJ APARTMENTS6.6 yr overdueMETRO DWELLERS PRIVATE LIMITED · MULUND WEST, Mumbai SuburbanP51800012045· filed Dec 2018 → now Dec 2019· 55.5% built· 1 complaint
- DECCAN RESIDENCY6.6 yr overdueDECCAN DEVELOPERS · NEAR RAM MANDIR, SangliP53100004556· 81.8% built
- WOODLAND6.6 yr overdueSHAURYA INFRA BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700005808· filed Dec 2018 → now Dec 2019· 90.9% built
- HARI AAKRUTI6.6 yr overdueKARDA BUILDCON PRIVATE LIMITED · Kathe Galli, NashikP51600000423· filed Dec 2018 → now Dec 2019· 90.9% built· 4 complaints
- VASANT VIHAR6.6 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019139· 81.8% built
- Unicorn Nest I6.6 yr overdueUnicorn Developers · Sangamner, AhmednagarP52200012510· filed Dec 2018 → now Dec 2019· 90.9% built
- SAHARA PEARL6.6 yr overdueSAHARA BUILDCON · Sasvad (M Cl), PuneP52100002551· 90.9% built
- GAJANAN SMRUTI6.6 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019112· 81.8% built
- PRIME VILLA6.6 yr overdueLEERA RAMJI ARETHIYA · Panvel, RaigarhP52000004578· 63.6% built
- AANGAN VILLA6.6 yr overdueSHREE KHODIYAR DEVELOPERS · Uran, RaigarhP52000004845· 81.8% built
- KSP RESIDENCY6.6 yr overdueKRISHNAT SHAHU POWAR · Maruti mandir, RatnagiriP52800012180· 88% built
- The Back Water Residency phase I - D Building6.6 yr overdueLNK PROJECTS Through Proprietor Mr Narayan Baburao Khasnis · Haveli, PuneP52100019828· 90.9% built
- Vishwa Abha6.6 yr overdueM/s. Vishwa Green Realtors Private Limited · Uran, RaigarhP52000003732· filed Dec 2018 → now Dec 2019· 90.9% built
- SHREE OM RESIDENCY6.6 yr overduePRABHAT RAMRAO DESAI · Sangli Miraj Kupwad (M Corp.), SangliP53100009550· filed Dec 2018 → now Dec 2019· 81.8% built
- ARCHWAY6.6 yr overdueAAB ASSOCIATES · Pune (M Corp.), PuneP52100009345· filed Dec 2018 → now Dec 2019· 90.9% built
- HARISHCHANDRA RESIDENCY6.6 yr overduePRATAP NARAYAN DESHMUKH · AMRAVATI, AmravatiP50300013119· 81.8% built
- SHIVANAND APARTMENT6.6 yr overdueDEAL CONSTRUCTION · Nashik, NashikP51600003142· 90.9% built
- PARVATI ARCADE6.6 yr overdueCHANDRAKAUMUDI CONSTRUCTION · Mahad, RaigarhP52000001957· 90.9% built
- ABHISHEK FLORIDA- ORCHID6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004263· 90.9% built
- KUL COURT6.6 yr overdueKumar Builders Mumbai Realty Pvt Ltd · Mumbai, Mumbai SuburbanP51800009338· filed Dec 2018 → now Dec 2019· 76.2% built· 2 complaints
- SAILEELA6.6 yr overdueDENNIS JAMES FERNANDES · KHALAPUR, RaigarhP52000010923· filed Dec 2018 → now Dec 2019· 86.4% built
- SHIVALAY APARTMENT6.6 yr overdueShivalay Developers · Ulawe, RaigarhP52000009972· 90.9% built
- DIGAMBAR SADAN6.6 yr overduemsdevelopers · Nanded Waghala (M Corp.), NandedP51100006594· 32% built
- APURVA6.6 yr overdueSHARAD SHAMRAO SAWANT · NEAR WALCHAND COLLAGE, SangliP53100014495· 90.9% built
- RAJ TOWER6.6 yr overdueJAYBHAVE BUILDERS · RANE NAGAR, NashikP51600011857· filed Dec 2018 → now Dec 2019· 86.8% built· 1 complaint
- SAACHI HEIGHTS6.6 yr overdueVINAYAKUMAR REKHCHAND RATHI · AKOLA, AkolaP50100022672· 90.9% built
- TRINITY CO OP HSG SOC LTD6.6 yr overduePIONEER ENTERPRISES · Kurla, Mumbai SuburbanP51800001462· 99.9% built
- Gulmohar Park A phase 16.6 yr overdueMercury Artharaj Landmarks AOP · Haveli, PuneP52100007126· 42.7% built
- SHIV SAMRUDHI - A WING6.6 yr overdueSHIV DEVELOPERS · Wakad, PuneP52100014369· 81.8% built
- SWAPNASHILP6.6 yr overdueFUTURISTIC HOMES · Wakad, PuneP52100003880· 73.2% built
- ABHISHEK FLORIDA- BLOSSOM6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000008362· 90.9% built
- ABHISHEK FLORIDA- DAFFODILS6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005514· 90.9% built
- SHREE KRISHNA PLAZA6.6 yr overdueSHREE HANUMAN ENTERPRISES · Thakurli, Cholegaon, ThaneP51700014660· 90.9% built· 2 complaints
- PARSHVA AANGAN6.6 yr overdueSONALI MEHUL DOSHI · Uran, RaigarhP51700000724· 37.6% built
- Panvelkar Nisarg Phase-I6.6 yr overduePanvelkar Realty Private Limited · Ambarnath, ThaneP51700004393· filed Dec 2018 → now Dec 2019· 90.9% built
- ABHISHEK FLORIDA- LOTUS6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005376· 90.9% built
- ABHISHEK FLORIDA- MARIGOLD6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004893· 90.9% built
- Sri Gurumangal6.6 yr overdueManisha Vishnu Rane · Nashik, NashikP51600010391· 90.5% built
- MANGALDEEP CHSL.6.6 yr overdueDHARIWAL CONSTRUCTIONS (INDIA) PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800010018· filed Dec 2018 → now Dec 2019· 90.9% built
- LITTLE HEARTS PHASE 26.6 yr overdueSHREEMANGAL VISHHRAM DEVELOPERS · UNDRI, PuneP52100009230· 90.9% built
- JAS LUXURIA , J-16.6 yr overdueASHNAY Developers · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000029· 99.6% built
- Rivaah Regency6.6 yr overdueAjay Nanasaheb Jadhavrao · WAGHOLI, PuneP52100009655· filed Dec 2018 → now Dec 2019· 90.9% built
- NISARGA SPARSH6.6 yr overdueARYA NISARGA PROPERTIES · Mawal, PuneP52100004715· 35.5% built
- ARIHANT ANSHULA6.6 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Navi Mumbai, RaigarhP52000009246· 85.5% built· 1 complaint
- KESHAV APARTMENT6.6 yr overdueGULAB SUREKHA PAWAR · LIC COLONY, LaturP52400016021· 10.5% built
- VAMA PARADISE6.6 yr overdueVAMA LIFESTYLES · VIRAR WEST, PalgharP99000010889· 90.9% built
- Sai Arcade6.6 yr overdueKiran Patel · Jail Road, NashikP51600011987· 76.4% built
- Sri Guruashish6.6 yr overdueVishnu Shankar Rane · Nashik, NashikP51600010609· 90% built
- KAKADE PLAZA PHASE 16.6 yr overdueSuryakant Kakade · Kopare, PuneP52100012132· 93.9% built
- PAYAL CO OP HSG SOC6.6 yr overdueSUFAL ASSOCIATES · PRABHAT ROAD, PuneP52100009888· filed Dec 2018 → now Dec 2019· 81.8% built
- Janaki Complex6.6 yr overduePravin Narayan Lad · Fish Market, RatnagiriP52800017248· 90.9% built
- SKYLON SPACES6.6 yr overdueSAI KRUPA DEVELOPERS · Borivali, Mumbai SuburbanP51800010405· filed Dec 2018 → now Dec 2019· 90.9% built
- ABHISHEK FLORIDA- SUNFLOWER, ROSE, JASMINE6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005897· 90.9% built· 1 complaint
- ARIHANT NANO PEARL6.6 yr overdueSURAJ ANNASAHEB UPADHYE · KUPWAD, SangliP53100015629· 53.6% built
- Suyash Galaxy6.6 yr overdueSejal Developers · Panvel, RaigarhP52000004408· 90.9% built
- COURTYARD6.6 yr overdueYOGESH & YOGESH DEVELOPERS · PASHAN, PuneP52100007218· filed Dec 2018 → now Dec 2019· 51.8% built
- SAMRUDDHI HEIGHTS6.6 yr overdueLAXMAN EKNATH GOMASE · Nashik (M Corp.), NashikP51600013275· 90.9% built
- LODHA ETERNIS SERENA A6.6 yr overdueLODHA DEVELOPERS LIMITED · Andheri, Mumbai SuburbanP51800000294· 90.9% built· 1 complaint
- JAYRAM RESIDENCY6.6 yr overdueJAYRAM BUILDERS AND DEVELOPERS · Nagpur (M Corp.), NagpurP50500014242· 55.4% built
- Aurum6.6 yr overdueSanjeevkumar Harakchand Kankariya · Aurangabad (M Corp.), AurangabadP51500001970· 74.5% built
- KALYANI SAI ENCLAVE6.6 yr overdueJ K BUILDERS AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500012465· 59.1% built
- Promenade - The Address6.6 yr overdueWadhwa Residency Pvt Ltd · Kurla, Mumbai SuburbanP51800000201· 90.9% built· 21 complaints
- MANORAMA CHS6.6 yr overdueRUPA PROPERTIES & SECURITIES PVT. LTD. · Thane, ThaneP51700005251· 90.9% built
- PPRL Mera Ghar - Building E26.6 yr overdueParakh Plexus Realty Ltd. · Jalgaon (M Corp.), JalgaonP49900001778· 50.9% built
- KANHA RESIDENCY6.6 yr overdueEKADANTA SHELTERS · Malkhed, SataraP52700008109· 15.1% built
- SHALOM JOVE6.6 yr overdueCOTTADIYIL ENTERPRISES · Thane, ThaneP51700012851· filed Dec 2018 → now Dec 2019· 90.9% built
- Teerth Technospace 56.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100011316· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- PRABHUKUNJ APPARTMENT6.6 yr overdueTULJAI DEVELOPERS · Yavatmal (M Cl), YavatmalP51000007459· 50% built
- SAPPHIRE6.6 yr overdueJANGID BUILDERS PRIVATE LIMITED · Mira Road East, ThaneP51700020060· 28.4% built
- SHREE CHAMUNDA HEIGHTS6.6 yr overdueSHREE CHAMUNDA REALTORS · Mumbai City, Mumbai CityP51900009861· 58.6% built
- TRILIUM6.6 yr overdueTRIF REAL ESTATE AND DEVELOPMENT LTD · Nagpur (M Corp.), NagpurP50500012878· 77.7% built
- URBANVILLE6.6 yr overdueSAI KRUPA BUILDERS · Kalyan, ThaneP51700005910· 31% built
- SHREERAM MAREEGOLD6.6 yr overdueR.G.DEVELOPERS · LOHGAON, PuneP52100003038· 27.3% built
- SARTHAK HOMES6.6 yr overdueSARTHAK INFRA · NANA MASTER NAGAR, RaigarhP52000008473· 90.9% built· 1 complaint
- CITY VISTA6.6 yr overdueKOLTE-PATIL REAL ESTATE PRIVATE LIMITED · KharadiP52100007612· 63.6% built· 3 complaints
- SWASTIK HEIGHTS6.6 yr overdueMANGALAM DEVELOPER · Ramsheth Thakur International Sports Complex, RaigarhP52000021121· 88.2% built· 1 complaint
- G M HEIGHT6.6 yr overdueGARODIA & MAKWANA DEVELOPERS · Vasai, PalgharP99000005833· filed Mar 2018 → now Dec 2019· 70% built
- KINGSTONE AVENUE PH 16.6 yr overdueSupreme Developers · Pimpale Saudagar, PuneP52100001909· filed Dec 2018 → now Dec 2019· 70.8% built· 2 complaints
- SAI HARMONY NEST6.6 yr overdueSAI KRIPA PROMOTORS & DEVELOPERS · SAICITY, AhmednagarP52200005212· 81.8% built
- SAMARTH CARINA COMMERCIA6.6 yr overdueMAHESH ZUMBARLAL KHINVASARA · NEAR ADITYA BIRLA HOSPITAL, PuneP52100015662· 9.1% built
- BHAGIRTHI APPARTMENT6.6 yr overdueMANOJ YASHWANT MORE · Khedshi, RatnagiriP52800009918· 47.7% built
- SHREE SIDDHIVINAYAK HEIGHTS6.6 yr overdueAJIT KRISHNAN RATNAM · Titwala, ThaneP51700003326· filed Dec 2018 → now Dec 2019· 90.9% built
- ASHWA PLATINUM6.6 yr overdueASHWAMEDH BUILDERS AND DEVELOPERS · Thane, ThaneP51700001143· 59.3% built· 1 complaint
- Xrbia Hinjewadi Road / Riverfront - Ph - 26.6 yr overdueXrbia North Hinjewadi Developers Private Limited · Bebad Ohol, PuneP52100000379· filed Dec 2018 → now Dec 2019· 90.9% built· 7 complaints
- Sangam Solitaire A wing6.6 yr overdueSangam Press Pvt Ltd · Pune (M Corp.), PuneP52100000438· 82.5% built
- PADMAJA RESIDENCY6.6 yr overduePADMA BUILDCON · Nashik (M Corp.), NashikP51600013300· filed Dec 2018 → now Dec 2019· 90.9% built
- PRITHVI RESIDENCY6.6 yr overduePRITHVI BUILD HOMES · Borivali, Mumbai SuburbanP51800009232· filed Dec 2018 → now Dec 2019· 90.9% built
- MADHUKRISHNA CHS LTD6.6 yr overdueBUILT TECH BUILDERS & DEVELOPERS PVT. LTD. · Rahataghar, RatnagiriP52800008814· 66.4% built
- BELLA VISTA6.6 yr overdueLAXMI KESHAV CONSTRUCTIONS AND SHRIKA DEVELOPERS PRIVATE LIMITED · Nagpur, NagpurP50500005466· 90.9% built· 1 complaint
- NANDANVAN PALACE6.6 yr overdueShreenath Developers(AOP) · Santaji Nagar, PuneP52100005286· 90.9% built
- GANESH ATRIA6.6 yr overdueZENITH DEVELOPERS · AMBAD, NashikP51600004173· filed Dec 2018 → now Dec 2019· 60.9% built
- Joy Legend Wing A6.6 yr overdueJAYANT SONI · Andheri, Mumbai SuburbanP51800005022· filed Dec 2018 → now Dec 2019· 70% built· 7 complaints
- HIRA RESIDENCY PHASE II6.6 yr overdueAL-SAAD CONSTRUCTIONS · Thane, ThaneP51700005670· 90.9% built
- K-S Aster6.6 yr overdueKaranje-Surana Constructions Pvt. Ltd. · Solapur (M Corp.), SolapurP52600002267· 90.9% built· 1 complaint
- MATOSHREE YASHODA RESIDANCY6.6 yr overdueDYNESHWAR KESHAVRAO BHOSALE · RAVIVAR PETH, NashikP51600016562· 36.4% built
- KOHINOOR IRIS PARK6.6 yr overdueKohinoor Properties · kalepadal, PuneP52100001617· 81.8% built
- ARIHANT PLAZA6.6 yr overdueARIHANT DEVELOPERS · Thane, ThaneP51700006068· 72.3% built
- MANORATH RESIDENCY PHASE - 26.6 yr overdueKrishnakumar Ramsinh Parmar · Near Lions School, Dadra & Nagar HaveliP49600000013· 84.5% built
- OXY EVOLVE6.6 yr overdueVENKATESH ASSOCIATES · WAGHOLI, PuneP52100000772· 90.9% built
- SAI SHRADDHA6.6 yr overdueBALAJI ENTERPRISES · BOPELE, RaigarhP52000015196· 40.9% built
- REELICON KIAN6.6 yr overdueJKDEVELOPERS · AMBEGAON BK, PuneP52100003028· filed Dec 2018 → now Dec 2019· 54.5% built
- ARPIT6.6 yr overdueTISTA IMPEX PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800004857· 56.8% built
- SIMRAN HEIGHTS6.6 yr overdueNAVRANG HOME MAKERS · Panvel, RaigarhP52000002052· 73.2% built
- KANAKIA WALLSTREET WING A6.6 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000121· 90.7% built· 2 complaints
- NEELKANTH AURA6.6 yr overdueNEELKANTH LIFESPACE LLP · NAVI MUMBAI, RaigarhP52000007335· 88% built
- VICTORY HEIGHTS6.6 yr overduePANCHMUKHI BUILDERS AND DEVELOPERS · Vasai, PalgharP99000005198· filed Dec 2018 → now Dec 2019· 90.9% built· 3 complaints
- Airiana6.6 yr overdueMitesh Lakhamshi Patel · LOHGAON, PuneP52100007161· filed Sept 2018 → now Dec 2019· 25.9% built
- GRACE HEIGHTS6.6 yr overdueGRACE VENTURES · Pune City, PuneP52100009946· 68.6% built
- SHRINATHJI HEIGHTS6.6 yr overdueSHRINATHJI BUILDER AND DEVELOPERS · Nanivali, PalgharP99000012732· 90.9% built· 2 complaints
- Optimus6.6 yr overdueSiddhesh properties · Lahagaon, PuneP52100000803· filed Dec 2018 → now Dec 2019· 38.2% built· 2 complaints
- SHREE SADGURU COMPLEX PHASE I6.6 yr overdueEARTH HOME · Khalapur, RaigarhP52000011306· 90.9% built
- Tulip C Eco6.6 yr overdueAshoka Township (AOP) · Kajikhore, NashikP51600015179· 27.3% built
- ARCH GARDENS I AND II6.6 yr overdueSAI PREM DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700002994· filed Dec 2018 → now Dec 2019· 87.9% built
- RUDRAKSH RESIDENCY6.6 yr overdueMUGDHA SANDEEP BODKE · satpur, NashikP51600012753· 90.9% built
- NEELAYA6.6 yr overdueNAIKNAVARE BUILDCON PVT LTD · TALEGAON, PuneP52100000013· 95.5% built
- KINGSTON COURT6.6 yr overdueMAHALAXMI ENTERPRISES · Vasai, PalgharP99000003618· 70.6% built
- Anmol Nayantara City Two phase 16.6 yr overdueBafna Realtors Pvt Ltd · Karmayogi nagar, NashikP51600001967· filed Dec 2018 → now Dec 2019· 81.7% built
- Teerth Technospace 156.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100007204· filed Dec 2018 → now Dec 2019· 90.9% built
- Mayuresh Residency6.6 yr overdueMAYURESH REALTORS AND DEVELOPERS PRIVATE LIMITED · Sangli Miraj Kupwad (M Corp.), SangliP53100004815· 81.8% built
- Teerth Technospace 46.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100011403· filed Dec 2018 → now Dec 2019· 90.9% built
- Galaxy Orchid6.6 yr overdueGalaxy Constructions · Pune City, PuneP52100008975· 10.8% built
- VAKRATUND HEIGHTS6.6 yr overdueRAVIRAJ BUILDCON · Chandsi, NashikP51600013690· 90.9% built
- Pranjal Residency6.6 yr overdueBalasaheb Sadashiv Murkute · Baner, PuneP52100005273· 81.8% built· 1 complaint
- GANESH AVENUE6.6 yr overdueNERKAR PROPERTIES LLP · Nashik (M Corp.), NashikP51600007654· filed Dec 2018 → now Dec 2019· 69.5% built
- Goolden Woods6.6 yr overdueKirti Construction · Nideban (CT), LaturP52400010216· 78.2% built· 1 complaint
- OAK VIEW6.6 yr overduePM Construction · Thergaon Near PCMC Zonal Office, PuneP52100006090· 94.1% built· 4 complaints
- Omkar Residency6.6 yr overdueSAMARTH DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500013702· 90.9% built
- Panvelkar Estate - Rockford6.6 yr overdueVijay Ramchandra Panvelkar · Ambarnath, ThaneP51700000431· 72.7% built
- FOUR AVENUES6.6 yr overdueIKON CONSTRUCTIONS · Haveli, PuneP52100006853· filed Dec 2018 → now Dec 2019· 90.9% built
- SWEET HOME BUILDING 16.6 yr overdueIPSIT ENTERPRISE · Shirgaon, PalgharP99000009859· 18.2% built
- Akshar Jyot6.6 yr overdueAkshar Enterprises · Near rau hotel, Peth road, NashikP51600018428· 43.6% built
- TULSI ANAND6.6 yr overdueANAND HOMES · Eranjade, ThaneP51700008015· 48.5% built
- NEPTUNE SWARAJYA SECTOR 2 - B166.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700011196· filed Dec 2018 → now Dec 2019· 59.2% built
- Swara Sparsh6.6 yr overdueM/S Chinchwade Avhale Associates · Wakad, PuneP52100008838· 42.3% built
- CHOPDA TWIN TOWER BUILDING B6.6 yr overdueARHUM HILLS-N-LANDS PRIVATE LIMITED · NEAR CHOPDA LAWNS, NashikP51600010586· filed Jan 2019 → now Dec 2019· 90.9% built
- IMPERIUM APARTMENTS6.6 yr overdueKALASH DEVELOPERS ASSOCIATES · nashik, NashikP51600010643· filed Dec 2018 → now Dec 2019· 80% built
- NISARG GREENS - Commercial Phase-I6.6 yr overdueNND Ambernath LLP · Morivali, ThaneP51700016412· 90.9% built
- Shanti Niwas6.6 yr overdueD.G. Patel & Co. · Kurla, Mumbai SuburbanP51800007402· filed Dec 2018 → now Dec 2019· 90.9% built
- Sundaram residency6.6 yr overdueJadhav Enterprises · Tathwade, PuneP52100000907· filed Dec 2018 → now Dec 2019· 81.8% built· 2 complaints
- Chhoriya Residency Nandurbar Phase - 26.6 yr overdueChhoriya and Kela Developers · Nandurbar, NandurbarP49700009502· filed Dec 2018 → now Dec 2019· 50.6% built
- MY RESIDENCY6.6 yr overdueHITESH INDRAVADAN PATEL · Andheri, Mumbai SuburbanP51800004728· 99.5% built
- JAS Exotica Phase II6.6 yr overdueHriday Developers · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000030· 83.6% built
- SAMADNYA APARTMENTS6.6 yr overdueSARASWATI CONSTRUCTIONS · MUNICIPAL PARK, JalgaonP49900013764· 45.6% built
- VIRAT AANGAN BUILDING NO 16.6 yr overdueSIDDHIVINAYAK DEVELOPERS · GANESH NAGAR, ThaneP51700007977· 72.7% built
- OLIVE-16.6 yr overdueJVM ENTERPRISE · Thane, ThaneP51700001276· 35.9% built
- REGENCY PLATINUM6.6 yr overdueDHAANIYA ENTERPRISES · Ulhasnagar, ThaneP51700021512· 90.9% built
- KIMAYA MAYURSHRI6.6 yr overdueSAMIR AMRUT GANDHI · GANDHI NAGAR, SolapurP52600000788· 26.8% built
- Sai Exotique B Wing6.6 yr overdueSAIBABA SALES PRIVATE LIMITED · Pimpri Chinchawad (M Corp.), PuneP52100009721· filed Dec 2018 → now Dec 2019· 81.8% built
- PENINSULA HEIGHTS6.6 yr overduePRIESKA REAL ESTATES PVT. LTD. · VIRAR WEST, PalgharP99000011703· 43.1% built
- NAKSHATRA PLAZA6.6 yr overdueV S KHOT REAL ESTATE DEVELOPERS · Gadhinglaj, KolhapurP53000012651· 90.9% built
- Construction of 406 TR TS 442 EWS 258 MIG TS at Gavanpada Mulund east Mumbai6.6 yr overdueMHADA · Kurla, Mumbai SuburbanP51800000024· filed Dec 2018 → now Dec 2019· 90.8% built
- GARDEN COURT TYPE B26.6 yr overdueDEEAARDEE ENTERPRISES · VASANT LEELA, ThaneP51700014836· 90.9% built
- VINAY UNIQUE CORNER6.6 yr overdueVINAYUNIQUE CONSTRUCTION PRIVATE LIMITED · BOLINJ, PalgharP99000010331· 88.2% built
- Orbit Bonneville6.6 yr overdueB-Orbit Amparo Constructions PVT Ltd · MOSHI, PuneP52100003348· filed Dec 2018 → now Dec 2019· 90.9% built
- CRD Gardenia Apartments 16.6 yr overdueDr Chandrashekhar Raghunath Dound · Palghar, PalgharP99000009462· filed Dec 2018 → now Dec 2019· 81.8% built
- Parshwa Chintamani6.6 yr overdueVeetarag Builders & Developers · Parshwanath Nagar, SangliP53100015249· 81.8% built
- Time Blossom6.6 yr overdueSudeep Rajendra Chhajed · Sadashiv Nagar, NashikP51600017542· 90.9% built
- LOTUS PARK6.6 yr overdueMATRUKRUPA DEVELOPERS · Ambegaon Bk, PuneP52100016278· 62.7% built
- SHAH GOVIND APARTMENT PHASE II6.6 yr overdueSHAH BUILDERS AND DEVELOPERS · Bhagur Rural, NashikP51600001700· 64.1% built
- SAI NAKSHATRA BUILDING A AND B PHASE- I6.6 yr overdueVIKAS LAXMAN CHAUDHARY · NAKSHATRAWADI AURANGABAD, AurangabadP51500005710· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B36.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009783· filed Dec 2018 → now Dec 2019· 60.2% built· 1 complaint
- Balaji Arcade Wing A6.6 yr overdueSHIKHAR DEVELOPERS · Kalyan, ThaneP51700012219· 90.9% built
- Vantagio6.6 yr overdueVyankatesh Infra · Osmanpura, AurangabadP51500013507· 59.1% built
- AUDUMBAR6.6 yr overdueVAS BUILDER & DEVELOPERS · Borivali East, Mumbai SuburbanP51800011943· 41.5% built
- Fortune6.6 yr overdueWonder Spaces · Talegaon Dabhade (M Cl), PuneP52100001687· 90.9% built
- T12 NAMED MAGNA BEING PHASE 2 OF THE PROJECT COMPRISING BUILDINGS T12 AND T136.6 yr overdueCavalcade Properties Private Limited · MOHAMMADWADI, PuneP52100015996· 72.7% built
- EELA Phase-I6.6 yr overdueM/s. Siddhashila Developers · Punawale, PuneP52100012382· filed Dec 2018 → now Dec 2019· 89.1% built
- BROOKEFIELD WILLOWS6.6 yr overdueNirman Trimurti Developers · Pisoli, PuneP52100002035· 90.9% built· 1 complaint
- JIN YASH6.6 yr overdueContendre Infratech Pvt. Ltd. · SHILPHATA, RaigarhP52000017145· 90.9% built
- BHAVESHWAR CORNER6.6 yr overdueBHAVESHWAR CONSTRUCTION · Karanjade, RaigarhP52000006595· 39.9% built
- DOLPHIN PLATINA6.6 yr overdueDOLHIN HOME DEVELOPERS · Haveli, PuneP52100014580· 90.9% built
- Pratham Residency6.6 yr overduePratham realtors · Talegaon Dabhade (M Cl), PuneP52100008144· 90.9% built
- GANESH AURA6.6 yr overdueVEDDANT REALTY · Haveli, PuneP52100005169· 72.7% built
- Leisure town6.6 yr overdueBhansali Infotech LLP · hadpsar, PuneP52100001401· filed Dec 2018 → now Dec 2019· 90.9% built· 13 complaints
- PAVILION 796.6 yr overdueWAKADKAR ASSOCIATE · Wakad, PuneP52100004489· 23.6% built
- DEV RATNA6.6 yr overdueSDC DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700007785· 90.9% built
- KANCHAN COMFORTZ SANGAMNER PHASE 16.6 yr overdueKanchan Infra · Ghulewadi (CT), AhmednagarP52200001316· filed Dec 2018 → now Dec 2019· 59.4% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 2 - B126.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008852· filed Dec 2018 → now Dec 2019· 60.2% built
- NEMINATH APARTMENT SRA CHS AND SHREE SIDDHAGIRI SRA CHS6.6 yr overdueSUBHASH VELJI CHAWDA · Borivali, Mumbai SuburbanP51800011251· 41.9% built
- NYATI ETERNITY COMMERCIAL II6.6 yr overdueNITIN DWARKADAS NYATI · AXIS BANK UNDRI, PuneP52100021443· 45.2% built
- PRASHANT UDYAN CHS LTD6.6 yr overdueSHREE CHAMUNDA REALTORS · Mumbai City, Mumbai CityP51900009273· 43.2% built
- Rachayati Enclave6.6 yr overdueRachayati Realtors and Developers pvt ltd · Amravati (M Corp.), AmravatiP50300013564· 90.9% built
- Sun Planet Phase III6.6 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · Haveli, PuneP52100018258· 81.8% built
- TULIP CLASSIC6.6 yr overdueTushar Mohanrao Khatavkar · Rajarampuri 12th lane, KolhapurP53000015468· 72.5% built
- Clover Casablanca Phase II6.6 yr overdueWorthwhile Properties Pvt. Ltd. · Mawal, PuneP52100002277· filed Dec 2018 → now Dec 2019· 90.9% built
- DATTA VIHAR6.6 yr overdueSHREE UMIYA BUILDCON · Ambegaon, PuneP52100016362· 90.9% built
- Om Heights6.6 yr overdueOM BUILDERS AND DEVELOPERS · Near Global School, JalgaonP49900015232· 81.8% built
- GRAPE CITY PHASE I6.6 yr overdueMs AMBER ESTATE · ANANDVALLI BEHIND SHRI GURUJI HOSPITAL, ThaneP51700001499· filed Dec 2018 → now Dec 2019· 90.9% built
- charms hill6.6 yr overdueM/S PRIME DEVELOPERS · Vangani (CT), ThaneP51700007816· filed Dec 2018 → now Dec 2019· 89.1% built
- Gokul Park6.6 yr overdueSai Ganesh Realtors · Vasai, PalgharP99000000895· filed Dec 2018 → now Dec 2019· 53.6% built
- Mallhar Estate6.6 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001367· filed Dec 2018 → now Dec 2019· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.