RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 20 of 61
- Shreemanyogi6.9 yr overdueMORNING STAR REALITIES · Pimpri Chinchawad (M Corp.), PuneP52100002250· filed Dec 2018 → now Dec 2019· 86.4% built
- AARIV EXOTICA6.9 yr overdueIK ONKAR CONSTRUCTIONS · BALEWADI, PuneP52100009605· 84.5% built
- OM SAI HEIGHTS6.9 yr overdueOM SAI DEVELOPERS · Junnar, PuneP52100003063· 49.1% built
- SAVALI TOWER6.9 yr overdueSavali Developers · OPP RELIANCE PETROL PUMP SASVAD, PuneP52100015927· 49.1% built
- I.K. GROUP6.9 yr overdueI K GROUP · Palghar, PalgharP99000005540· filed Dec 2018 → now Dec 2019· 58.8% built
- HIra Heights6.9 yr overdueMayura Promoters And Developers Pvt. Ltd. · Solapur (M Corp.), SolapurP52600003853· 90.9% built
- RAKHI TOWER PHASE 16.9 yr overdueWESTERN DEVELOPMENTS · Borivali, Mumbai SuburbanP51800005504· 80.7% built· 1 complaint
- Morphic Arham6.9 yr overdueMorphic Developers · Mukundnagar, PuneP52100003108· filed Jun 2018 → now Dec 2019· 90.9% built
- KUL Utsav Phase I -Building F6.9 yr overdueKumar Builders · Pune, PuneP52100009849· 90.9% built
- Morya Residency Phase II6.9 yr overdueABHAY LAXMANRAO KULKARNI · Jalna (M Cl), JalnaP51400002209· 90.9% built
- GAJANAN SMRUTI6.9 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019112· 81.8% built
- GIRIRAJ APARTMENTS6.9 yr overdueMETRO DWELLERS PRIVATE LIMITED · MULUND WEST, Mumbai SuburbanP51800012045· filed Dec 2018 → now Dec 2019· 55.5% built· 1 complaint
- SHIVDARSHAN APARTMENT6.9 yr overdueSAHYADRI BUILDCON · Nashik (M Corp.), NashikP51600010151· 90.9% built
- Unicorn Nest I6.9 yr overdueUnicorn Developers · Sangamner, AhmednagarP52200012510· filed Dec 2018 → now Dec 2019· 90.9% built
- SAHARA PEARL6.9 yr overdueSAHARA BUILDCON · Sasvad (M Cl), PuneP52100002551· 90.9% built
- WOODLAND6.9 yr overdueSHAURYA INFRA BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700005808· filed Dec 2018 → now Dec 2019· 90.9% built
- DECCAN RESIDENCY6.9 yr overdueDECCAN DEVELOPERS · NEAR RAM MANDIR, SangliP53100004556· 81.8% built
- VASANT VIHAR6.9 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019139· 81.8% built
- HARI AAKRUTI6.9 yr overdueKARDA BUILDCON PRIVATE LIMITED · Kathe Galli, NashikP51600000423· filed Dec 2018 → now Dec 2019· 90.9% built· 4 complaints
- PRIME VILLA6.9 yr overdueLEERA RAMJI ARETHIYA · Panvel, RaigarhP52000004578· 63.6% built
- KSP RESIDENCY6.9 yr overdueKRISHNAT SHAHU POWAR · Maruti mandir, RatnagiriP52800012180· 88% built
- AANGAN VILLA6.9 yr overdueSHREE KHODIYAR DEVELOPERS · Uran, RaigarhP52000004845· 81.8% built
- Vishwa Abha6.9 yr overdueM/s. Vishwa Green Realtors Private Limited · Uran, RaigarhP52000003732· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- The Back Water Residency phase I - D Building6.9 yr overdueLNK PROJECTS Through Proprietor Mr Narayan Baburao Khasnis · Haveli, PuneP52100019828· 90.9% built
- SHREE OM RESIDENCY6.9 yr overduePRABHAT RAMRAO DESAI · Sangli Miraj Kupwad (M Corp.), SangliP53100009550· filed Dec 2018 → now Dec 2019· 81.8% built
- ARCHWAY6.9 yr overdueAAB ASSOCIATES · Pune (M Corp.), PuneP52100009345· filed Dec 2018 → now Dec 2019· 90.9% built
- HARISHCHANDRA RESIDENCY6.9 yr overduePRATAP NARAYAN DESHMUKH · AMRAVATI, AmravatiP50300013119· 81.8% built
- SHIVANAND APARTMENT6.9 yr overdueDEAL CONSTRUCTION · Nashik, NashikP51600003142· 90.9% built
- VAMA PARADISE6.9 yr overdueVAMA LIFESTYLES · VIRAR WEST, PalgharP99000010889· 90.9% built
- ARIHANT ANSHULA6.9 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Navi Mumbai, RaigarhP52000009246· 85.5% built· 1 complaint
- ABHISHEK FLORIDA- BLOSSOM6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000008362· 90.9% built
- Sri Guruashish6.9 yr overdueVishnu Shankar Rane · Nashik, NashikP51600010609· 90% built
- Gulmohar Park A phase 16.9 yr overdueMercury Artharaj Landmarks AOP · Haveli, PuneP52100007126· 42.7% built
- SHIVALAY APARTMENT6.9 yr overdueShivalay Developers · Ulawe, RaigarhP52000009972· 90.9% built
- KAKADE PLAZA PHASE 16.9 yr overdueSuryakant Kakade · Kopare, PuneP52100012132· 93.9% built
- NISARGA SPARSH6.9 yr overdueARYA NISARGA PROPERTIES · Mawal, PuneP52100004715· 35.5% built
- ABHISHEK FLORIDA- SUNFLOWER, ROSE, JASMINE6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005897· 90.9% built· 1 complaint
- SHIV SAMRUDHI - A WING6.9 yr overdueSHIV DEVELOPERS · Wakad, PuneP52100014369· 81.8% built
- KUL COURT6.9 yr overdueKumar Builders Mumbai Realty Pvt Ltd · Mumbai, Mumbai SuburbanP51800009338· filed Dec 2018 → now Dec 2019· 76.2% built· 2 complaints
- JAS LUXURIA , J-16.9 yr overdueASHNAY Developers · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000029· 99.6% built
- APURVA6.9 yr overdueSHARAD SHAMRAO SAWANT · NEAR WALCHAND COLLAGE, SangliP53100014495· 90.9% built
- SKYLON SPACES6.9 yr overdueSAI KRUPA DEVELOPERS · Borivali, Mumbai SuburbanP51800010405· filed Dec 2018 → now Dec 2019· 90.9% built
- ABHISHEK FLORIDA- MARIGOLD6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004893· 90.9% built
- Sai Arcade6.9 yr overdueKiran Patel · Jail Road, NashikP51600011987· 76.4% built
- ARIHANT NANO PEARL6.9 yr overdueSURAJ ANNASAHEB UPADHYE · KUPWAD, SangliP53100015629· 53.6% built
- TRINITY CO OP HSG SOC LTD6.9 yr overduePIONEER ENTERPRISES · Kurla, Mumbai SuburbanP51800001462· 99.9% built
- ABHISHEK FLORIDA- LOTUS6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005376· 90.9% built
- ABHISHEK FLORIDA- ORCHID6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004263· 90.9% built
- Sri Gurumangal6.9 yr overdueManisha Vishnu Rane · Nashik, NashikP51600010391· 90.5% built
- PARVATI ARCADE6.9 yr overdueCHANDRAKAUMUDI CONSTRUCTION · Mahad, RaigarhP52000001957· 90.9% built
- SAACHI HEIGHTS6.9 yr overdueVINAYAKUMAR REKHCHAND RATHI · AKOLA, AkolaP50100022672· 90.9% built
- Panvelkar Nisarg Phase-I6.9 yr overduePanvelkar Realty Private Limited · Ambarnath, ThaneP51700004393· filed Dec 2018 → now Dec 2019· 90.9% built
- ABHISHEK FLORIDA- DAFFODILS6.9 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005514· 90.9% built
- PARSHVA AANGAN6.9 yr overdueSONALI MEHUL DOSHI · Uran, RaigarhP51700000724· 37.6% built
- SHREE KRISHNA PLAZA6.9 yr overdueSHREE HANUMAN ENTERPRISES · Thakurli, Cholegaon, ThaneP51700014660· 90.9% built· 2 complaints
- Rivaah Regency6.9 yr overdueAjay Nanasaheb Jadhavrao · WAGHOLI, PuneP52100009655· filed Dec 2018 → now Dec 2019· 90.9% built
- DIGAMBAR SADAN6.9 yr overdueMsdevelopers · Nanded Waghala (M Corp.), NandedP51100006594· 32% built
- SAILEELA6.9 yr overdueDENNIS JAMES FERNANDES · KHALAPUR, RaigarhP52000010923· filed Dec 2018 → now Dec 2019· 86.4% built
- RAJ TOWER6.9 yr overdueJAYBHAVE BUILDERS · RANE NAGAR, NashikP51600011857· filed Dec 2018 → now Dec 2019· 86.8% built· 1 complaint
- LITTLE HEARTS PHASE 26.9 yr overdueSHREEMANGAL VISHHRAM DEVELOPERS · UNDRI, PuneP52100009230· 90.9% built
- Janaki Complex6.9 yr overduePravin Narayan Lad · Fish Market, RatnagiriP52800017248· 90.9% built
- PAYAL CO OP HSG SOC6.9 yr overdueSUFAL ASSOCIATES · PRABHAT ROAD, PuneP52100009888· filed Dec 2018 → now Dec 2019· 81.8% built
- KESHAV APARTMENT6.9 yr overdueGULAB SUREKHA PAWAR · LIC COLONY, LaturP52400016021· 10.5% built
- MANGALDEEP CHSL.6.9 yr overdueDHARIWAL CONSTRUCTIONS (INDIA) PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800010018· filed Dec 2018 → now Dec 2019· 90.9% built
- SWAPNASHILP6.9 yr overdueFUTURISTIC HOMES · Wakad, PuneP52100003880· 73.2% built
- UNIQUE ELITA6.9 yr overdueANKUR SHUBHAM DEVELOPERS · Andheri, Mumbai SuburbanP51800006885· filed Dec 2018 → now Dec 2019· 45.9% built· 1 complaint
- SUNRISE HOMES6.9 yr overdueKHALIF SIRAJ SHAIKH · Damat, RaigarhP52000010277· 61.8% built
- Bliss county A and B Wing6.9 yr overdueVISION DEVELOPERS AND BUILDERS · RAHATNI, PuneP52100003752· 29.5% built
- JYOTI PALACE6.9 yr overdueWESTBURY CONSTRUCTION PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800006809· filed Dec 2018 → now Dec 2019· 65.6% built
- Tiara6.9 yr overdueSHETH AND POPAT ENTERPRISE · Wakad, PuneP52100007260· 26.8% built· 1 complaint
- ACHARYA ASHRAM SAHAKARI GRIHA RACHANA SANSTHA MARYADIT6.9 yr overduePrarthana Constructions · Borivali, Mumbai SuburbanP51800008405· filed Dec 2018 → now Dec 2019· 84.5% built· 1 complaint
- 11 West6.9 yr overduePARINEE REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800003709· 90.9% built· 2 complaints
- VINAY UNIQUE HEIGHTS6.9 yr overdueSUV DEVELOPERS · Vasai, PalgharP99000002691· 83.6% built
- HARIGANGA HEIGHTS6.9 yr overdueKALASH LANDMARKS · Amravati (M Corp.), AmravatiP50300011446· 32.7% built
- Pragati Residency6.9 yr overdueSiddhi Developers · Near New Polytechnic College, KolhapurP53000015144· 67.7% built
- Megapolis Mystic - C6.9 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park, Phase 3, PuneP52100019959· 90.9% built
- HIRA RESIDENCY PHASE II6.9 yr overdueAL-SAAD CONSTRUCTIONS · Thane, ThaneP51700005670· 90.9% built
- SAMADNYA APARTMENTS6.9 yr overdueSARASWATI CONSTRUCTIONS · MUNICIPAL PARK, JalgaonP49900013764· 45.6% built
- KUBER AAGAN6.9 yr overdueCRATIVE HOME MAKERS · Kalyan, ThaneP51700010264· 63.6% built· 3 complaints
- RADHA RESIDENCY6.9 yr overdueGOVINDA CONSTRUCTION · Nashik (M Corp.), NashikP51600012697· 90.9% built
- GAURISHANKAR BUNGALOW REDEVELOPMENT6.9 yr overdueS S REALITY · Shreekrishna Nagar, Mumbai SuburbanP51800015462· 90.9% built
- MOHINI TOWER6.9 yr overdueMOHINI SHELTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800006731· 98.2% built· 1 complaint
- MUTUAL BENEFIT CO OP HSG SOC LTD6.9 yr overdueSUNRISE HOUSING · Kurla, Mumbai SuburbanP51800002333· 81.8% built
- MATOSHREE YASHODA RESIDANCY6.9 yr overdueDYNESHWAR KESHAVRAO BHOSALE · RAVIVAR PETH, NashikP51600016562· 36.4% built
- KIMAYA MAYURSHRI6.9 yr overdueSAMIR AMRUT GANDHI · GANDHI NAGAR, SolapurP52600000788· 26.8% built
- Om Heights6.9 yr overdueOM BUILDERS AND DEVELOPERS · Near Global School, JalgaonP49900015232· 81.8% built
- Joy Legend Wing A6.9 yr overdueJAYANT SONI · Andheri, Mumbai SuburbanP51800005022· filed Dec 2018 → now Dec 2019· 70% built· 7 complaints
- Anmol Nayantara Gold6.9 yr overdueBafna Builders and Land Developers · Nashik, NashikP51600002894· filed Dec 2018 → now Dec 2019· 71.5% built· 2 complaints
- DOLPHIN PLATINA6.9 yr overdueDOLHIN HOME DEVELOPERS · Haveli, PuneP52100014580· 90.9% built
- Twin Arcs6.9 yr overdueWhite Properties and Ventures · Punawale, PuneP52100001145· 90.9% built
- PADMAJA RESIDENCY6.9 yr overduePADMA BUILDCON · Nashik (M Corp.), NashikP51600013300· filed Dec 2018 → now Dec 2019· 90.9% built
- PARTH CLASSIC6.9 yr overduePARTH DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100013837· filed Dec 2018 → now Dec 2019· 58.6% built
- FLOWER CITY6.9 yr overdueAARADHYA PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100011239· 80% built
- GLORIS6.9 yr overdueSahakar Developers · Borivali, Mumbai SuburbanP51800001984· filed Dec 2018 → now Dec 2019· 80.5% built
- Mohan Nano estates II6.9 yr overdueMOHAN LIFESPACES LLP · AMBERNATH, ThaneP51700013253· 90.9% built
- ARISTOLIA6.9 yr overdueFORTUNE ASSOCIATES · Hadapsar, PuneP52100001480· 38.2% built
- MAGNOVA MANOR PHASE 16.9 yr overdueMAGNOVA REALTY · WAKAD, PuneP52100004858· 81.8% built
- MAJESTIQUE CITY6.9 yr overdueMANISH DWARKADAS MAHESHWARI · Wagholi, PuneP52100000113· 90.9% built
- BLUE DIAMOND RESIDENCY6.9 yr overdueKIMAYA CONSTRUCTION · Ambarnath, ThaneP51700002359· 90.9% built
- SIRVI Heights6.9 yr overduePYRAMID ENTERPRISES · KAMOTHE, RaigarhP52000012162· 59.1% built
- Jeevan Aashiana6.9 yr overdueBrahmani Constructions · Talegaon Dabhade (M Cl), PuneP52100014493· 46.4% built
- RAJ RESIDENCY6.9 yr overdueRAMESHWAR CONSTRUCTIONS · Nashik (M Corp.), NashikP51600009461· 89.1% built
- Arihant Heights6.9 yr overdueSamruddhi Developers · Haveli, PuneP52100015353· 77.3% built
- VIRALI APARTMENT6.9 yr overdueCHANDRASHEKHAR TUKARAM JADHAV · Chiplun (M Cl), RatnagiriP52800010221· 90.9% built
- VINAY UNIQUE IMPERIA6.9 yr overdueIMPERIUM BUILDCON LLP · Vasai-Virar City (M Corp), PalgharP99000008596· 81.8% built· 8 complaints
- NILOY6.9 yr overdueSHREE SAI BUILDERS & DEVELOPERS · Ambarnath, ThaneP51700000166· 81.8% built
- GANESH AURA6.9 yr overdueVEDDANT REALTY · Haveli, PuneP52100005169· 72.7% built
- SHIVPURAM A PLOT A6.9 yr overdueLUNKAD VISHWA DEVELOPERS · Haveli, PuneP52100002861· 81.8% built
- REELICON KIAN6.9 yr overdueJKDEVELOPERS · AMBEGAON BK, PuneP52100003028· filed Dec 2018 → now Dec 2019· 54.5% built
- SHAAD RESIDENCY6.9 yr overdueSHADAB ISLAM QURESHI · Ward E, Mumbai CityP51900009967· 95.7% built· 2 complaints
- SAMRTH CHAAYA6.9 yr overdueN M N DEVELOPERS · Khedshi, RatnagiriP52800002942· 57.3% built
- Satyam Rajyog6.9 yr overdueSatyam Constructions ·P52100002338· filed Dec 2018 → now Dec 2019· 90.9% built
- KINGSTONE AVENUE PH 16.9 yr overdueSupreme Developers · Pimpale Saudagar, PuneP52100001909· filed Dec 2018 → now Dec 2019· 70.8% built· 2 complaints
- GOLDSTAR DECENT HOMES6.9 yr overdueGOLDSTAR SANKALP CONSTRUCTION · Thane, ThaneP51700000053· filed Dec 2018 → now Dec 2019· 82.9% built
- SHANTI SEVEN6.9 yr overdueSHANTISTAR BUILDERS · Thane, ThaneP51700002572· 89.1% built
- SHANKAR COMPLEX II6.9 yr overdueJARIMARI RESIDENCY · Kalyan, ThaneP51700010530· 44.5% built
- Nirmal Lifestyle-Zircon6.9 yr overdueNirmal Lifestyle Ltd · Kurla, Mumbai SuburbanP51800004719· filed Dec 2018 → now Dec 2019· 71.8% built· 65 complaints
- GANGA NEWTOWN PHASE I6.9 yr overdueSHREE BALAJI ASSOCIATES PUNE LLP · Haveli, PuneP52100001431· 87.4% built· 1 complaint
- Elite Abodeh6.9 yr overdueGanesh Dashrath Dale · LOHGAON, PuneP52100009181· filed Dec 2018 → now Dec 2019· 97.3% built
- Shravan Dhara6.9 yr overdueM/s Suyog Nirman · Chiplun (M Cl), RatnagiriP52800001197· 39.1% built
- Kisna6.9 yr overdueShreeji Realties Private Limited · Andheri, Mumbai SuburbanP51800003802· 90.9% built
- Rite Luxuria6.9 yr overdueRite Developers Pvt. Ltd. · Kurla, Mumbai SuburbanP51800006260· filed Dec 2018 → now Dec 2019· 90.9% built· 4 complaints
- SHRIRAM TOWER6.9 yr overdueSUDHASHRI INFRACON · Nagpur (M Corp.), NagpurP50500012525· 90.9% built
- Rudraksha6.9 yr overdueMahesh Manohar Panhalkar · Kolhapur (M Corp.), KolhapurP53000002311· 90.9% built
- SS Builders Building No.76.9 yr overdueS S BUILDERS · Vasai, PalgharP99000004734· 81.8% built
- NYATI ETERNITY COMMERCIAL II6.9 yr overdueNITIN DWARKADAS NYATI · AXIS BANK UNDRI, PuneP52100021443· 45.2% built
- PRINCE TOWER6.9 yr overdueADITYA BUILDCON · Aurangabad (M Corp.), AurangabadP51500007890· 90.9% built
- ALIANA CITY PLAZA6.9 yr overdueZILL DEVELOPERS · Khalapur, RaigarhP52000002935· filed Dec 2018 → now Dec 2019· 42.4% built· 1 complaint
- Rambaug City A16.9 yr overdueShriram Developers · Shirwal, SataraP52700002887· 80.9% built
- SAI NAKSHATRA BUILDING A AND B PHASE- I6.9 yr overdueVIKAS LAXMAN CHAUDHARY · NAKSHATRAWADI AURANGABAD, AurangabadP51500005710· 90.9% built
- SAISERENITY6.9 yr overdueJAYINFRASTREUCTURIES · Anandwalli Nashik, NashikP51600007991· 90.9% built· 1 complaint
- PRASHANT UDYAN CHS LTD6.9 yr overdueSHREE CHAMUNDA REALTORS · Mumbai City, Mumbai CityP51900009273· 43.2% built
- VINAY UNIQUE GARDENS6.9 yr overdueVINAYUNIQUE DEVELOPERS · DONGRE, PalgharP99000012052· 86.4% built· 9 complaints
- VIJAY RESIDENCY6.9 yr overdueVEDANT PROPERTIES · Pune (M Corp.), PuneP52100013999· 78.2% built
- Celestine6.9 yr overdueLotus Construction · Pune City, PuneP52100002736· 39.4% built
- Modispaces Amazon6.9 yr overdueModispaces Real Estate Pvt Ltd · Borivali, Mumbai SuburbanP51800004328· 45.5% built
- PEACE VALLEY6.9 yr overdueR J DEVELOPERS · Ravet, PuneP52100012347· filed Dec 2018 → now Dec 2019· 81.4% built
- MAHAVIR SYMPHONY6.9 yr overdueRAKESH AMRUTLAL SHAH · Vasai, PalgharP99000011172· filed Dec 2018 → now Dec 2019· 90.9% built
- Goolden Woods6.9 yr overdueKirti Construction · Nideban (CT), LaturP52400010216· 78.2% built· 1 complaint
- Panvelkar Estate - Rockford6.9 yr overdueVijay Ramchandra Panvelkar · Ambarnath, ThaneP51700000431· 72.7% built
- VENKATESH JOYNEST PHASE 46.9 yr overdueSHREE VENKATESH GROUP · Haveli, PuneP52100017998· 90.9% built
- SAINATH HERITAGE6.9 yr overdueSAINATH ENTERPRISES · Panvel, RaigarhP52000010186· filed Dec 2018 → now Dec 2019· 90.9% built
- Pristine Pacific H , I6.9 yr overdueMELANGE DEVELOPERS · Pune (M Corp.), PuneP52100001211· 90.9% built
- BELLA VISTA6.9 yr overdueARMAND CORPORATION · CHEMBUR, Mumbai SuburbanP51800007308· filed Dec 2018 → now Dec 2019· 63.6% built
- Balaji Arcade Wing C6.9 yr overdueSHIKHAR DEVELOPERS · Kalyan, ThaneP51700005709· 61.4% built
- Gala Amora6.9 yr overdueKarishma Realty · Andheri, Mumbai SuburbanP51800006181· 23.6% built
- SAKET PLAZA6.9 yr overdueS S BUILDERS AND DEVELOPERS · AYODYA NAGARI NASHIK, NashikP51600016202· 40.9% built
- SANKALP HERITAGE6.9 yr overdueSHYAM BIHARILAL GEHANI · Borivali, Mumbai SuburbanP51800003309· 90.9% built
- PARAISO-16.9 yr overdueSARTHAK BUILDTECH ·P52100003064· 81.8% built
- RUDRAKSH RESIDENCY6.9 yr overdueMUGDHA SANDEEP BODKE · satpur, NashikP51600012753· 90.9% built
- SMS ARCADE WING C6.9 yr overdueAayush Madhusudan Agrawal · SEVEN HILL, AurangabadP51500018133· 90.9% built
- FOUR AVENUES6.9 yr overdueIKON CONSTRUCTIONS · Haveli, PuneP52100006853· filed Dec 2018 → now Dec 2019· 90.9% built
- DISHA KUNJABAN PHASE 36.9 yr overdueDEVANAND NARAYANRAO KOTGIRE (HUF) · Wadgaon Kolhati (CT), AurangabadP51500001537· filed Dec 2018 → now Dec 2019· 90.9% built
- SILVERENE6.9 yr overdueSHREEJI COMBINE · Andheri, Mumbai SuburbanP51800005090· filed Dec 2018 → now Dec 2019· 88.2% built
- NIRMAL RESIDENCY6.9 yr overduePRITAM SURESH PACHARE · MORWA, ChandrapurP50900015827· 61.3% built
- Mallhar Towers6.9 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001951· filed Dec 2018 → now Dec 2019· 81.4% built
- DNYANESHWARI COMPLEX6.9 yr overdueShree Raghunath Maharaj Developers · CHOVISWADI, PuneP52100016255· 47.7% built
- SHILP SIDDHI6.9 yr overdueHemant Dattatraya Gaikwad · Shivram Nagar, NashikP51600011679· 81.8% built
- VEDANT PERIDOT6.9 yr overdueNANIS BUILDCON PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500009166· 84.5% built
- RUNWAL GREENS Wings 5 - 86.9 yr overdueRunwal Apartments Private Limited · Kurla, Mumbai SuburbanP51800000271· 72.7% built· 44 complaints
- Teerth Technospace 66.9 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100004940· filed Dec 2018 → now Dec 2019· 90.9% built
- SHRI SAHYOG6.9 yr overdueRAMDAS RAOSAHEB JAGTAP · Karanje Peth Satara (CT), SataraP52700006267· filed Dec 2018 → now Dec 2019· 90.9% built
- DURVANKUR APARTMENT6.9 yr overdueMANOJ JAYANT BHAGWAT · Pen (M Cl), RaigarhP52000011694· 43.2% built
- Raj Height6.9 yr overdueBhavani Enterprises · SHIRGOAN, ThaneP51700006732· 90.9% built
- SHWETA CHS6.9 yr overdueATHARVA DEVELOPERS · Kurla, Mumbai SuburbanP51800001142· filed Dec 2018 → now Dec 2019· 90.9% built
- KRISHNABAN Phase 16.9 yr overdueBhuvi Landmarks LLP · Jalna, JalnaP51400006388· filed Dec 2018 → now Dec 2019· 78.2% built
- Chishti Apartment6.9 yr overdueDolphin Developers · Khopoli, RaigarhP52000013808· 90.9% built
- RITU DREAMS6.9 yr overdueRITU REALITY · Vasai, PalgharP99000002765· filed Dec 2018 → now Dec 2019· 71.4% built
- Teerth Technospace 96.9 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100004297· filed Dec 2018 → now Dec 2019· 90.9% built
- Neptune Flying Kites A Wing - Right Wing6.9 yr overdueNEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800007428· filed Dec 2018 → now Dec 2019· 90.9% built· 8 complaints
- Samraat Nucleus - Project 016.9 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Bhabha Nagar, NashikP51600001208· 88.6% built
- BEAUPRIDE6.9 yr overdueSHETH REALTORS · Andheri, Mumbai SuburbanP51800000418· 87.7% built· 1 complaint
- GOKULDHAM APARTMENT6.9 yr overdueRAJESH BHAGULAL DHAMONE · NEAR KINGS COLLEGE, JalnaP51400015664· 27.3% built
- TATER FLORENCE IVY-B WING6.9 yr overdueTATER REALTY · Karjat, RaigarhP52000002578· filed Dec 2018 → now Dec 2019· 90.9% built
- SANJAR DEVELOPERS AND BUILDERS6.9 yr overdueSANJAR DEVELOPERS & BUILDERS · Borivali, Mumbai SuburbanP51800003814· 88.2% built
- NAGESHWAR6.9 yr overdueMADHHU DAULATRAO PATIL · Panvel, RaigarhP52000006769· 74.5% built
- VIMAL RAJ WING A-1, MEDITYARAVIRAJ COMPLEX6.9 yr overdueRITESH RAMESH JAIN · Thane, ThaneP51700007634· 84.5% built
- Rachana One Up6.9 yr overdueRachana Value Homes Pvt Ltd · Bopele, RaigarhP52000002087· 81.8% built
- Marvel Ganga Sangria G,H,J Building6.9 yr overdueMARVEL LANDMARKS PVT LTD · MOHAMMADWADI, PuneP52100002371· filed Dec 2018 → now Dec 2019· 95.2% built· 15 complaints
- Central Park6.9 yr overdueOpulent Properties · Manjari Bk, PuneP52100000909· 90.9% built
- PARK PLAZA WING A6.9 yr overduePPR CONSTRUCTION LLP · HOHGAON, PuneP52100002914· 55.7% built
- AAIJI BLISS6.9 yr overdueSHRI GANESH DEVELOPERS · Karanjade, RaigarhP52000011848· 29.5% built
- NEPTUNE SWARAJYA SECTOR 2 - B126.9 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008852· filed Dec 2018 → now Dec 2019· 60.2% built
- Rassaz Greens6.9 yr overdueRais Ahmad · Thane, ThaneP51700008730· 50% built
- SAPPHIRE6.9 yr overdueJANGID BUILDERS PRIVATE LIMITED · Mira Road East, ThaneP51700020060· 28.4% built
- SAI FORTUNE6.9 yr overdueSURESH GURALDAS THADANI · Ulhasnagar, ThaneP51700015389· 37.7% built
- Grow More Bliss B Wing6.9 yr overdueGrowmore Space Solutions Pvt. Ltd. · Borivali, Mumbai SuburbanP51800005958· 81.8% built
- WHITE PEARL6.9 yr overdueS S SHRIYA INFRASTRUCTURES · Nagpur (M Corp.), NagpurP50500010689· 11.6% built
- TULSI ANAND6.9 yr overdueANAND HOMES · Eranjade, ThaneP51700008015· 48.5% built
- OM SHILP6.9 yr overdueOM SHILP · Haveli, PuneP52100013506· 81.8% built
- SWAMI HIGHLANDS6.9 yr overdueSHREE SWAMI SAMARTH ASSOCIATES · Badlapur (M Cl), ThaneP51700002816· 90.9% built
- Anmol Nayantara City Two phase 16.9 yr overdueBafna Realtors Pvt Ltd · Karmayogi nagar, NashikP51600001967· filed Dec 2018 → now Dec 2019· 81.7% built
- PANDAV CASITA6.9 yr overdueS R BUILDWELL · Nashik (M Corp.), NashikP51600011954· 90.9% built
- Adityasagar Complex6.9 yr overdueSiddhesh Mahadeo Kanade · Vabhave, SindhudurgP52900012910· filed Dec 2018 → now Dec 2019· 69.5% built
- ROHAN ABHILASHA BUILDING F6.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000490· 83% built
- SATYAM OLEANDER6.9 yr overdueSAHYOG GROUP · Ambarnath(M Cl), ThaneP51700010440· 74.2% built· 2 complaints
- TRISHABH SIGNET6.9 yr overdueDimension Housing Realty LLP · Kurla, Mumbai SuburbanP51800001222· 90% built· 1 complaint
- Giri Darshan Apartment6.9 yr overdueConcept Townships & Estate Developers Pvt Ltd · Talegaon Dabhade (M Cl), PuneP52100011639· 54.5% built
- Samarth Siddhi6.9 yr overdueShree Samarth Developers · Haveli, PuneP52100000711· 81.8% built
- ARMONIA RESIDENCY6.9 yr overdueM2 DEVELOPERS · Somatane, PuneP52100013738· 81.8% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.