RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 21 of 61
- SUNSHINE INFINITY6.9 yr overdueSQ INFRASTRUCTURE PRIVATE LIMITED · Ward FNorth, Mumbai CityP51900003947· filed Dec 2018 → now Dec 2019· 83.6% built· 4 complaints
- Mohan Greenwoods Building 16.9 yr overdueMOHAN LIFESPACES LLP · Manjarli, ThaneP51700015601· 90.9% built
- Life Republic Sector R3 - 3rd Avenue6.9 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Jambe, PuneP52100007511· 90.9% built· 5 complaints
- KRISHNA DARSHAN6.9 yr overdueBODKE BUILDCON · KAMATWADE, NashikP51600014276· 90.9% built· 2 complaints
- SAMADNYA APARTMENTS6.9 yr overdueSARASWATI CONSTRUCTIONS · MUNICIPAL PARK, JalgaonP49900013764· 45.6% built
- DEV RATNA6.9 yr overdueSDC DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700007785· 90.9% built
- KOHINOOR IRIS PARK6.9 yr overdueKohinoor Properties · kalepadal, PuneP52100001617· 81.8% built
- Neptune Flying Kites A Wing - Right Wing6.9 yr overdueNEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800007428· filed Dec 2018 → now Dec 2019· 90.9% built· 8 complaints
- VARAD VIHAR6.9 yr overdueSHREE DEVELOPERS · Haveli, PuneP52100012703· filed Aug 2018 → now Dec 2019· 52.7% built
- PANDURANG SANKUL6.9 yr overdueDESAIBROTHERS · Karad (M Cl), SataraP52700011348· 12% built
- SHIVAM PALACE6.9 yr overdueSHIVAM CONSTRUCTION · MAMDAPUR, RaigarhP52000015309· 81.4% built
- Samarth Siddhi6.9 yr overdueShree Samarth Developers · Haveli, PuneP52100000711· 81.8% built
- SWARA RESIDENCY6.9 yr overdueYOGESH ENTERPRISES · Panvel, RaigarhP52000006983· 79.4% built
- NEPTUNE SWARAJYA SECTOR 2 - B15 AND B176.9 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700006446· filed Dec 2018 → now Dec 2019· 70.5% built· 2 complaints
- Atmaram Plaza6.9 yr overdueShreeyan Developers · Vasai, PalgharP99000003881· 45.5% built
- ALIANA CITY PLAZA6.9 yr overdueZILL DEVELOPERS · Khalapur, RaigarhP52000002935· filed Dec 2018 → now Dec 2019· 42.4% built· 1 complaint
- OSTWAL DREAM LAND6.9 yr overdueSHREE OSTWAL BUILDERS LTD · Palghar, PalgharP99000008545· filed Dec 2018 → now Dec 2019· 90.9% built
- SKY MAX6.9 yr overdueHARBANSLAL TULSIRAM WADHWA · Haveli, PuneP52100001534· filed Dec 2018 → now Dec 2019· 80% built
- REDEVELOPMENT OF ULKA CHSL6.9 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800004627· 90.9% built
- LABDHI GARDENS PHASE 46.9 yr overdueLabdhi Lifestyle Limited · Neral, Mumbai CityP51900009217· 86.1% built· 1 complaint
- SMS ARCADE WING C6.9 yr overdueAayush Madhusudan Agrawal · SEVEN HILL, AurangabadP51500018133· 90.9% built
- SAI SAMARTH SANKUL6.9 yr overdueSAI SAMARTH ENTERPRISES · Kudal (CT), SindhudurgP52900008286· 45.5% built
- NANDANVAN PALACE6.9 yr overdueShreenath Developers(AOP) · Santaji Nagar, PuneP52100005286· 90.9% built
- The Pinnacle6.9 yr overdueGERARIE ENTERPRISES AND DEVELOPERS PVT. LTD · Kurla, Mumbai SuburbanP51800005304· filed Dec 2018 → now Dec 2019· 90.9% built
- Alpine Heritage6.9 yr overdueALPINE SKYSCRAPERS LLP · NA, RaigarhP52000015494· 81.8% built
- Anmol Fortune - II6.9 yr overdueWadhwa Realty Pvt Ltd. · Borivali, Mumbai SuburbanP51800001089· 99.1% built· 5 complaints
- NEPTUNE SWARAJYA SECTOR 2 - 1B6.9 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700003705· filed Dec 2018 → now Dec 2019· 55.6% built
- CRESCENT IMPERIA6.9 yr overdueCRESCENT ARK LIFESTYLES PVT LTD · Andheri, Mumbai SuburbanP51800002184· 90.9% built
- Tejas Emerald6.9 yr overdueTejas Enterprises · Panvel, RaigarhP52000009591· 90.9% built
- SS Builders Building No.76.9 yr overdueS S BUILDERS · Vasai, PalgharP99000004734· 81.8% built
- Sunshine Joy Phase 26.9 yr overdueGreenlife Associates · Mulshi, PuneP52100004441· filed Dec 2018 → now Dec 2019· 86.4% built
- PHASE III VISION WOODS6.9 yr overdueSHUBBAN PROPERTIES VISION WOODS · pune, PuneP52100004840· filed Dec 2018 → now Dec 2019· 78.2% built
- SHARADA PRIDE6.9 yr overdueSHARADA ALLIANCE PROMOTERS & BUILDERS · Phaltan (M Cl), SataraP52700003907· 44.5% built
- SHUBHAM APARTMENT6.9 yr overdueRAMESH GULAB TUPE · VILLAGE PUSHPAK NODE , TALUKA PANVEL, RaigarhP52000015885· 90.9% built
- STKANWARRAMPALACIOPHASE16.9 yr overdueVINOD PREMCHAND CHANDWANI · Chikhali Bk., PuneP52100000276· 90.9% built
- ARIHANT RESIDENCY6.9 yr overdueNIRWANA ASSOCIATES · Baner, PuneP52100011552· 69.5% built· 1 complaint
- 11 West6.9 yr overduePARINEE REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800003709· 90.9% built· 2 complaints
- CENTRAL PLAZA6.9 yr overdueAMITKUMAR ZAVERCHAND SHETH · Mahad (M Cl), RaigarhP52000002418· 90.9% built
- Choice Ambe Smruti6.9 yr overdueCHOICE BUILDCON LLP · Khalapur, RaigarhP52000000824· 64.3% built
- Megapolis Mystic - C6.9 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park, Phase 3, PuneP52100019959· 90.9% built
- SORRENTO6.9 yr overdueSAHAJ ANKUR DEVELOPERS · Andheri, Mumbai SuburbanP51800003022· filed Dec 2018 → now Dec 2019· 95% built· 2 complaints
- VIMAL RAJ WING A-1, MEDITYARAVIRAJ COMPLEX6.9 yr overdueRITESH RAMESH JAIN · Thane, ThaneP51700007634· 84.5% built
- KRISHNA BHUVAN C.H.S.6.9 yr overdueSHAUNAK DILIP KIRKIRE · Ward FNorth, Mumbai CityP51900007903· 90.9% built· 5 complaints
- PEACE VALLEY6.9 yr overdueR J DEVELOPERS · Ravet, PuneP52100012347· filed Dec 2018 → now Dec 2019· 81.4% built
- Arihant Heights6.9 yr overdueSamruddhi Developers · Haveli, PuneP52100015353· 77.3% built
- NEPTUNE SWARAJYA SECTOR 2 - B86.9 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009785· filed Dec 2018 → now Dec 2019· 54.5% built· 3 complaints
- NANA PATIL PRIDE6.9 yr overduePATIL BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700008376· filed Dec 2018 → now Dec 2019· 80.2% built
- Park Royale AB Wing6.9 yr overdueSHIVRANJANI PROPERTIES LLP · Andheri, Mumbai SuburbanP51800001315· 96.4% built
- Raj - Baiju6.9 yr overdueRaj Arcade Pvt. Ltd. · Borivali, Mumbai SuburbanP51800003361· 36.4% built
- AARAMBH6.9 yr overduePANDHARINATH VITTHAL JAMBHALKAR · Haveli, PuneP52100002457· filed Dec 2018 → now Dec 2019· 76.4% built
- NOBEL SAGAR RESIDENCY6.9 yr overdueNOBLE SAGAR CONSTRUCTION · NEAR SHRI NAGARI, SataraP52700010865· 90.9% built
- Shine Square6.9 yr overdueNamoh Builders & Developers · Pimpri Chinchawad (M Corp.), PuneP52100003130· filed Dec 2018 → now Dec 2019· 75.9% built· 1 complaint
- Teerth Technospac 106.9 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100004312· filed Dec 2018 → now Dec 2019· 90.9% built
- Hubtown Sunmist A 6th to Above Floor6.9 yr overdueHubtown Limited · Andheri, Mumbai SuburbanP51800001202· 81.2% built· 8 complaints
- OXY EVOLVE6.9 yr overdueVENKATESH ASSOCIATES · WAGHOLI, PuneP52100000772· 90.9% built
- SAIVIJAYICON6.9 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600009951· 81.8% built
- URBANVILLE6.9 yr overdueSAI KRUPA BUILDERS · Kalyan, ThaneP51700005910· 31% built
- GARDEN COURT TYPE B26.9 yr overdueDEEAARDEE ENTERPRISES · VASANT LEELA, ThaneP51700014836· 90.9% built
- LODHA BELMONDO ST. ANDREWS E6.9 yr overdueLodha Developers Limited · Gahunje, PuneP52100000182· 90.9% built· 1 complaint
- HIRA RESIDENCY PHASE II6.9 yr overdueAL-SAAD CONSTRUCTIONS · Thane, ThaneP51700005670· 90.9% built
- LODHA FRESHIA WING D, E6.9 yr overdueLodha Developers Limited · Kalyan, ThaneP51700006149· 90.9% built
- OM SHILP6.9 yr overdueOM SHILP · Haveli, PuneP52100013506· 81.8% built
- KUBER AAGAN6.9 yr overdueCRATIVE HOME MAKERS · Kalyan, ThaneP51700010264· 63.6% built· 3 complaints
- Raza Imperial6.9 yr overdueShakeel Ahmad Abdul Gafoor Quazi · Raza Colony, NashikP51600009442· 90.9% built
- SUNANDA CIRCLE B WING PHASE 16.9 yr overdueRUDIS DEVELOPERS · Thane, ThaneP51700009812· 90.9% built· 1 complaint
- YASHRAJ6.9 yr overdueArjun Developers · Khed (CT), SataraP52700014475· 81.8% built
- Sai Hira6.9 yr overdueMRUNALI REALTY LLP · MOSHI, PuneP52100000634· 90.9% built
- Sunrise Enclave6.9 yr overdueSunrise Realtors · Pimpri Chinchawad (M Corp.), PuneP52100002153· 65.9% built
- Eden Garden II6.9 yr overdueM C Babu · Uran, RaigarhP52000008714· 82.5% built
- Panvelkar Estate - Stanford - Phase 16.9 yr overduePanvelkar Infrastructures Private Limited · Ambarnath, ThaneP51700000366· filed Dec 2018 → now Dec 2019· 83% built
- SHAMAL RESIDENCY6.9 yr overdueRAVINDRA GOPAL KULKARNI · Lote, RatnagiriP52800009656· 88.6% built
- NISARG PALMS6.9 yr overdueADITYA SHAGUN DEVELOPERS · BAVDHAN BK, PuneP52100015113· 72.7% built
- Mont Vert Cresta6.9 yr overdueMont Vert Constructions · Old Mumbai Pune Highway, PuneP52100004636· 73% built
- RAMESHWARAM6.9 yr overdueUPADHYAYA REALITIES · NAIK NAGAR, AurangabadP51500007678· 89.1% built
- RAIL VIEW6.9 yr overdueUMESH NARESH JAIN · Thane, ThaneP51700002009· 90.9% built
- MANORAMA CHS6.9 yr overdueRUPA PROPERTIES & SECURITIES PVT. LTD. · Thane, ThaneP51700005251· 90.9% built
- Sparsh Building no. 36.9 yr overdueShree Enterprises · Panvel, RaigarhP52000006745· 77.2% built
- DEV PRIDE APARTMENT6.9 yr overdueDEVSHREE DEVELOPRS · Nashik (M Corp.), NashikP51600010024· 49.1% built
- Xrbia Hinjewadi Road / Riverfront - Ph - 26.9 yr overdueXrbia North Hinjewadi Developers Private Limited · Bebad Ohol, PuneP52100000379· filed Dec 2018 → now Dec 2019· 90.9% built· 7 complaints
- Uttam Townscapes6.9 yr overdueFORTUNE DEVELOPERS AND INFRASTRUCTURES · Vishrantwadi, PuneP52100014002· 90.9% built
- Shreedham Classic6.9 yr overdueShreedham Construction Private Limited · Andheri, Mumbai SuburbanP51800012234· filed Dec 2018 → now Dec 2019· 89.9% built· 1 complaint
- SHAMBHURAJ GARDEN WING-A AND WING-B6.9 yr overdueSHAMBHURAJ DEVELOPERS · PHALTAN, SataraP52700014866· 16.4% built
- SATYAM OLEANDER6.9 yr overdueSAHYOG GROUP · Ambarnath(M Cl), ThaneP51700010440· 74.2% built· 2 complaints
- VARDHAMAN DREAMS PHASE II6.9 yr overdueVARDHMAN PROPERTISE · Wakad, PuneP52100001649· 90.2% built
- 81 AUREATE6.9 yr overduePYRAMID DEVELOPERS · Andheri, Mumbai SuburbanP51800010171· filed Dec 2018 → now Dec 2019· 98% built· 25 complaints
- KAPILASHRAM6.9 yr overdueRAMRAI Buildcon LLP · Navi Sadashiv Peth, PuneP52100018672· 70.5% built
- Pankaj Aasmaan Phase I6.9 yr overduePankaj Developers · Lahagaon, PuneP52100009665· 81.8% built
- JMDVARDHAM6.9 yr overdueCOSTAL VINCOM PVT LTD · Borivali, Mumbai SuburbanP51800005339· 86.4% built
- Pristine Greens Phase 16.9 yr overduePRISTINE PROPERTIES · BORHADEWADI, PuneP52100009406· 90.9% built· 9 complaints
- SWAMI HIGHLANDS6.9 yr overdueSHREE SWAMI SAMARTH ASSOCIATES · Badlapur (M Cl), ThaneP51700002816· 90.9% built
- ARMADAPHASEI6.9 yr overdueG K WONDERS · WAKAD, PuneP52100001684· 59.1% built
- VISHWAJEET ELITE6.9 yr overdueVISHWAJEET MEADOWS · Ambarnath, ThaneP51700001654· filed Dec 2018 → now Dec 2019· 31.4% built
- NAVKAR PARK6.9 yr overduePARKONS TRENDZ · Haveli, PuneP52100005084· filed Apr 2019 → now Dec 2019· 81.8% built· 1 complaint
- Shankeshwar Crimson6.9 yr overdueNitin Chhaganlal Jain · Haveli, PuneP52100000087· 90.9% built
- ALANKAR F BUILDING6.9 yr overdueR K LUNKAD HOUSING COMPANY · CHARHOLI, PuneP52100016029· 81.8% built
- SHREE CHAMUNDA HEIGHTS6.9 yr overdueSHREE CHAMUNDA REALTORS · Mumbai City, Mumbai CityP51900009861· 58.6% built
- Shree Sai Pooja6.9 yr overdueM/s Mahalaxmi Construction Co. · Ambarnath, ThaneP51700002237· 90.9% built
- SHREE POOJA6.9 yr overdueMANGALAM BUILDCON · NERAL, RaigarhP52000001841· 81.8% built
- BHUVI MADHURBAN6.9 yr overdueBhuvi Landmarks LLP · Balapur, AurangabadP51500002962· filed Dec 2018 → now Dec 2019· 78.2% built
- VIRAT AANGAN BUILDING NO 16.9 yr overdueSIDDHIVINAYAK DEVELOPERS · GANESH NAGAR, ThaneP51700007977· 72.7% built
- Samrudhee Malhar6.9 yr overdueSAMRUDHEE HOMES · Sasvad (M Cl), PuneP52100002866· filed Dec 2018 → now Dec 2019· 77.3% built
- KINGSTON COURT6.9 yr overdueMAHALAXMI ENTERPRISES · Vasai, PalgharP99000003618· 70.6% built
- Shanti Niwas6.9 yr overdueD.G. Patel & Co. · Kurla, Mumbai SuburbanP51800007402· filed Dec 2018 → now Dec 2019· 90.9% built
- HARIGANGA HEIGHTS6.9 yr overdueKALASH LANDMARKS · Amravati (M Corp.), AmravatiP50300011446· 32.7% built
- Nirmal Lifestyle-Zircon6.9 yr overdueNirmal Lifestyle Ltd · Kurla, Mumbai SuburbanP51800004719· filed Dec 2018 → now Dec 2019· 71.8% built· 65 complaints
- SHUBH AASHISH6.9 yr overdueA B BUILDER & DEVELOPERS PVT LTD · Mumbai, Mumbai SuburbanP51800009692· filed Dec 2018 → now Dec 2019· 90.9% built
- REDEVELOPMENT OF VISHVA ANAND CHS LTD6.9 yr overdueR R CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800004066· 90.9% built
- IMPERIA HOMES6.9 yr overdueGPRS REALTY · Vakola, Mumbai CityP51900010379· 58.6% built
- NILGAGAN CO-OPERATIVE HOUSING SOCIETY LIMITED6.9 yr overdueFSK BUILDERS & DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700002833· 90.9% built
- ATULYA NIRMAN6.9 yr overdueD S ASSOCIATES · Punawale, PuneP52100003976· 81.8% built· 2 complaints
- POTE AALAYA6.9 yr overduePRAKASH GAJANAN POTE · Near Mari aai Temple, RaigarhP52000001069· 90.9% built
- Kisna6.9 yr overdueShreeji Realties Private Limited · Andheri, Mumbai SuburbanP51800003802· 90.9% built
- CALIFORNIA HEIGHTS6.9 yr overdueSUDHIR ASHOK MANDALE · Khed, PuneP52100005103· 65.7% built
- PAVILION 796.9 yr overdueWAKADKAR ASSOCIATE · Wakad, PuneP52100004489· 23.6% built
- RIDDHI SIDDHI REGENCY6.9 yr overdueK. RIDDHI SIDDHI DEVELOPERS · Panvel, RaigarhP52000012203· 90.9% built
- construction of 24 flats and 12 shops on plot bearing R.S. No. 599-4 part, Balajipark, Kolhapur6.9 yr overduePune Housing and Area Development Board Pune · Near Hocky Stadium, KolhapurP53000019417· 55.5% built
- Shivdatta Aishvaryam6.9 yr overdueShivdatta Associates · Sangli Miraj Kupwad (M Corp.), SangliP53100001478· 72.7% built
- Asmeeta Infratech Limited - Asmeeta Texpa6.9 yr overdueAsmeeta Infratech Limited · kon (CT), ThaneP51700009154· 81.8% built
- Saheels Fortune Park II6.9 yr overdueNeev Sai Associates · PUNE, PuneP52100002349· 90.9% built
- ARYAN HEIGHTS6.9 yr overdueAryan Construction · Haveli, PuneP52100010649· 39.5% built
- TRIMURTI BHAVAN6.9 yr overdueSWAMI CHAITANYA ASSOCIATES · Chiplun (M Cl), RatnagiriP52800005249· 86.4% built
- SAHIL APARTMENT6.9 yr overdueRAMESH GULAB TUPE · PANVEL, RaigarhP52000016275· 90.9% built
- KUBER GANRAJ6.9 yr overdueKUBER ABHIRAJ INFRA · GANESH NAGAR, ThaneP51700008998· 81.7% built· 57 complaints
- Tulsi Elanza6.9 yr overdueMETRO CAPITAL · Kurla, Mumbai SuburbanP51800006377· 27.3% built
- Om Sat6.9 yr overdueShree Siddhi Developers · Ward FNorth, Mumbai CityP51900007293· filed Dec 2018 → now Dec 2019· 90.9% built
- Diamond One6.9 yr overdueDiamond Estate Builders & Developers · Nagpur (M Corp.), NagpurP50500001314· 81.8% built
- DNS TOWER6.9 yr overdueRajendra Dattatray Sawant · Kurla, Mumbai SuburbanP51800009731· filed Dec 2018 → now Dec 2019· 90.9% built· 2 complaints
- Shravan Dhara6.9 yr overdueM/s Suyog Nirman · Chiplun (M Cl), RatnagiriP52800001197· 39.1% built
- LANDMARK6.9 yr overdueCRESCENT REALTORS INDIA PVT LTD · Andheri, Mumbai SuburbanP51800003163· 90.9% built
- GOLDSTAR DECENT HOMES6.9 yr overdueGOLDSTAR SANKALP CONSTRUCTION · Thane, ThaneP51700000053· filed Dec 2018 → now Dec 2019· 82.9% built
- Kamdhenu Commerz6.9 yr overdueKAMDHENU BUILDERS AND DEVELOPERS · Thane, ThaneP51700000559· 93.6% built
- ATHARV-VARAD APARTMENT6.9 yr overdueM/S SHREE GAJANANSUPERCON · AUSA ROAD, LaturP52400015184· 10% built
- Mohan Areca II6.9 yr overdueMOHAN LIFESPACES LLP · Shirgaon, ThaneP51700017925· 90.9% built
- YASH LAXMI6.9 yr overdueAkshay Developers · Karjat, RaigarhP52000009103· 60% built
- Shhraddha Vishwa6.9 yr overdueShhraddha Enterprises · Bhavani Peth, SolapurP52600000065· 90.9% built
- Engracia6.9 yr overdueJagtap Patil Promoters & Builders · Haveli, PuneP52100002471· 81.8% built
- USHAPRABHA CHS6.9 yr overdueSHASHIKANT GAJANAN POTE · Panvel, RaigarhP52000007082· 90.9% built
- Akashvedh Phase 16.9 yr overdueRaghvendra Buildcon · Pimpri Chinchawad (M Corp.), PuneP52100006065· filed Dec 2018 → now Dec 2019· 90.9% built
- Chhoriya Residency Nandurbar Phase - 26.9 yr overdueChhoriya and Kela Developers · Nandurbar, NandurbarP49700009502· filed Dec 2018 → now Dec 2019· 50.6% built
- Mallhar Estate6.9 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001367· filed Dec 2018 → now Dec 2019· 90.9% built
- DEEP REKHA PLAZA6.9 yr overdueSANJAYKUMAR RAMCHANDRA PATIL · Sangli Miraj Kupwad (M Corp.), SangliP53100004600· 98.2% built
- Santkrupa Sankul6.9 yr overdueChandrakant Kashinath Kele · KESHAR NAGAR, DhuleP49800011701· 81.8% built
- Akshar Jyot6.9 yr overdueAkshar Enterprises · Near rau hotel, Peth road, NashikP51600018428· 43.6% built
- SHRI BALAJI NIWAS6.9 yr overdueBHOOMI ENTERPRISES · PALGHAR, PalgharP99000015857· 72.7% built
- BAITUS SALEHEEN6.9 yr overdueRainbow Constructions · SHANTINAGAR, NagpurP50500016107· 53.2% built
- MARATHON NEXZONE AVIOR -16.9 yr overdueSANVO RESORTS PVT. LTD. · Panvel, RaigarhP52000000502· 75.1% built· 16 complaints
- SHREEJI KRUPA6.9 yr overduePARESH PUJARA AND ABHIRAJ PUJARA (AOP) · Andheri, Mumbai SuburbanP51800003649· 90.9% built
- SAMRUDDHI HEIGHTS6.9 yr overdueLAXMAN EKNATH GOMASE · Nashik (M Corp.), NashikP51600013275· 90.9% built
- DATTA VIHAR6.9 yr overdueSHREE UMIYA BUILDCON · Ambegaon, PuneP52100016362· 90.9% built
- SAPPHIRE6.9 yr overdueJANGID BUILDERS PRIVATE LIMITED · Mira Road East, ThaneP51700020060· 28.4% built
- PRITHVI RESIDENCY6.9 yr overduePRITHVI BUILD HOMES · Borivali, Mumbai SuburbanP51800009232· filed Dec 2018 → now Dec 2019· 90.9% built
- SAI RAJ6.9 yr overdueSAI DHARA ENTERPRISE · Vasai, PalgharP99000002245· 90% built
- AARAMBH6.9 yr overdueSAPTARSHI DEVELOPERS · Shirur, PuneP52100004850· 60.6% built
- POPULAR COLONY6.9 yr overdueBALAJI CONSTRUCTION COMPANY · Haveli, PuneP52100015233· 72.7% built
- Ganesh Heights6.9 yr overdueShiv Builders and Developers · Badlapur (M Cl), ThaneP51700006830· 90.9% built
- SERENE HOMES6.9 yr overdueMANAS PROMOTERS & DEVELOPERS · Bhosari, PuneP52100012409· 73.1% built
- RAVI KARAN HEIGHTS6.9 yr overdueRAMKRISHNA DEVELOPERS · Haveli, PuneP52100013812· 22.7% built
- N.M.Joshi Building No.4 Annex6.9 yr overdueSHREE DEVELOPERS · Kurla, Mumbai SuburbanP51800006487· 80.6% built
- SHREE SIDDHIVINAYAK HEIGHTS6.9 yr overdueAJIT KRISHNAN RATNAM · Titwala, ThaneP51700003326· filed Dec 2018 → now Dec 2019· 90.9% built
- Time Blossom6.9 yr overdueSudeep Rajendra Chhajed · Sadashiv Nagar, NashikP51600017542· 90.9% built
- SAISERENITY6.9 yr overdueJAYINFRASTREUCTURIES · Anandwalli Nashik, NashikP51600007991· 90.9% built· 1 complaint
- ELITE GREEN ACRES - I AND J6.9 yr overdueSUNITA GAJENDRA PATIL · Mawal, PuneP52100003819· 81.8% built
- SHILP SIDDHI6.9 yr overdueHemant Dattatraya Gaikwad · Shivram Nagar, NashikP51600011679· 81.8% built
- Adinath Suvastu6.9 yr overdueADINATH DEVELOPERS · Satara (CT), AurangabadP51500005255· 90.9% built
- SARTHAK HOMES6.9 yr overdueSARTHAK INFRA · NANA MASTER NAGAR, RaigarhP52000008473· 90.9% built· 1 complaint
- ND Enclave6.9 yr overdueN & D Constructions LLP · Andheri, Mumbai SuburbanP51800010411· filed Dec 2018 → now Dec 2019· 90.5% built
- DHAIRYASHEEL PRIDE6.9 yr overduePANDURANG VINAYAK KANDALGAONKAR · padatewadi, SindhudurgP52900004575· 81.8% built
- Sairaj Heights6.9 yr overdueSAIBABA SALES PRIVATE LIMITED · Pimpri Chinchawad (M Corp.), PuneP52100001542· filed Dec 2018 → now Dec 2019· 81.8% built· 2 complaints
- GOVINDA B6.9 yr overdueSAI ANAND BUILDERS · Nashik, NashikP51600007264· filed Dec 2018 → now Dec 2019· 90.9% built
- PANOM PARK PHASE 1 WING A B C AND C EXTENSION6.9 yr overduePANOM DEVELOPERS LLP · Andheri, Mumbai SuburbanP51800005027· 90.9% built
- Tiara6.9 yr overdueSHETH AND POPAT ENTERPRISE · Wakad, PuneP52100007260· 26.8% built· 1 complaint
- VINAY UNIQUE IMPERIA6.9 yr overdueIMPERIUM BUILDCON LLP · Vasai-Virar City (M Corp), PalgharP99000008596· 81.8% built· 8 complaints
- Airiana6.9 yr overdueMitesh Lakhamshi Patel · LOHGAON, PuneP52100007161· filed Sept 2018 → now Dec 2019· 25.9% built
- TULIP N6.9 yr overdueROYALE URBANSPACE · SHAHAPUR, ThaneP51700011791· 53.2% built
- Bliss county A and B Wing6.9 yr overdueVISION DEVELOPERS AND BUILDERS · RAHATNI, PuneP52100003752· 29.5% built
- The HUB6.9 yr overdueZAMBAD INFRASTRUCTURE LIMITED · Shendra Kamangar, AurangabadP51500005443· 88.6% built
- SWAPNASHILP RESIDENCY6.9 yr overdueM/S NIRMITI BUILDERS & DEVELOPERS · Junnar, PuneP52100011894· 29.5% built
- GAURISHANKAR BUNGALOW REDEVELOPMENT6.9 yr overdueS S REALITY · Shreekrishna Nagar, Mumbai SuburbanP51800015462· 90.9% built
- Gundecha Desire6.9 yr overdueRockline Developers Pvt. Ltd. · Andheri, Mumbai SuburbanP51800001166· filed Dec 2018 → now Dec 2019· 90.9% built· 4 complaints
- Ratnesh Plaza6.9 yr overdueBabasaheb Pandurang Patil · Sawantwadi (M Cl), SindhudurgP52900011813· 90.9% built
- Rosa Oasis Phase 26.9 yr overdueUma Enterprises · Thane, ThaneP51700005311· filed Dec 2018 → now Dec 2019· 99% built
- Chintamani Heights6.9 yr overdueYASH ENTERPRISES · Kulgaon, ThaneP51700014730· 90.9% built
- RAM KRISHNA PLAZA6.9 yr overdueSHINDE SURVE AND ASSOCIATES · Chiplun (M Cl), RatnagiriP52800013031· 0% built
- ROYAL RESIDENCY6.9 yr overdueSANJAY HARISCHANDRA MORE · Mahad (M Cl), RaigarhP52000010729· 40% built
- WHITE PEARL6.9 yr overdueS S SHRIYA INFRASTRUCTURES · Nagpur (M Corp.), NagpurP50500010689· 11.6% built
- AMANN MARINA6.9 yr overdueMS RELLIANCE CONSTRUCTION CO · Ward GSouth, Mumbai CityP51900010428· filed Dec 2018 → now Dec 2019· 81.8% built· 3 complaints
- SADGURU PLANET6.9 yr overdueSADGURU INFRAPROJECTS I PVT LTD · Kalamboli, RaigarhP52000013809· 90.9% built
- REDEVLOPMENT OF RAJENDRA NAGAR - SHREE GANESH CHS LTD.6.9 yr overdueKaustubh Construction Private Limited · Borivali, Mumbai SuburbanP51800006765· filed Dec 2018 → now Dec 2019· 81.8% built
- KANHA RESIDENCY6.9 yr overdueEKADANTA SHELTERS · Malkhed, SataraP52700008109· 15.1% built
- GLORIS6.9 yr overdueSahakar Developers · Borivali, Mumbai SuburbanP51800001984· filed Dec 2018 → now Dec 2019· 80.5% built
- SHREE RASRAJ TOWER6.9 yr overdueK MEHTA AND COMPANY · Borivali, Mumbai SuburbanP51800000873· 90.9% built
- KIMAYA MAYURSHRI6.9 yr overdueSAMIR AMRUT GANDHI · GANDHI NAGAR, SolapurP52600000788· 26.8% built
- SANJAR DEVELOPERS AND BUILDERS6.9 yr overdueSANJAR DEVELOPERS & BUILDERS · Borivali, Mumbai SuburbanP51800003814· 88.2% built
- PRAYAG CITY Phase I6.9 yr overduePRAYAG BUILDERS AND DEVELOPERS · VIHIGHAR, RaigarhP52000004381· 89.1% built· 3 complaints
- PRAMAN HERITAGE6.9 yr overduePRAMAN DEVELOPERS · Ward ABCD, Mumbai CityP51900004810· 90.9% built
- SAI KRUPA RESIDENCY6.9 yr overdueSAIRAJ DEVELOPERS · BADLAPUR, ThaneP51700015567· 90.9% built
- ASHWA PLATINUM6.9 yr overdueASHWAMEDH BUILDERS AND DEVELOPERS · Thane, ThaneP51700001143· 59.3% built· 1 complaint
- ORION6.9 yr overdueSUDARSHAN DEVELOPERS · Haveli, PuneP52100007244· 42.4% built
- NEPTUNE SWARAJYA SECTOR 2 - B 146.9 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700003706· filed Dec 2018 → now Dec 2019· 65.8% built· 1 complaint
- Swastik Sapphire6.9 yr overdueSwastik Realtors · Kurla, Mumbai SuburbanP51800000239· 63.6% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.