RERA projects past their possession deadline
11,767 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 22 of 59
- ROYAL OASIS PHASE 16.6 yr overdueRIKKI RONIE DEVELOPERS · Borivali, Mumbai SuburbanP51800002382· filed Dec 2018 → now Dec 2019· 94.5% built· 2 complaints
- BAITUS SALEHEEN6.6 yr overdueRainbow Constructions · SHANTINAGAR, NagpurP50500016107· 53.2% built
- JYOTI PALACE6.6 yr overdueWESTBURY CONSTRUCTION PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800006809· filed Dec 2018 → now Dec 2019· 65.6% built
- VEENA DYNASTY PH II6.6 yr overdueNIKUNJ DEVELOPERS · Vasai, PalgharP99000007769· 89.1% built
- VIJAY RESIDENCY6.6 yr overdueVEDANT PROPERTIES · Pune (M Corp.), PuneP52100013999· 78.2% built
- SHREE SADGURU COMPLEX PHASE I6.6 yr overdueEARTH HOME · Khalapur, RaigarhP52000011306· 90.9% built
- SHREE SIDDHIVINAYAK HEIGHTS6.6 yr overdueAJIT KRISHNAN RATNAM · Titwala, ThaneP51700003326· filed Dec 2018 → now Dec 2019· 90.9% built
- VINAY UNIQUE IMPERIA6.6 yr overdueIMPERIUM BUILDCON LLP · Vasai-Virar City (M Corp), PalgharP99000008596· 81.8% built· 8 complaints
- Sparsh Building no. 36.6 yr overdueShree Enterprises · Panvel, RaigarhP52000006745· 77.2% built
- YASHRAJ6.6 yr overdueArjun Developers · Khed (CT), SataraP52700014475· 81.8% built
- BELLA VISTA6.6 yr overdueLAXMI KESHAV CONSTRUCTIONS AND SHRIKA DEVELOPERS PRIVATE LIMITED · Nagpur, NagpurP50500005466· 90.9% built· 1 complaint
- SORRENTO6.6 yr overdueSAHAJ ANKUR DEVELOPERS · Andheri, Mumbai SuburbanP51800003022· filed Dec 2018 → now Dec 2019· 95% built· 2 complaints
- SWAMI HIGHLANDS6.6 yr overdueSHREE SWAMI SAMARTH ASSOCIATES · Badlapur (M Cl), ThaneP51700002816· 90.9% built
- SAPTARSHI RESIDENCY C WING6.6 yr overdueSUBHAGYA PROMOTERS & BUILDERS PRIVATE LIMITED · AHER NAGAR , NEAR AHER GARDEN, PuneP52100010341· filed Dec 2018 → now Dec 2019· 45.5% built
- ADCON MERIDIAN6.6 yr overdueHI SKY REALTY · Andheri, Mumbai SuburbanP51800010498· filed Dec 2018 → now Dec 2019· 90.9% built
- CALIFORNIA HEIGHTS6.6 yr overdueSUDHIR ASHOK MANDALE · Khed, PuneP52100005103· 65.7% built
- BALAJI HEIGHTS6.6 yr overdueLALAN BALJI SHAH · Nashik, NashikP51600010064· filed Dec 2018 → now Dec 2019· 50.9% built
- ATULYA NIRMAN6.6 yr overdueD S ASSOCIATES · Punawale, PuneP52100003976· 81.8% built· 2 complaints
- BHAVESHWAR CORNER6.6 yr overdueBHAVESHWAR CONSTRUCTION · Karanjade, RaigarhP52000006595· 39.9% built
- Promenade - The Address6.6 yr overdueWadhwa Residency Pvt Ltd · Kurla, Mumbai SuburbanP51800000201· 90.9% built· 21 complaints
- GANGA NEWTOWN PHASE I6.6 yr overdueSHREE BALAJI ASSOCIATES PUNE LLP · Haveli, PuneP52100001431· 87.4% built· 1 complaint
- VISHWAJEET MANOR6.6 yr overdueABHIJEET REALTY · Ambarnath, ThaneP51700001321· 45.5% built
- Shaankeshwar Pride6.6 yr overdueSri Shaankeshwar Developers · Pimpri Chinchawad (M Corp.), PuneP52100013140· 81.8% built
- BLUEBELL IMPERIAL6.6 yr overdueDeepak Bhupatrai Vora · Vasai, PalgharP99000002856· 33.3% built
- SMS ARCADE WING C6.6 yr overdueAayush Madhusudan Agrawal · SEVEN HILL, AurangabadP51500018133· 90.9% built
- IMPERIA HOMES6.6 yr overdueGPRS REALTY · Vakola, Mumbai CityP51900010379· 58.6% built
- LAKEVIEW APARTMENT6.6 yr overdueTRIMURTI BUILDERS AND DEVELOPERS · Vasai, PalgharP99000007342· 28.8% built· 1 complaint
- SHASHWAT PARK6.6 yr overdueMODERN CONSTRUCTION · Badlapur (M Cl), ThaneP51700004817· filed Dec 2018 → now Dec 2019· 17.3% built
- Anmol Nayantara City Two phase 16.6 yr overdueBafna Realtors Pvt Ltd · Karmayogi nagar, NashikP51600001967· filed Dec 2018 → now Dec 2019· 81.7% built
- VARDHAMAN DREAMS PHASE II6.6 yr overdueVARDHMAN PROPERTISE · Wakad, PuneP52100001649· 90.2% built
- KRISHNA DARSHAN6.6 yr overdueBODKE BUILDCON · KAMATWADE, NashikP51600014276· 90.9% built· 2 complaints
- T12 NAMED MAGNA BEING PHASE 2 OF THE PROJECT COMPRISING BUILDINGS T12 AND T136.6 yr overdueCavalcade Properties Private Limited · MOHAMMADWADI, PuneP52100015996· 72.7% built
- Mayuresh Residency6.6 yr overdueMAYURESH REALTORS AND DEVELOPERS PRIVATE LIMITED · Sangli Miraj Kupwad (M Corp.), SangliP53100004815· 81.8% built
- Bhosales Mallhar Heritage6.6 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001531· filed Dec 2018 → now Dec 2019· 90.9% built
- Portia6.6 yr overdueVilas Javdekar Lifestyle Developers Pvt. Ltd. · Haveli, PuneP52100000301· filed Dec 2018 → now Dec 2019· 68.2% built
- RAJYOG RESIDENCY6.6 yr overdueBALAJI VIKRAM AWARE · Haveli, PuneP52100014835· 18.2% built
- PRAMAN HERITAGE6.6 yr overduePRAMAN DEVELOPERS · Ward ABCD, Mumbai CityP51900004810· 90.9% built
- Shantiniketan Wing B36.6 yr overdueAnmol Associates · Kalyan, ThaneP51700010374· 75% built
- ELITE DREAMS6.6 yr overdueAJINKYA DEVELOPERS · Haveli, PuneP52100007217· 44.1% built
- DURVANKUR APARTMENT6.6 yr overdueMANOJ JAYANT BHAGWAT · Pen (M Cl), RaigarhP52000011694· 43.2% built
- DISHA KUNJABAN PHASE 36.6 yr overdueDEVANAND NARAYANRAO KOTGIRE (HUF) · Wadgaon Kolhati (CT), AurangabadP51500001537· filed Dec 2018 → now Dec 2019· 90.9% built
- RIDDHI SIDDHI REGENCY6.6 yr overdueK. RIDDHI SIDDHI DEVELOPERS · Panvel, RaigarhP52000012203· 90.9% built
- LAXMI RESIDENCY6.6 yr overdueOM SAI ENTERPRISE · Vasai-Virar City (M Corp), PalgharP99000009380· filed Dec 2018 → now Dec 2019· 90.9% built
- PRIDE PHOENIX BUILDING C1-C26.6 yr overdueABAD ESTATE AOP · Chikalthana, AurangabadP51500000337· 90.9% built
- Aayushi Apartment6.6 yr overduePRIYANSHI ENTERPRISES · Karanjade, RaigarhP52000005046· 27.3% built
- Omkara Hills6.6 yr overdueOmkara Builders & Developers · KARANJADE, RaigarhP52000000692· 82.7% built
- SHALIMAR SHELTERS6.6 yr overdueSADGURU ENTERPRISES · Borivali, Mumbai SuburbanP51800004740· 90.9% built
- Chetna Kunj CHS6.6 yr overdueK Merchant Construction Ltd · Borivali, Mumbai SuburbanP51800010821· 69.1% built
- SHAH GOVIND APARTMENT PHASE II6.6 yr overdueSHAH BUILDERS AND DEVELOPERS · Bhagur Rural, NashikP51600001700· 64.1% built
- TULSI AAHAN6.6 yr overdueRAJ GROUP · Ambarnath, ThaneP51700000064· 73.9% built
- VISHWAJEET ELITE6.6 yr overdueVISHWAJEET MEADOWS · Ambarnath, ThaneP51700001654· filed Dec 2018 → now Dec 2019· 31.4% built
- RUDRA6.6 yr overdueShree DPS Project and Services Pvt. Ltd. · Borivali, Mumbai SuburbanP51800010461· 90.9% built· 1 complaint
- AMBIKA HERITAGE6.6 yr overdueRADHA MEERA BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000003237· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- VENKATESH GRAFFITI PHASE 36.6 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100001000· 90.9% built· 1 complaint
- Flying Colors6.6 yr overdueNEPTUNE CONSTRUCTIONS · Kurla, Mumbai SuburbanP51800008417· filed Dec 2018 → now Dec 2019· 74.5% built
- VINAY UNIQUE GARDENS6.6 yr overdueVINAYUNIQUE DEVELOPERS · DONGRE, PalgharP99000012052· 86.4% built· 9 complaints
- JASWANTI WOODS6.6 yr overdueASHRAY REALTORS · Kurla, Mumbai SuburbanP51800002192· 90.9% built
- SAINATH HERITAGE6.6 yr overdueSAINATH ENTERPRISES · Panvel, RaigarhP52000010186· filed Dec 2018 → now Dec 2019· 90.9% built
- SILVANA COUNTY6.6 yr overdueDIAMOND PROPERTIES · CHAROLI PHATA, PuneP52100018403· 90.9% built
- Vantagio6.6 yr overdueVyankatesh Infra · Osmanpura, AurangabadP51500013507· 59.1% built
- SHRIRAM TOWER6.6 yr overdueSUDHASHRI INFRACON · Nagpur (M Corp.), NagpurP50500012525· 90.9% built
- Sundaram residency6.6 yr overdueJadhav Enterprises · Tathwade, PuneP52100000907· filed Dec 2018 → now Dec 2019· 81.8% built· 2 complaints
- AFFORDABLE HOUSING PROPOSED ON KH.NO.54,CITY SURVEY NO.173 LAYOUT PLAN NEAR SHESHNAGAR.6.6 yr overdueNagpur Improvement Trust · SHESHNAGAR, NagpurP50500017530· 58.7% built
- AAYAN- BUILDING 26.6 yr overdueGANDHI BAFNA CONSTRUCTION PVT LTD · WAGHOLI, PuneP52100007092· filed Dec 2018 → now Dec 2019· 65.9% built
- AFFAN PLAZA6.6 yr overdueTAJ BUILDERS AND DEVELOPERS · GANDHARPALE, RaigarhP52000013713· 81.8% built
- RENTAL BUILDING A-1 R26.6 yr overdueSONAM SPARK INFRA LIMITED · Thane, ThaneP51700004747· filed Sept 2020 → now Dec 2019· 56.6% built
- PENINSULA HEIGHTS6.6 yr overduePRIESKA REAL ESTATES PVT. LTD. · VIRAR WEST, PalgharP99000011703· 43.1% built
- GADIMA PARK PHASE 16.6 yr overdueAJIT BUILDERS AND DEVELOPERS · Atpadi, SangliP53100006274· 99.2% built
- PEACE VALLEY6.6 yr overdueR J DEVELOPERS · Ravet, PuneP52100012347· filed Dec 2018 → now Dec 2019· 81.4% built
- SWAPNASHILP RESIDENCY6.6 yr overdueM/S NIRMITI BUILDERS & DEVELOPERS · Junnar, PuneP52100011894· 29.5% built
- Tiara6.6 yr overdueSHETH AND POPAT ENTERPRISE · Wakad, PuneP52100007260· 26.8% built· 1 complaint
- Diamond One6.6 yr overdueDiamond Estate Builders & Developers · Nagpur (M Corp.), NagpurP50500001314· 81.8% built
- Dhoot Adi Residency-Shree Adi House CHSL6.6 yr overdueDHOOT DEVELOPERS PVT. LTD. · CHEMBUR EAST, Mumbai SuburbanP51800008557· filed Dec 2018 → now Dec 2019· 41.8% built
- CRYSTAL PARK - PHASE II6.6 yr overdueK K BUILDERS & DEVELOPERS · Palghar, PalgharP99000004379· 84.5% built
- Twin Arcs6.6 yr overdueWhite Properties and Ventures · Punawale, PuneP52100001145· 90.9% built
- QUALITY HEIGHTS I6.6 yr overdueQUALITY CONSTRUCTION CO · Thane, ThaneP51700010184· filed Dec 2018 → now Dec 2019· 90.9% built
- Park Royale AB Wing6.6 yr overdueSHIVRANJANI PROPERTIES LLP · Andheri, Mumbai SuburbanP51800001315· 96.4% built
- Megapolis Mystic - C6.6 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park, Phase 3, PuneP52100019959· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B116.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700010381· filed Dec 2018 → now Dec 2019· 56.6% built· 1 complaint
- Korgaonkar Park6.6 yr overdueASHISH ANIL KORGAONKAR · Gadhinglaj, KolhapurP53000001698· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B96.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700005264· filed Dec 2018 → now Dec 2019· 53.4% built
- 7 Ishanya6.6 yr overdueSGC Realty · Sadarbazar (CT), SataraP52700008094· 42.5% built
- SPARSH6.6 yr overdueVALUABLE DREAMSCAPE LLP · Andheri, Mumbai SuburbanP51800002394· filed Dec 2018 → now Dec 2019· 50.7% built
- MAHAVIR SYMPHONY6.6 yr overdueRAKESH AMRUTLAL SHAH · Vasai, PalgharP99000011172· filed Dec 2018 → now Dec 2019· 90.9% built
- TRIBECA6.6 yr overdueNESTOR BUILDERS & DEVELOPERS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800009815· filed Dec 2018 → now Dec 2019· 90.9% built· 2 complaints
- LAABH NEELKANTH6.6 yr overdueLAABH BUILDTECH · Thane, ThaneP51700010195· 83.9% built
- SILVANACOUNTY6.6 yr overdueDIAMOND PROPERTIES · CHARHOLI, PuneP52100002224· 85.9% built
- ARYAN HEIGHTS6.6 yr overdueAryan Construction · Haveli, PuneP52100010649· 39.5% built
- SAI RAJ6.6 yr overdueSAI DHARA ENTERPRISE · Vasai, PalgharP99000002245· 90% built
- NEPTUNE SWARAJYA SECTOR 2 - B15 AND B176.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700006446· filed Dec 2018 → now Dec 2019· 70.5% built· 2 complaints
- GRACE HEIGHTS6.6 yr overdueGRACE VENTURES · Pune City, PuneP52100009946· 68.6% built
- DISHA KUNJABAN PHASE 26.6 yr overdueDEVANAND NARAYANRAO KOTGIRE (HUF) · Wadgaon Kolhati (CT), AurangabadP51500001997· filed Dec 2018 → now Dec 2019· 90.9% built
- SOLITAIRE SEVEN6.6 yr overdueAtul Builders · BANER, PuneP52100006186· filed Dec 2018 → now Dec 2019· 90.9% built
- shree aditya residency6.6 yr overdueshree aditya associates · Sangli Miraj Kupwad (M Corp.), SangliP53100009014· 81.8% built
- BLUE DIAMOND RESIDENCY6.6 yr overdueKIMAYA CONSTRUCTION · Ambarnath, ThaneP51700002359· 90.9% built
- ARMONIA RESIDENCY6.6 yr overdueM2 DEVELOPERS · Somatane, PuneP52100013738· 81.8% built
- NAVKAR PARK6.6 yr overduePARKONS TRENDZ · Haveli, PuneP52100005084· filed Apr 2019 → now Dec 2019· 81.8% built· 1 complaint
- Pragati Residency6.6 yr overdueSiddhi Developers · Near New Polytechnic College, KolhapurP53000015144· 67.7% built
- GOLDEN WINDS Building E Phase 26.6 yr overdueGOLDEN BRICKS DEVELOPERS · Pune City, PuneP52100005025· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B66.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008931· filed Dec 2018 → now Dec 2019· 49% built· 3 complaints
- Teerth Technospace 126.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100006740· filed Dec 2018 → now Dec 2019· 90.9% built
- Bloomdale Duplex Home 46.6 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007215· filed Dec 2018 → now Dec 2019· 81.8% built
- Joy Legend Wing A6.6 yr overdueJAYANT SONI · Andheri, Mumbai SuburbanP51800005022· filed Dec 2018 → now Dec 2019· 70% built· 7 complaints
- Resham6.6 yr overdueManoj Vasudev Wadhwa · Andheri, Mumbai SuburbanP51800009249· filed Dec 2018 → now Dec 2019· 56.4% built
- Teerth Technospace 66.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100004940· filed Dec 2018 → now Dec 2019· 90.9% built
- TRISHABH SIGNET6.6 yr overdueDimension Housing Realty LLP · Kurla, Mumbai SuburbanP51800001222· 90% built· 1 complaint
- OM SHILP6.6 yr overdueOM SHILP · Haveli, PuneP52100013506· 81.8% built
- Raj - Baiju6.6 yr overdueRaj Arcade Pvt. Ltd. · Borivali, Mumbai SuburbanP51800003361· 36.4% built
- Celestine6.6 yr overdueLotus Construction · Pune City, PuneP52100002736· 39.4% built
- NEPTUNE SWARAJYA SECTOR 2 - B136.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700012000· filed Dec 2018 → now Dec 2019· 62.7% built
- VIMAL RAJ WING A-1, MEDITYARAVIRAJ COMPLEX6.6 yr overdueRITESH RAMESH JAIN · Thane, ThaneP51700007634· 84.5% built
- NEPTUNE SWARAJYA SECTOR 2 - 2B6.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700005899· filed Dec 2018 → now Dec 2019· 54.5% built
- Mohan Nano estates II6.6 yr overdueMOHAN LIFESPACES LLP · AMBERNATH, ThaneP51700013253· 90.9% built
- LANDMARK6.6 yr overdueCRESCENT REALTORS INDIA PVT LTD · Andheri, Mumbai SuburbanP51800003163· 90.9% built
- ANANDI ARPAN PHASE II6.6 yr overdueANANDI CONSTRUCTIONS · Vengurla (M Cl), SindhudurgP52900007995· 81.8% built
- SKY MAX6.6 yr overdueHARBANSLAL TULSIRAM WADHWA · Haveli, PuneP52100001534· filed Dec 2018 → now Dec 2019· 80% built
- AKSHAY RESIDENCY6.6 yr overdueRAJENDRA RAMANLAL LUNAKD · Wakad, PuneP52100005552· 40.9% built
- Life Republic Sector R3 - 3rd Avenue6.6 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Jambe, PuneP52100007511· 90.9% built· 5 complaints
- Radhe Govind Niwas6.6 yr overdueSHRIVARI PROPERTIES · Bajaj Nagar, NagpurP50500016170· 61.8% built
- KAPILASHRAM6.6 yr overdueRAMRAI Buildcon LLP · Navi Sadashiv Peth, PuneP52100018672· 70.5% built
- SPACE PALACE6.6 yr overdueSPACE ASSOCIATE · Ulawe, RaigarhP52000003658· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B 196.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009912· filed Dec 2018 → now Dec 2019· 57.1% built
- SHREE RAVI ENCLAVE6.6 yr overdueRAVINDRA DEVELOPERS PVT LTD · Nashik (M Corp.), NashikP51600011917· 90.9% built
- NEELAYA6.6 yr overdueNAIKNAVARE BUILDCON PVT LTD · TALEGAON, PuneP52100000013· 95.5% built
- VEDANT EMERALD PHASE 26.6 yr overdueNANIS BUILDCON PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500012141· 82.7% built
- SHANTI SEVEN6.6 yr overdueSHANTISTAR BUILDERS · Thane, ThaneP51700002572· 89.1% built
- NEPTUNE SWARAJYA SECTOR 2 - B86.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009785· filed Dec 2018 → now Dec 2019· 54.5% built· 3 complaints
- KANHA RESIDENCY6.6 yr overdueEKADANTA SHELTERS · Malkhed, SataraP52700008109· 15.1% built
- SHIVALAY APARTMENT6.6 yr overdueDEEPAK PANDURANG BHALEKAR · Chiplun (M Cl), RatnagiriP52800013453· 67.3% built· 3 complaints
- ANA Avant Garde Phase 16.6 yr overdueSTEELFAB ENGINEERING CORPORATION · Thane, ThaneP51700001388· filed Dec 2018 → now Dec 2019· 97.4% built· 25 complaints
- Xrbia Hinjewadi Road / Riverfront - Ph - 26.6 yr overdueXrbia North Hinjewadi Developers Private Limited · Bebad Ohol, PuneP52100000379· filed Dec 2018 → now Dec 2019· 90.9% built· 7 complaints
- SAMRTH CHAAYA6.6 yr overdueN M N DEVELOPERS · Khedshi, RatnagiriP52800002942· 57.3% built
- NEPTUNE SWARAJYA SECTOR 2 - B46.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700005949· filed Dec 2018 → now Dec 2019· 63.9% built
- DHAIRYASHEEL PRIDE6.6 yr overduePANDURANG VINAYAK KANDALGAONKAR · padatewadi, SindhudurgP52900004575· 81.8% built
- Flora6.6 yr overdueSiddhidata Construction and Siddhesh Landge Developers · Pimple Nilakh, PuneP52100016341· 81.8% built
- Elite Abodeh6.6 yr overdueGanesh Dashrath Dale · LOHGAON, PuneP52100009181· filed Dec 2018 → now Dec 2019· 97.3% built
- Tulsi Elanza6.6 yr overdueMETRO CAPITAL · Kurla, Mumbai SuburbanP51800006377· 27.3% built
- SHARADA PRIDE6.6 yr overdueSHARADA ALLIANCE PROMOTERS & BUILDERS · Phaltan (M Cl), SataraP52700003907· 44.5% built
- SHREE AMBA BUSINESS PARK WING A6.6 yr overdueSHREE AMBA BUSINESS PARK · RAHATGAON NEAR RING ROAD T-POINT, AmravatiP50300015750· 72.7% built
- Sai Tirupati Greens Phase- I6.6 yr overdueSai Tirupati Properties · Wadmukhwadi, PuneP52100010061· 81.8% built· 1 complaint
- Tulip Anchor Park6.6 yr overdueLakozy Buliders LLP · Vasai, PalgharP99000009059· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- Teerth Technospace 56.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100011316· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 2 - 1B6.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700003705· filed Dec 2018 → now Dec 2019· 55.6% built
- NEPTUNE SWARAJYA SECTOR 2 - B186.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008868· filed Dec 2018 → now Dec 2019· 57.1% built
- Vedaarya Homes6.6 yr overdueAdditya Infrastructure · Borkhedi, NagpurP50500003103· filed Dec 2018 → now Dec 2019· 90.9% built
- ROYAL ORCHID6.6 yr overdueSHRI GANESH DEVELOPERS · Kurla, Mumbai SuburbanP51800010432· 79.5% built
- SAI FORTUNE6.6 yr overdueSURESH GURALDAS THADANI · Ulhasnagar, ThaneP51700015389· 37.7% built
- BHARGAV6.6 yr overdueR N ENTERPRISES · Thane, ThaneP51700009004· 90.9% built
- Mont Vert Velocity6.6 yr overdueNiraj Kumar Associates Pvt Ltd · Pashan, PuneP52100001973· filed Dec 2018 → now Dec 2019· 90.7% built
- SHAMAL RESIDENCY6.6 yr overdueRAVINDRA GOPAL KULKARNI · Lote, RatnagiriP52800009656· 88.6% built
- PPRL Mera Ghar - Building E26.6 yr overdueParakh Plexus Realty Ltd. · Jalgaon (M Corp.), JalgaonP49900001778· 50.9% built
- Mallhar Estate6.6 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001367· filed Dec 2018 → now Dec 2019· 90.9% built
- VST3- AAKASH GANGA 66.6 yr overdueVIDARBHA TOWN DEVELOPERS · MALDONGRI ROAD, ChandrapurP50900009769· 29.5% built
- REDEVELOPMENT OF VISHVA ANAND CHS LTD6.6 yr overdueR R CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800004066· 90.9% built
- ASHWA PLATINUM6.6 yr overdueASHWAMEDH BUILDERS AND DEVELOPERS · Thane, ThaneP51700001143· 59.3% built· 1 complaint
- Chintamani Builders6.6 yr overdueChintamani Builders · Kalambhe, ThaneP51700009293· filed Dec 2018 → now Dec 2019· 90.9% built
- Leisure town6.6 yr overdueBhansali Infotech LLP · hadpsar, PuneP52100001401· filed Dec 2018 → now Dec 2019· 90.9% built· 13 complaints
- Grow More Bliss B Wing6.6 yr overdueGrowmore Space Solutions Pvt. Ltd. · Borivali, Mumbai SuburbanP51800005958· 81.8% built
- SHRI EKDANT ENCLAVE6.6 yr overdueMoreshwar Narayanrao Bhagat · Nagpur (M Corp.), NagpurP50500013928· 72.7% built
- ORION6.6 yr overdueSUDARSHAN DEVELOPERS · Haveli, PuneP52100007244· 42.4% built
- The Sacred Basil Phase II6.6 yr overdueAshapuri Realtors · Pirangut, PuneP52100001486· 81.8% built
- PRIDE REGENCY6.6 yr overdueSHAILESH CONSTRUCTION CO · Daund (CT), PuneP52100000716· 81.6% built
- NIVASA UDAAN - PHASE II6.6 yr overdueNIVASA REALTY · LOHEGAON, PuneP52100017799· 37.7% built
- BORA VILLE PHASE - II6.6 yr overdueBORA REALTIES · PUNEP52100000757· 90.9% built
- ASHOK SMRUTI DEFG6.6 yr overdueM/s Keytech · Thane, ThaneP51700000864· 84.5% built
- ARISTOLIA6.6 yr overdueFORTUNE ASSOCIATES · Hadapsar, PuneP52100001480· 38.2% built
- VARDHMAN VATIKA6.6 yr overdueDIWALI DEVELOPERS · Thane, ThaneP51700018906· 90.9% built
- Rambaug City A16.6 yr overdueShriram Developers · Shirwal, SataraP52700002887· 80.9% built
- VINAY UNIQUE HOMES6.6 yr overdueVINAYUNIQUE REALTORS · Vasai-Virar City (M Corp), PalgharP99000007717· 88.2% built· 2 complaints
- Teerth Technospace 16.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100011100· filed Dec 2018 → now Dec 2019· 81.8% built
- AKSHAT PRIME6.6 yr overdueYOGESH CONSTRUCTION · Uran, RaigarhP52000002802· 90.9% built
- JADHAV RESIDENCY6.6 yr overduePALAK BUILDERS · Vasai, PalgharP99000011045· 90.9% built
- ELITE SQUARE6.6 yr overdueSHRINIWAS ASSOCIATES · Aurangabad (M Corp.), AurangabadP51500006306· 46.4% built
- BALAJI DARPAN6.6 yr overdueBALAJI INFRA · Panvel, RaigarhP52000005816· 49.4% built
- GOVIND KRUPA6.6 yr overdueM/S C & D ENGINEER'S & DEVELOPERS · AMRAVATI, AmravatiP50300015320· 35.5% built
- Tejal Park6.6 yr overdueM/S Tejal Park · Aurangabad (M Corp.), AurangabadP51500002693· 90.9% built
- SAHIL APARTMENT6.6 yr overdueRAMESH GULAB TUPE · PANVEL, RaigarhP52000016275· 90.9% built
- Mallhar Towers6.6 yr overdueShendre and Associates · Kolhapur (M Corp.), KolhapurP53000001951· filed Dec 2018 → now Dec 2019· 81.4% built
- Raj Height6.6 yr overdueBhavani Enterprises · SHIRGOAN, ThaneP51700006732· 90.9% built
- PARK SOLITAIRE6.6 yr overdueAMAZON MANA & ASSOCIATES AOP · Andheri, Mumbai SuburbanP51800006074· filed Dec 2018 → now Dec 2019· 87.7% built· 4 complaints
- ARIHANT RESIDENCY6.6 yr overdueNIRWANA ASSOCIATES · Baner, PuneP52100011552· 69.5% built· 1 complaint
- MARATHON NEXZONE AVIOR -16.6 yr overdueSANVO RESORTS PVT. LTD. · Panvel, RaigarhP52000000502· 75.1% built· 16 complaints
- SAISERENITY6.6 yr overdueJAYINFRASTREUCTURIES · Anandwalli Nashik, NashikP51600007991· 90.9% built· 1 complaint
- Mont Vert Vesta6.6 yr overdueMont Vert Estates · Mulshi, PuneP52100003950· filed Dec 2018 → now Dec 2019· 89.1% built
- CRESENZO RESIDENCES6.6 yr overduePARESH PUJARA AND ABHIRAJ PUJARA (AOP) · Andheri, Mumbai SuburbanP51800005898· 90.9% built· 1 complaint
- KalpaVruksha B6.6 yr overdueVaichal Constructions Pvt Ltd · Mulshi, PuneP52100004001· filed Dec 2018 → now Dec 2019· 90.9% built
- UNIQUE ELITA6.6 yr overdueANKUR SHUBHAM DEVELOPERS · Andheri, Mumbai SuburbanP51800006885· filed Dec 2018 → now Dec 2019· 45.9% built· 1 complaint
- Balaji Arcade Wing C6.6 yr overdueSHIKHAR DEVELOPERS · Kalyan, ThaneP51700005709· 61.4% built
- Pristine Pacific H , I6.6 yr overdueMELANGE DEVELOPERS · Pune (M Corp.), PuneP52100001211· 90.9% built
- Sunshine Joy Phase 26.6 yr overdueGreenlife Associates · Mulshi, PuneP52100004441· filed Dec 2018 → now Dec 2019· 86.4% built
- GURU ATMAN6.6 yr overdueGURUKRUPA BUILDCON · NAVI MUMBAI, RaigarhP52000002703· 90.9% built
- SHREEJI VANDAN6.6 yr overdueSHREE LAND DEVELOPERS AND BUILDERS · Indira Nagar, NashikP51600011735· 90.9% built
- NISARG VISHWA6.6 yr overdueNISARG BUILDCON · Wakad, PuneP52100005116· 72.7% built
- Teerth Technospace 96.6 yr overdueTEERTH DEVELOPERS AND TEERTH REALTIES JV · Baner, PuneP52100004297· filed Dec 2018 → now Dec 2019· 90.9% built
- KALYANI SAI ENCLAVE6.6 yr overdueJ K BUILDERS AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500012465· 59.1% built
- ANANDTARAS HARITARA6.6 yr overdueANANDTARA PROPERTIES · Haveli, PuneP52100004122· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- LODHA FRESHIA WING D, E6.6 yr overdueLodha Developers Limited · Kalyan, ThaneP51700006149· 90.9% built
- SIRVI AVENUE6.6 yr overduePYRAMID ENTERPRISES · Karanjade, RaigarhP52000004615· 68.2% built
- ANAND VIEW A WING6.6 yr overdueSHREE ARIHANT DEVELOPERS · Vasai, PalgharP99000005956· filed Dec 2018 → now Dec 2019· 72.5% built
- NEPTUNE SWARAJYA SECTOR 2 - B56.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700011913· filed Dec 2018 → now Dec 2019· 49% built· 2 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.