RERA projects past their possession deadline
11,767 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 19 of 59
- Citrine6.8 yr overdueAchalare Welworth Associates · Marunji, PuneP52100002515· 90.9% built· 4 complaints
- ARIHANT PARK PHASE - 46.8 yr overdueMADAN NEMICHAND BAFANA · Supa, AhmednagarP52200014569· 90.9% built
- HERITAGE PRIDE6.8 yr overdueHERITAGE REALTORS · CHEMBUR, Mumbai SuburbanP51800008751· filed Sept 2018 → now Sept 2019· 50.9% built
- Shanti Elixir6.8 yr overdueDivyanand Properties LLP · Mundhawa, PuneP52100004234· filed Sept 2018 → now Sept 2019· 46.4% built
- NECTAR RESIDENCY-II6.8 yr overdueJACKPOT DEALER PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500015022· 44.5% built
- TROPICANA VILLAS PHASE 16.8 yr overdueTropicana Leisure Hospitality Pvt.Ltd · Mushet, RaigarhP52000010185· 89.1% built
- TEEJADEEP HEIGHTS6.8 yr overdueTEEJADEEP DEVELOPERS · Thane, ThaneP51700010345· filed Sept 2018 → now Sept 2019· 91.8% built· 1 complaint
- POOJA RAJAS6.8 yr overdueGokhale Constructions · Kothrud, PuneP52100013970· 81.8% built
- ATHARVA FORTUNE6.8 yr overdueATHARVA INFRASTRUCTURES · Pipla, NagpurP50500002140· 90.9% built
- GRAND TEN6.8 yr overdueGadiya Reality Scheme · GOLWADI, AurangabadP51500015430· 62.8% built
- RAGHUNANDAN-NX6.8 yr overdueVASTU DEVELOPERS · NAVAPADA GANESH NAGAR, ThaneP51700014552· 90.9% built
- SAISHREE APARTMENT6.8 yr overdueSAISHREE DEVELOPERS · Sangli Miraj Kupwad (M Corp.), SangliP53100000324· 81.8% built
- PYRAMID CITY 56.8 yr overduePYRAMID ARCADES PVT LTD · Pipla, NagpurP50500005437· filed Sept 2018 → now Sept 2019· 89.1% built· 1 complaint
- Sara Metroville B6.8 yr overdueSara Infrastructures · Punawale, PuneP52100001689· 90.9% built
- MOTIWALA PRIDE6.8 yr overdueAYYUB USMAN MOTIWALA · Solapur (M Corp.), SolapurP52600004509· 27.3% built
- Carmichael Residences6.8 yr overdueR A Realty Ventures LLP · Ward ABCD, Mumbai CityP51900001442· filed Sept 2018 → now Sept 2019· 77.2% built· 1 complaint
- KARTIK PLAZA6.8 yr overdueSUBHASH YUVRAJ MANMODE · ZINGABAI TAKLI, NagpurP50500015522· 40% built
- SWARAJ ICON6.8 yr overdueSWARAJ DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100012944· 81.8% built· 1 complaint
- SHUBHARAMBHA RESIDENCY6.8 yr overdueSANDEEP CHANDRAKANT KAKADE · Talegaon Dabhade (M Cl), PuneP52100007790· 52.7% built
- JAJOO NAIKS AMAR VRINDAVAN APARTMENT6.8 yr overdueAMAR BUILDTECH PVT LTD · TRIMURTI CHOWCK, NashikP51600008287· 81.8% built
- Sai Savitri Villa6.8 yr overdueSavitri Group · Thane, ThaneP51700010636· 90.9% built· 2 complaints
- MAHANKALI COMPLEX6.8 yr overdueUSHA RAVINDRA SAGARE HUF · NEAR MHASOBA MANDIR, SangliP53100015691· 67.3% built
- PRIME RESIDENCY6.8 yr overdueRAJESH SHANKAR KASHMIRE · PANCHVATI, NashikP51600010552· 90.9% built
- Raghunandan6.8 yr overdueSuhas Manohar Shinde · Nachane (CT), RatnagiriP52800014238· 60.9% built
- Dream Empire6.8 yr overdueSai Siddhi Developers · GANESH NAGAR, SangliP53100001530· 81.8% built
- HAPPY HOME CHS LTD6.8 yr overdueJAY ENTERPRISES · Panvel, RaigarhP52000002992· filed Sept 2018 → now Sept 2019· 68.2% built
- Nisarg Vatika6.8 yr overdueNisarg Ventures · Pimpri Chinchawad (M Corp.), PuneP52100006131· 72.7% built
- MARVEL CERISE BLDG B, C, D6.8 yr overdueMARVEL REALTORS AND DEVELOPERS LTD ·P52100002648· filed Sept 2018 → now Sept 2019· 95.2% built· 22 complaints
- VYANKATESH PRIDE6.8 yr overdueMADHURA DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500002419· 59.4% built
- Radha Madhav CHSL6.8 yr overdueShri Krishna Chaitanya Enterprises · Borivali, Mumbai SuburbanP51800005539· filed Sept 2018 → now Sept 2019· 90.9% built· 2 complaints
- RIDDHI SIDHHI APARTMENTS6.8 yr overdueM/S GOLDEE INFRASTRUCTURE · Bopele, RaigarhP52000013328· 36.4% built
- Purshattam Residency6.8 yr overdueOM ASSOCIATS · Kolhapur (M Corp.), KolhapurP53000013860· 77.6% built· 3 complaints
- Sukhwani Boulevard Commerz6.8 yr overdueVicky G Sukhwani · Next to HP Petrol Pump, Sus, PuneP52100021251· 55.5% built
- DREAMZ PARK WING A6.8 yr overdueDREAMZ INFRASPACE · Amravati (M Corp.), AmravatiP50300007239· 63.6% built
- RAVECHI DEEP6.8 yr overdueSMIT KIRAN DOSHI · Ulawe, RaigarhP52000005619· 90.9% built
- MANTRI MYSTICA A PART6.8 yr overdueOMEGA PREMISES PVT LTD · RAHATNI, PuneP52100005136· filed Sept 2018 → now Sept 2019· 81.7% built· 5 complaints
- SARANG ARYAN6.8 yr overdueARYAN ENTRPRISES · KARANJADE, RaigarhP52000003780· 72.7% built
- VENKATESH JOYNEST PHASE 36.8 yr overdueSHREE VENKATESH GROUP · Haveli, PuneP52100013900· 90.9% built
- PANORAMA PAHSE 46.8 yr overdueJEWEL HOUSING · Pune City, PuneP52100005793· filed Sept 2018 → now Sept 2019· 86.4% built
- PERFECT RESIDENCY6.8 yr overduePERFECT DEVELOPERS · Nashik, NashikP51600002318· 67.3% built
- NISARG RESIDENCY WING A6.8 yr overdueSHREE DATTAKRUPABUILDERS AND DEVELOPERS · Baramati (M Cl), PuneP52100002548· 78.2% built
- NYATI ELAN WEST II6.8 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100015826· 81.4% built
- Gayatri CHSL6.8 yr overdueKhushi Associates · Borivali, Mumbai SuburbanP51800002567· filed Sept 2018 → now Sept 2019· 90.9% built
- ALOK REGENCY6.8 yr overdueALOK CONSTRUCTION · Vasai, PalgharP99000004517· filed Sept 2018 → now Sept 2019· 80% built
- NIRMITEE LAXMINARAYAN6.8 yr overdueNIRMITEE BUILDERS & DEVELOPERS · Kudal, SindhudurgP52900007673· 77.3% built
- NOORJAHAN APARTMENT6.8 yr overdueBALAJI CHANDRABHAN PATIL · OSMANPURA, AurangabadP51500008027· filed Sept 2018 → now Sept 2019· 90.9% built
- Sai Prasad6.8 yr overdueSumit Snehashish Joint Venture · Andheri, Mumbai SuburbanP51800010933· filed Sept 2018 → now Sept 2019· 39.1% built
- VISHWAJEET PARADISE6.8 yr overdueKOHINOOR INFRA DEVELOPMENT · Ambarnath, ThaneP51700008406· filed Sept 2018 → now Sept 2019· 81.8% built· 1 complaint
- SHREE TIRUMALA PARADISE APARTMENT6.8 yr overdueROONGTA HOMES LLP · NASHIK, NashikP51600001631· 81.8% built
- SDPL Aashray Dabha6.8 yr overdueSANDEEP DWELLERS PVT. LTD. · Dabha, NagpurP50500014329· 88.3% built
- VASTU SIDDHI6.8 yr overdueSIDDHIVINAYAK GROUP · Ambarnath (R), ThaneP51700011663· 90% built
- KANAKIA HOLLYWOOD6.8 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000123· 88.5% built· 1 complaint
- Regent Orchid - Hema Niwas CHSL6.8 yr overdueRDB Mumbai Infrastructures Private Limited · Andheri, Mumbai SuburbanP51800011724· filed Sept 2018 → now Sept 2019· 90.9% built
- SAI DWARKA PHASE 46.8 yr overdueMAA SANKALP BUILDCON · YAWALEWADI, PuneP52100003592· filed Sept 2018 → now Sept 2019· 90.9% built· 3 complaints
- SHREE SAI POOJA APARTMENT6.8 yr overdueOM SAI REALTY · BADLAPUR, ThaneP51700020600· 85.5% built
- RAGHAV SANKUL6.8 yr overdueNANDKISHOR SHIVNARAYAN DUBE · Khamgaon, BuldanaP50000006634· 22.9% built
- SHREE BALAJI ENCLAVE6.8 yr overdueNabhraj Construction · Aurangabad (M Corp.), AurangabadP51500000945· 90.9% built
- PRAYAG KALASH6.8 yr overduePRAYAG DEVELOPERS · Pen (M Cl), RaigarhP52000011275· filed Dec 2018 → now Oct 2019· 90.9% built
- M/s.New Saikrupa Panvel CHS Ltd6.8 yr overdueM/s.Sai Realty · Panvel, RaigarhP52000002568· 90.9% built
- MAJESTIC HEIGHT6.8 yr overdueSIRAJ GAFOOR KHAN · Dapoli Camp, RatnagiriP52800012843· 51.8% built
- LAXMI VINAYAK6.8 yr overdueLAXMI VINAYAK · Dhayari (Part), PuneP52100002074· 90% built
- Shree Vitthal Annex6.8 yr overdueYuvraj Madolappa Chidre · CHOVISWADI, PuneP52100014925· 81.8% built
- CREST6.8 yr overdueVALSAMMA MAMACHAN ·P52100010483· 81.8% built
- RELIABLE HEIGHTS6.8 yr overdueRELIABLE BUILDERS · VIKASNAGAR, SataraP52700016158· 33.2% built
- KADIR APARTMENT6.8 yr overdueBARKAT BUILDERS AND DEVELOPERS · Dapoli Camp, RatnagiriP52800013027· 58.2% built
- SERA BELLA6.8 yr overdueSURESH FAGUNMAL CHETWANI · Tathawade, PuneP52100009897· 45.9% built
- AKIB APARTMENT6.8 yr overdueBARKAT BUILDERS AND DEVELOPERS · Dapoli Camp, RatnagiriP52800012776· 58.2% built
- Laxmi Datta6.8 yr overdueManish Bhaskar Danke · Sangli Miraj Kupwad (M Corp.), SangliP53100011734· 81.8% built
- RAJ PARK6.8 yr overdueMR SANJAY BALAPRASAD BIYANI · Nanded Waghala (M Corp.), NandedP51100012601· 54.7% built
- GURUSNEH6.8 yr overdueM M ASSOCIATES · Nashik, NashikP51600009138· filed Oct 2018 → now Oct 2019· 84.5% built
- Vedant Residency6.8 yr overdueVaishnavi Builders · Talegaon Dabhade (R), PuneP52100004823· 53.2% built
- DISHA PRIMO6.8 yr overdueJAY GANESH CORPORATE · Shirur, PuneP52100002486· 45.6% built
- SANTOSHI SRUSHTI6.8 yr overdueSHREE SANTOSHI DEVELOPERS · Haveli, PuneP52100011828· filed Oct 2018 → now Oct 2019· 90.9% built
- SWATISH6.8 yr overdueAna Developers · Kothrud, PuneP52100007676· 54.5% built
- LAXMI SHANTIBAN6.8 yr overdueLAXMI ROPERTIES · Haveli, PuneP52100009542· 90.9% built
- SANSKRUTI SAHANIVAS6.8 yr overdueGAJADATTA BUILDERS · Sangli Miraj Kupwad (M Corp.), SangliP53100000599· 90.9% built
- VISHNU VIHAR6.8 yr overdueNOBLE PROMETERS &BULIDERS · Pimpri Chinchawad (M Corp.), PuneP52100009834· 90.9% built· 2 complaints
- Pancham Phase I at Nanded City6.8 yr overdueNanded City Development & Construction Co. Ltd. · Nanded City, PuneP52100000385· 91.4% built
- CITY ELITE6.8 yr overdueM/S. STEEL CITY DEVELOPERS · ULWE NAVI MUMBAI, RaigarhP52000003317· 65% built
- ANVI PARK6.8 yr overdueDALVIADHAVPROPERTIES · Shirur, PuneP52100005557· 90.9% built
- ALPHA RESIDENCY6.8 yr overdueKonark Shakti Group of Companies · Borivali, Mumbai SuburbanP51800005227· 90.9% built
- Tejas Parishma6.8 yr overdueTejas Enterprises · Panvel, RaigarhP52000006095· 90.9% built
- CHALAT GROUP BUILDERS AND DEVELOPERS6.8 yr overdueSUVARNA SHAJI CHALAT · Vadghar (CT), RaigarhP52000014016· 90.9% built
- Tejas Ela6.8 yr overdueVijay Harinarayan Sarda · Prathamesh Park, Baner, PuneP52100016518· 68.2% built
- Dharamshi Milestone6.8 yr overdueSanjay Navinchandra Dharamshi · Bavadhan BK, PuneP52100006908· 37.6% built
- GIRNAR 1086.8 yr overduePADMAVATI BUILDERS · Haveli, PuneP52100002263· 90.9% built
- Redevelopment of Marhaba Co-operative Housing Society Limited6.8 yr overdueShree Mahavir Estates · Mumbai, Mumbai SuburbanP51800001749· filed Oct 2018 → now Oct 2019· 78.2% built
- BALAJI NIWAS6.8 yr overdueSANTOSH DINKAR NARVEKAR · PUNE, PuneP52100014262· 73.1% built
- MAHAVIR UTSAV B6.8 yr overdueRajesh Construction · Palghar, PalgharP99000015701· 90.9% built
- TROPICAL PALMS BUILDING H6.8 yr overdueOm Developers Project Green · Pimpri Chinchawad (M Corp.), PuneP52100005869· filed Oct 2018 → now Oct 2019· 59.5% built· 14 complaints
- Skyi First Bhukum Phase I6.8 yr overdueEnerrgia Skyi Realty · Bhukum, PuneP52100000462· 86.4% built· 1 complaint
- SHIV NAKSHATRA6.8 yr overdueLandmark infra · Jail Road, NashikP51600006926· 27.3% built
- Sagar Vihar Phase 46.8 yr overdueAkash Construction · Ahmadnagar (M Corp.), AhmednagarP52200011344· 52.5% built
- EKTA GREENVILLE PHASE 1 WING I AND J6.8 yr overdueEKTA HOUSING PRIVATE LIMITED · Nashik, NashikP51600001224· filed Oct 2018 → now Oct 2019· 88.1% built· 1 complaint
- The Nook Phase 16.8 yr overduePyramid Developers · Tathwade, PuneP52100004015· filed Oct 2018 → now Oct 2019· 77% built· 28 complaints
- Rachana Park Wing F6.8 yr overdueShree Construction Builders and Developers · Off Nagar Manmad Highway, AhmednagarP52200016429· 90.9% built
- M M SPECTRA6.8 yr overdueM. M. DEVELOPERS - SHRAMJIVI · Kurla, Mumbai SuburbanP51800010867· filed Oct 2018 → now Oct 2019· 98.2% built· 9 complaints
- Kandivali Shiv Krupa CHSL6.8 yr overdueNeminath Construction · Borivali, Mumbai SuburbanP51800008693· 90.9% built· 1 complaint
- Gorai Laxmi CHSL Casa Bellisimo B wing6.8 yr overdueJaydev Realtors Private Limited · Borivali, Mumbai SuburbanP51800002562· 96.4% built
- VIJAY HEIGHTS6.8 yr overdueVIJAY HEIGHTS · Vasai, PalgharP99000007422· 45.5% built
- Rainbow6.8 yr overdueSG VENTURES · Haveli, PuneP52100007423· filed Jun 2018 → now Oct 2019· 67.7% built
- Rachana Sahira Wing A6.8 yr overdueRachana construction Co. (Nagpur) Pvt. Ltd. · Nagpur (M Corp.), NagpurP50500001307· filed Oct 2018 → now Oct 2019· 90.9% built· 1 complaint
- VRINDAVAN APARTMENT6.8 yr overdueUDAY NIVRUTTIRAO PATIL · Latur (M Cl), LaturP52400013945· 10% built
- LANDMARK APARTMENT6.8 yr overdueSAND N STEEL · INDIAN, NagpurP50500014017· 4.5% built
- PATELS ELYSIUM - 16.8 yr overdueAPACE REALTY · Ambarnath(M Cl), ThaneP51700009543· 87.3% built
- Goodwill Palette6.8 yr overdueIra Ventures · Ravet, PuneP52100002390· 76.4% built
- Coral Residency B6.8 yr overdueSaanvi Landmarks Pvt.Ltd · Malwan (M Cl), SindhudurgP52900003719· filed Oct 2018 → now Oct 2019· 90.9% built
- NIVAN6.8 yr overdueM/S. PARADIGM REAL ESTATES LLP · Andheri, Mumbai SuburbanP51800011423· filed Oct 2018 → now Oct 2019· 90% built
- ATHARVA RESIDENCY6.8 yr overdueMAHENDRA BALIRAM BHOJANE · Amravati (M Corp.), AmravatiP50300014140· 27.3% built
- JASH PRIDE6.8 yr overdueTRINETRA BUILDERS AND DEVELOPERS · KARANJADE, RaigarhP52000007656· filed Nov 2018 → now Oct 2019· 90.9% built
- KAVITA PEARL6.8 yr overdueKAVITA INFRA · Kalyan-Dombivali (M Corp.), ThaneP51700007502· 90.9% built
- Kate city6.8 yr overdueSagar Mahadev Kate · Rui, PuneP52100013834· 75% built
- AARYA VASTU6.7 yr overdueDEEPESH MADHUKAR SHINDE · Tisgaon, AurangabadP51500001963· 61.4% built
- RAMAA HERITAIGE - PHASE I6.7 yr overdueWADHWA BUILDERS & DEVELOPERS · UNDRI, PuneP52100021140· 64.1% built
- MAULI PRASAD6.7 yr overduePRATIBHA ANAND SHINDE · SUPA, AhmednagarP52200016258· 69.1% built
- Raj Heights6.7 yr overdueShiv Mangal Developers · Ward FNorth, Mumbai CityP51900000631· 90.9% built· 1 complaint
- 1CITYPRIDE6.7 yr overduePANCHRATNA DEVELOPERS · Shrigonda(MCL), AhmednagarP52200014423· 40.2% built
- SARAL ORCHID6.7 yr overdueSARAL ENTERPRISE · SECTOR 19, RaigarhP52000015015· 90.9% built
- Abhishek Luxuria6.7 yr overdueAbhishek Developers · Dunetha, DamanP49500000016· 33.6% built
- SMITA GLORY A WING6.7 yr overdueMAHESH DASHRATH MHASKE · Haveli, PuneP52100014274· 29.5% built
- PUSHPCHHAYA RIVER VIEW6.7 yr overdueRAKA SURANA ASSOCIATES · Bhusawal (CT), JalgaonP49900006545· 27% built
- 93 Avenue Phase- III6.7 yr overdueRAVIRAJ BOKADIA CREATIVE · Pune City, PuneP52100019662· 54.5% built
- THE SECRET GARDEN6.7 yr overdueRAVIRAJ ABHINANDAN ASSOCIATES LLP · EMPRESS TOWER SOPAN BAUGH, PuneP52100016302· 72.7% built
- Shrirambhakti6.7 yr overdueTHAKKAR AND ASSOCIATES · Sangli Miraj Kupwad (M Corp.), SangliP53100004673· 90.9% built
- TRIMURTI PROXIMA6.7 yr overdueSUBHASH FAUJDAR YADAV · Karanjade, RaigarhP52000000746· 36.4% built
- GRAND ARENA6.7 yr overdueS H CONSTRUCTIONS · Thane, ThaneP51700012136· filed Nov 2018 → now Nov 2019· 66.3% built· 1 complaint
- LAXMI VANDAN APARTMENT6.7 yr overdueRISHI BUILDERS AND DEVELOPERS · Deolaligaon, NashikP51600001553· filed Nov 2018 → now Nov 2019· 89.1% built
- Shinde Darade Complex6.7 yr overdueSHINDE DARADE ASSOCIATES · Jalochi, PuneP52100008723· 32.3% built
- PENTAGON HEIGHTS6.7 yr overdueDAMJI HARI CONSTRUCTIONS · Bhiwandi, ThaneP51700010871· filed Nov 2018 → now Nov 2019· 90.9% built· 7 complaints
- SAI KRISHNA6.7 yr overdueSRI VARI BUILDERS · Panvel, RaigarhP52000003232· 54.7% built
- Bloomdale Row House 66.7 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007914· filed Nov 2018 → now Nov 2019· 81.8% built
- Sudarshan Lands End6.7 yr overdueJagjit estate & Devlopment Co. Pvt. Ltd · Borivali, Mumbai SuburbanP51800000373· filed Nov 2018 → now Nov 2019· 80.9% built
- Rituparna Residence6.7 yr overdueMITAALI GROOP · Katraj, PuneP52100010236· 83.8% built
- LODHA AMARA - TOWER 1 - 5, 7 - 196.7 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700001065· 78.2% built· 26 complaints
- Sulabh Monali6.7 yr overdueGokhale Constructions · Pune (M Corp.), PuneP52100014571· 90.9% built· 1 complaint
- Bloomdale Row House 56.7 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500007925· filed Nov 2018 → now Nov 2019· 81.8% built
- Construction of 534 EWS T/s under PMAY, mauza Pimpalgaon, Tah. Hinganghat, Dist. Wardha6.7 yr overdueMHADA (NAgpur Board) · Hinganghat (M Corp.), WardhaP50400016042· 76.7% built
- SAYALI COMPLEX6.7 yr overduePANDIT NANABHAU MOLAK · DEHU, PuneP52100008283· filed Sept 2020 → now Nov 2019· 72.3% built
- Sukhakarta6.7 yr overdueMAK Buildcon · Sangli Miraj Kupwad (M Corp.), SangliP53100014503· 81.8% built
- PATIL PLAZA6.7 yr overduePRIME DEVELOPERS · WARNALI, SangliP53100013269· 54.9% built
- HERAMB RESIDENCY6.7 yr overdueVISION REALITIES · Sangli Miraj Kupwad (M Corp.), SangliP53100010304· 81.8% built
- SHIVARCHAN6.7 yr overdueOjas Constructions · Vasai, PalgharP99000013953· 90.9% built
- DREAM PRIDE6.7 yr overdueDREAM WORLD CONSTRUCTION LLP · Khindwadi, SataraP52700014158· 90.9% built
- SRI SAI AMRUT6.7 yr overdueSRI VARI BUILDERS · Panvel, RaigarhP52000008969· 27.5% built
- BAGESHREE6.7 yr overdueSES ENTERPRISES · Dhayari (Part), PuneP52100006462· 41.8% built
- ANANDVAN DABHOLKAR SANKUL PHASE 36.7 yr overdueCONSORTEXE PROPERTIES PVT LTD · MHAPSEKAR TITHA, SindhudurgP52900014584· 51.5% built
- vedant imperial ABC phase 16.7 yr overdueMOHAN HARDASMAL THARWANI · Badlapur (M Cl), ThaneP51700006197· 78.5% built
- SHRI RADHIKA VIHAR6.7 yr overdueUDAY NIVARATTIRAO PATIL · MOTILAL ESTATE, LaturP52400014968· 10.9% built
- Pranjee Garden City Phase -II6.7 yr overduePranjee Properties Pvt. Ltd · Katrap, ThaneP51700005963· filed Nov 2018 → now Nov 2019· 81.5% built· 5 complaints
- VASTU GANESH6.7 yr overdueVASTUSHRADDHA BUILDERS · GOVT COLONY, SangliP53100014645· 73.1% built
- Neelkanth Enclave C Wing Arihant6.7 yr overdueBhaveshwar Properties Pvt Ltd · Kurla, Mumbai SuburbanP51800002669· 89.7% built· 2 complaints
- Diamond Crest Wing B6.7 yr overdueOm Mahavir Reality · Wagholi, PuneP52100014731· filed Dec 2021 → now Nov 2019· 90.9% built· 1 complaint
- SHREE ASHTAVINAYAK VASTU PRAKALPA6.7 yr overdueBALKRISHNA KASHINATH BHOIR · Badlapur (M Cl), ThaneP51700007934· 73.9% built
- PIYUSH APARTMENT6.7 yr overduePIYUSH ENTERPRISES · BOPELE, RaigarhP52000015435· 31.8% built
- KAMALRAJ PARIJAT A BUILDING6.7 yr overdueKAMALRAJ ASSOCIATES · DighiP52100002591· filed Nov 2018 → now Nov 2019· 90.9% built
- CHISHTIYA HEIGHTS6.7 yr overdueRAJDEEP ASSOCIATES · Kurla, Mumbai SuburbanP51800010873· filed Nov 2018 → now Nov 2019· 63.6% built
- RENUKA RESIDENCY6.7 yr overdueHIMANSHU SHAM TENDULKAR · police station, PalgharP99000009241· 81.8% built
- West Wind6.7 yr overdueKayum Ali Parkar · Dapoli Camp, RatnagiriP52800005455· 45% built
- YASHAPARTMENTKWING6.7 yr overdueBHAVESH SHANTILAL PAREKH · Palghar, PalgharP99000013382· 18.2% built
- S-Square6.7 yr overduesamarth associates · Sangli Miraj Kupwad (M Corp.), SangliP53100000523· 77.3% built
- KRISHNA CLASSIC6.7 yr overduePANDURANG MARUTI KALOKHE · Haveli, PuneP52100005965· 90.9% built
- krishna business center6.7 yr overduekrishna business center · opp. krishna vatika, JalnaP51400015451· 61.8% built
- SWAYAMBHU HEIGHTS6.7 yr overdueDHANALAXMI BUILDERS · MANJRI KHURDA, PuneP52100015250· 81.8% built
- Shree Hari complex6.7 yr overdueHari Chandra Construction · Tisgaon, AurangabadP51500013650· 63.6% built
- Choudhary Bhuvi landmarks - I6.7 yr overdueNEST DEVELOPERS · Tisgaon, AurangabadP51500004842· 54.8% built
- BLOSSOMCITY6.7 yr overdueDATTATRAY HANUMANT BORADE · Baramati (M Cl), PuneP52100004332· 26.6% built
- SAMARTH NIWAS6.7 yr overdueTHAKRE DEVELOPERS · CHOUDHARY PARK DIGHI PUNE 411015P52100005922· 72.7% built
- WEST END VILLAGE PHASE-II BUILDING - H6.7 yr overdueTHE CONSTRUCTION AND DEVELOPMENT COMPANY · Haveli, PuneP52100024034· 90.9% built
- SHIVDATTA PRASAD6.7 yr overdueSHIVDATTA BUILDERS & CONTRACTORS · Sangli Miraj Kupwad (M Corp.), SangliP53100002172· 90.9% built
- KRUSHNATARA SANKUL6.7 yr overdueVIPUL DILIP GARJE · Nashik (M Corp.), NashikP51600007734· 22.7% built
- REVELL ORCHID PHASE II BUILDING D6.7 yr overdueABHAY INDRABHAN FULFAGAR · LOHGAON, PuneP52100001922· 64.1% built
- Skyz Hill Bagade Tower6.7 yr overdueMukhtar Nisar Syed · Jaisingpura, AurangabadP51500015203· 58.6% built
- CASA LIVIA6.7 yr overdueVIKRAM PUNDALIK GADADE · ABHAY NAGAR, SangliP53100014679· 0.9% built
- VIVANTA6.7 yr overdueGopal Vishnuprasad Oza · Sangli Miraj Kupwad (M Corp.), SangliP52100003682· 40% built
- Kapila6.7 yr overdueGopal Vishnuprasad Oza · VISHRAMBAG, SangliP52100002635· 43.6% built
- PRAGATI PHASE III6.7 yr overdueM/S. PRAGATI INFRASTRUCTURES · Honaji nagar, AurangabadP51500012353· 90.9% built
- LAXMI VISHNUPURAM6.6 yr overdueLAXMI DEVELOPERS · Haveli, PuneP52100007068· 83.9% built
- KOTHARI HEIGHTS6.6 yr overdueKOTHARI AND WANDHEKAR ASSOCIATES · SHRIGONDA, AhmednagarP52200016088· 90.9% built
- AARAV BLISS6.6 yr overdueDIKSHIT RAJAN AGARWAL · WAGHOLI, PuneP52100013258· 85.8% built
- Ramkrishna6.6 yr overdueRaut Associates · Sangli Miraj Kupwad (M Corp.), SangliP53100005565· 81.8% built
- SHRI PLAZA6.6 yr overdueR G DEVELOPERS · Kolgaon, SindhudurgP52900014387· 74.1% built
- WINDFLOWER6.6 yr overdueLife Style Developers · Morewadi (CT), KolhapurP53000004913· filed Dec 2018 → now Dec 2019· 80.6% built
- PURVA RESIDENCY CONDOMINIUM6.6 yr overdueNAKSHATRA BUILDERS & DEVELOPERS · Amravati (M Corp.), AmravatiP50300008611· 32.6% built
- bhagyasiddhi heights6.6 yr overdueBHAGYA DEVELOPER · Nashik, NashikP51600006032· 67.3% built
- N G CANARY6.6 yr overdueRNA Builders (NG) · Thane, ThaneP51700000320· 39.1% built
- SADGURU RESIDENCY6.6 yr overdueRAM LAXMAN DEVELOPERS · DAIGHAR VILLAGE, ThaneP51700019675· 90.9% built
- NG GRAND PLAZA PHASE I6.6 yr overdueOM NAMAH SHIVAY DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700000068· 54.8% built
- Millenia Heights6.6 yr overdueLaxminarayan Shriramji Attal · Bhagyanagar, AurangabadP51500014763· 98.2% built
- N G ECLAT C WING PHASE I6.6 yr overdueNARINDERPAL ROSHANLAL GUPTA · Andheri, Mumbai SuburbanP51800000218· 91.8% built· 1 complaint
- SUPA HIGHTS6.6 yr overdueSAI BUILDERS AND DEVELOPERS · Supa, AhmednagarP52200013058· 90.9% built
- PANTNAGAR SARITA BUILDING CHANDRABHAGA6.6 yr overduePARICHARAK BUILDERS AND DEVELOPERS PVT LTD · Isbavi, SolapurP52600009438· 54.1% built
- BELLISIMO APARTMENTS6.6 yr overdueSARKAR CONSTRUCTIONS · kondhwa BK, PuneP52100004290· filed Jul 2019 → now Dec 2019· 90.9% built
- AAKAR ELITE6.6 yr overdueAAKAR BUILDCON · Nashik (M Corp.), NashikP51600005824· 63.6% built
- SANTOSH APARTMENTS6.6 yr overdueM/S NAMJOSHI AND DESAI ASSOCIATES · Talegaon Dabhade (M Cl), PuneP52100014235· 54.5% built
- UMIYA NAKSHATRA6.6 yr overdueM/s. Jigar Enterprise · Badlapur (M Cl), ThaneP51700008369· 90.9% built
- GULAB KUNJ6.6 yr overdueButtepatil-Sabale Properties · SHANIWAR PETH, PuneP52100002040· 41.4% built
- Vasant Vihar Co-operative Housing Society6.6 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · Kothrud, PuneP52100004322· 90.5% built
- Swapna Vastu6.6 yr overdueKrishna Developers · Nashik (M Corp.), NashikP51600011487· 63.6% built
- AARIV EXOTICA6.6 yr overdueIK ONKAR CONSTRUCTIONS · BALEWADI, PuneP52100009605· 84.5% built
- OM SAI HEIGHTS6.6 yr overdueOM SAI DEVELOPERS · Junnar, PuneP52100003063· 49.1% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.