RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 17 of 61
- DURGA HEIGHTS7.4 yr overdueSANDIP PIRAJI KOTKAR · Ahmadnagar (M Corp.), AhmednagarP52200012827· 81.8% built
- SAHAKAR DWARKA I7.4 yr overdueSANKET HOMES · PANVEL, RaigarhP52000002292· filed Jun 2018 → now Jun 2019· 81.2% built
- Regency Homes7.4 yr overdueWILSON V MANUEL GONSALVES · Vasai, PalgharP99000006502· 34.5% built
- DEZINER ASTER7.4 yr overdueDEZINERS HOMES PVT. LTD. · Ulawe, RaigarhP52000006304· 90.8% built
- HARI SPARSH PHASE III7.4 yr overdueDHARAN INFRA-EPC LIMITED · Bhagur Rural, NashikP51600000225· 90.5% built
- ARJUN RESIDENCY7.4 yr overdueVIJAY VASDEV BATHIJA · Taloje, RaigarhP52000012321· 61.5% built· 29 complaints
- GILT RESIDENCES7.4 yr overdueSAMRAT SPACES · Pune (M Corp.), PuneP52100001614· filed Jun 2018 → now Jun 2019· 18.2% built
- FLORA PHASE I7.4 yr overdueTAPADIA CONSTRUCTIONS LIMITED · TISGAON, AurangabadP51500011591· filed Jun 2018 → now Jun 2019· 79.7% built
- PAPA MAMTA RESIDENCY7.4 yr overdueANUP indrapal BASHANI · Wadagaon (CT), PuneP52100005206· 30.5% built
- BHOOMI NIWAS7.4 yr overdueBHOOMI CORPARATION · PALGHAR, PalgharP99000015823· 0.5% built
- Riverview Classic Building No.2,Phase II7.4 yr overdueRUTU BUILDERS · Kalyan, ThaneP51700001351· 98.6% built· 1 complaint
- RUSHI HEIGHTS7.4 yr overdueMEGHASHAM MALLIKARJUN YEMUL · .., SolapurP52600009148· 90.9% built
- EMERALD PH-IV7.4 yr overdueGAWADE CONSTRUCTION COMPANY · Wakad, PuneP52100001028· 76.4% built
- SIROCCO GRANDE7.4 yr overdueBENCHMARK TOWN PLANNING LLP · Punavale, PuneP52100000326· 75.3% built· 11 complaints
- AMBE KRUPA7.4 yr overdueGUDDI ENTERPRISES · Kurla, Mumbai SuburbanP51800002344· 56.6% built
- Varad Residency - Building B7.4 yr overdueDigambar Laxman Kumbhar · Jijamata nagar, PuneP52100015132· 0.5% built
- DAYALHEIGHTS7.4 yr overdueVINOD PREMCHAND CHANDWANI · Haveli, PuneP52100000191· 90.9% built
- Highrise Galaxy7.4 yr overdueHIGHRISE BUILDCON · AMBEGAON Bk, PuneP52100012996· 72.7% built
- Chhoriya - Regency7.4 yr overduePragati Infra Services Pvt. Ltd. · Kurdu, SolapurP52600001775· 81.8% built
- DREAMZ PARK WING B7.4 yr overdueDREAMZ INFRASPACE · Amravati (M Corp.), AmravatiP50300005712· 63.6% built
- SHREE SANDGURU BUILDERS AND DEVELOPERS7.4 yr overdueJAWAHAR MULCHAND BHEDA · VIRAR EAST, PalgharP99000012068· filed Jun 2018 → now Jun 2019· 90.9% built
- 36 AB - Anand Bhavan7.4 yr overdueVaswani 108 Lifespaces LLP · Andheri, Mumbai SuburbanP51800001726· 69.1% built
- BON VIVANT7.4 yr overdueMALKANI PROPERTIES · Mundhawa-Keshavnagar, PuneP52100000944· 63.3% built
- RHYTHM PARK7.4 yr overdueOM VENTURES · -, PuneP52100016489· 83.6% built
- VASUDEV SKY HIGH7.4 yr overdueSHREE PRATHAMESH DEVELOPER · Thane, ThaneP51700003503· 59% built
- Regalia Residency7.4 yr overdueRajHeramb Properties · Bavdhan, PuneP52100001872· filed Jun 2018 → now Jun 2019· 90.9% built
- SHRUSHTI-AYAAN HEIGHTS7.4 yr overdueSPARSH BUILDCON · Jail Road, NashikP51600013998· 2% built
- KRISHNA PARADISE7.4 yr overdueGOPAL KRISHNA DEVELOPERS · Kalyan-Dombivali (M Corp.), ThaneP51700012318· 90.9% built
- Lotus Laxmi 27.4 yr overdueSURYA PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100001075· 90.9% built
- SHREE SHIVNATH DEVELOPERS7.4 yr overdueSHREE SHIVNATH DEVELOPERS · Kubhephal, AurangabadP51500011333· 24.6% built
- Spectra7.4 yr overdueSaarrthi Blue Ventures Limited Liability Partnership · Kothrud, PuneP52100014363· 90.9% built· 1 complaint
- Apple Tree Cottage7.4 yr overdueSaraswati Constructions · pune, PuneP52100003385· 72.6% built
- SUNRISE HEIGHTS7.4 yr overdueUNITED DEVELOPER · Solapur (M Corp.), SolapurP52600000338· 82.5% built
- ANAND TARANG B1 AND B27.4 yr overdueR K LUNKAD BUILDERS AND PROMOTERS · Charoli Phata, PuneP52100000126· 90.9% built
- The Empire State7.4 yr overdueShivdatta Associates · Sangli Miraj Kupwad (M Corp.), SangliP53100000993· 81.8% built
- Mohan Willows I7.4 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700002731· filed Jun 2018 → now Jun 2019· 90.9% built· 1 complaint
- VASANT SPRINGWOODS PHASE 27.4 yr overdueM/S SHREE CONSTRUCTIONS · Badlapur (M Cl), ThaneP51700008622· 90.9% built
- PEBBLES 57.4 yr overdueSPACE INFRASTRUCTURE · Nagpur (M Corp.), NagpurP50500012361· 85.9% built
- VALLABH C H S LTD PROPOSED7.4 yr overdueSpendor Shelters Private Limited · Kalyan, ThaneP51700001106· 31.8% built
- Avnish Residency7.4 yr overduePrathamesh Buildwell · Collage Road, NashikP51600014671· 90.9% built
- AMITs COLORI Phase-II H and I Building7.4 yr overdueAMIT ENTERPRISES HOUSING LIMITED · Undri, PuneP52100001940· 95.5% built· 2 complaints
- KONARK SOLITAIRE - PHASE 17.4 yr overdueKONARK REALTIES J.V. · NEXT TO KDMC "A" WARD, ThaneP51700009356· 90.9% built
- TATER FLORENCE DAISY-C WING7.4 yr overdueTATER REALTY · Karjat, RaigarhP52000010005· 88.6% built
- RKL Complex B Building7.4 yr overdueRKL Complex · CHARHOLI, PuneP52100000266· 90.9% built
- ARMAAN RESIDENCY7.4 yr overdueRAIS AMIR PATEL · Panvel, RaigarhP52000005926· 50% built
- VIMAL KASTURI7.4 yr overdueAISHWARYA VIMAL BUILDERS · Haveli, PuneP52100009078· 90.9% built
- KRISHNA PARADISE7.4 yr overdueKRISHNA ENTERPRISES · Ulawe, RaigarhP52000012342· 42.5% built
- MANOHAR SHRUSTI7.4 yr overdueSAI VIDYA CONSTRUCTIONS · Kolhapur (M Corp.), KolhapurP53000007220· 92.7% built
- Rachana Madhukosh Wing C7.4 yr overdueRachana construction Co. (Nagpur) Pvt. Ltd. · Bhamti, NagpurP50500015593· 90.9% built
- GOVINDA HEIGHTS7.4 yr overdueRADHE DEVELOPERS · Nashik, NashikP51600004718· 52.7% built
- Girisparsh7.4 yr overdueEnvision Landmarks LLP · Haveli, PuneP52100001354· 90.9% built
- SAI RACHANA7.4 yr overdueSAI ASSOCIATES · Panvel, RaigarhP52000001349· 72.7% built
- Samarth Nilaya7.4 yr overdueShree Samarthkrupa Associates · Haveli, PuneP52100001584· 72.7% built
- Riddhi Siddhi Enclave7.4 yr overdueSNEHA CONSTRUCTIONS · Pune City, PuneP52100004206· filed Jun 2018 → now Jun 2019· 67.7% built· 1 complaint
- TANISHQ CASITA7.4 yr overdueNAVKAAR ASSOCIATES · AMBEGAON Bk, PuneP52100013979· 93.9% built
- AVIGHNA7.4 yr overdueAARADHYA PROMOTERS & BUILDERS LLP · Majgaon, SindhudurgP52900014032· 90.9% built
- SAI SADAN RESIDENCY 17.4 yr overdueSACHIN GANPATRAO TAWARE · Baramati (M Cl), PuneP52100008043· 90.9% built
- Venkatesh Imperia Phase I7.4 yr overdueRajHeramb Properties · PCMC, PuneP52100002796· filed Jun 2018 → now Jun 2019· 90.9% built
- PANCHARATNA COMPLEX7.4 yr overdueHONESTY BULDER AND DEVELOPERS · Lodhivali, RaigarhP52000008880· filed Jul 2018 → now Jun 2019· 90.9% built
- ANNAPURNA JEWELS7.4 yr overdueANNAPURNA CREATORS · Thane, ThaneP51700000893· 88.2% built
- Blue Bell7.4 yr overdueAbhaysinh Dhadve Patil Constructions Private Limited · Baner, PuneP52100008278· 88.2% built· 9 complaints
- Sai Pradnya7.4 yr overdueDrushti Realtors · Kurla, Mumbai SuburbanP51800007499· filed Jun 2018 → now Jun 2019· 74.1% built· 12 complaints
- Abhimanyu Nagari7.4 yr overdueAbhimanyu Group · Baramati (M Cl), PuneP52100010222· 77.3% built
- NEELKAMAL7.4 yr overdueNilkanth Associates · Talegaon Dabhade (M Cl), PuneP52100011030· 90.5% built
- PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T7.4 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000419· 78.2% built· 5 complaints
- Alankapuram ph 2 D building7.4 yr overdueR K Lunkad Housing corporation · CHARHOLI, PuneP52100000334· 81.8% built
- MAITRI SIYA APARTMENT7.4 yr overdueMAITRI AND PP REALTORS · Borivali, Mumbai SuburbanP51800012159· 35.4% built
- SHREE GOHIL MANSION CO OP HOUSING SOCIETY LTD7.4 yr overdueVIDISHA REAL ESTATE DEVELOPERS PVT LTD · Borivali, Mumbai SuburbanP51800009541· filed Jun 2018 → now Jun 2019· 90.9% built
- BHAKTI SAPPHIRE7.4 yr overdueDHAVAL BUILDERS · Pune City, PuneP52100000646· 58.3% built
- SAKET HEIGHTS APARTMENT7.4 yr overdueGEETA LAND DEVELOPERS · Deolaligaon, NashikP51600003851· filed Jun 2018 → now Jun 2019· 90.9% built
- Niramaya CHS Ltd7.4 yr overdueShamik Enterprises Pvt Ltd. · Andheri, Mumbai SuburbanP51800001624· filed Jun 2018 → now Jun 2019· 90.9% built
- LODHA BELMONDO AUGUSTA B7.4 yr overdueLodha Developers Limited · Gahunje, PuneP52100000406· 90.9% built· 2 complaints
- NAMDEV PLAZA7.4 yr overdueMETRO INFRA · Ambarnath, ThaneP51700003887· 58.2% built
- HUM SUB CHSL7.4 yr overdueSHRADDHARPAN DEVELOPERS · Borivali, Mumbai SuburbanP51800004487· filed Jun 2018 → now Jun 2019· 90.9% built· 3 complaints
- GREEN PARK PHASE 37.4 yr overdueRAJENDRA VASANTRAO INGOLE · Rui, PuneP52100008361· 81.8% built
- K K SUNDARBAN BUILDING A17.4 yr overdueK K DEVELOPERS · Girim, PuneP52100008965· 42.7% built
- TULSA NAMDEO RESIDENCY7.4 yr overdueRAM VASDEV BATHIJA · Ulawe, RaigarhP52000005472· 56.8% built· 1 complaint
- Yashwin Anand7.4 yr overdueVilas Javdekar & Sanjeevani Developers LLP · Sus, PuneP52100000012· 90.9% built
- VARDHAMAN RESIDENCY7.4 yr overdueVARDHAMAN ASSOCIATES · Wakad, PuneP52100001375· 70.5% built
- Dreamcastle7.4 yr overdueSancheti Space · Wakad, PuneP52100002264· 84.8% built
- Vrindavan Park7.4 yr overdueMohammed Salim Yusuf · Kalyan, ThaneP51700003010· 88.5% built
- DEVALAYA PHASE 17.4 yr overduePRASHANT SUDHAKARRAO KASHETTIWAR · BHADRAWATI, ChandrapurP50900011153· 35.4% built
- GALAXEE APARTMENT7.4 yr overdueHASMUKH INDRADEV GUPTA · LONAVALA, PuneP52100014995· 90.9% built
- NEELKANTH RESIDENCY7.4 yr overdueSHIVSHAKTI ASSOCIATES · Chikhali Bk., PuneP52100011342· filed Jun 2018 → now Jun 2019· 56.4% built
- TANVI RESIDENCY7.4 yr overdueARM ENGINEERS · Shirur, PuneP52100003796· 90.9% built
- VIVAAN7.4 yr overduePADALE CONSTRUCTIONS PVT LTD · Mahalunge, PuneP52100007627· 18.9% built
- PRERANA7.4 yr overdueBPN ASSOCIATES · Pune (M Corp.), PuneP52100004966· 52.7% built· 1 complaint
- Girnar Tirth7.4 yr overdueParshwa Associates · Kalyan, ThaneP51700007746· 45.5% built· 2 complaints
- Sairah7.4 yr overdueMetro Associates · Andheri, Mumbai SuburbanP51800005677· 70.5% built
- Uma Vatika7.4 yr overdueUma Creative · Ambarnath, ThaneP51700003281· 66.8% built
- Greens Centre7.4 yr overdueAMJ Land Developers · Chinchwad, PuneP52100013159· 81.8% built
- INFINITY TOWER A WING7.4 yr overduePURPLE BUILDCON · Punawale, PuneP52100002680· 75.7% built
- LALI RESIDENCY7.4 yr overdueARCHANA DEVELOPERS · GULTEKADI PUNE, PuneP52100008977· 81.8% built
- SARASWATI APARTMENT7.4 yr overdueGANESH SAKHARAM KANDEKAR · Bharana Naka, RatnagiriP52800010417· 63.6% built
- SHREE RADHE COMPLEX7.4 yr overdueSHRIKRUSHNA DEVELOPERS · Nagpur (M Corp.), NagpurP50500006951· filed Jun 2018 → now Jun 2019· 81.8% built
- NIVASA UDAAN7.4 yr overdueNIVASA REALTY · LOHGAON, PuneP52100006335· 51.8% built
- BEACON CHSL7.4 yr overdueBHUSHAN ANANT VICHARE · Borivali, Mumbai SuburbanP51800011740· filed Jun 2018 → now Jun 2019· 48.2% built
- YOGRAJ SRUSHTI7.4 yr overdueYOGRAJ GROUP · AURANGABAD, AurangabadP51500015073· 42.7% built
- SHREE GURUDEV RESIDENCY7.4 yr overdueNITIN SAHEBRAO UMAP · Amravati (M Corp.), AmravatiP50300013548· 30% built
- MARATHON EMBLEM-17.4 yr overdueUNITED ENTERPRISES · Kurla, Mumbai SuburbanP51800000645· 63.3% built
- PLATINUM PRIDE B WING7.4 yr overdueSHREE ASHTAVINAYAK DEVELOPERS · NEAR GOKUL DAIRY, RaigarhP52000004013· 67.7% built
- Tirumala Habitats7.4 yr overdueAAP Realtors Ltd. · Kurla, Mumbai SuburbanP51800004278· 96.1% built· 17 complaints
- Vibha7.4 yr overdueBKP Infraa · NARHE, PuneP52100005970· filed Jun 2018 → now Jun 2019· 42% built
- Alankar E building7.4 yr overdueR K Lunkad Housing Company · charoli, PuneP52100000231· 81.8% built
- August Homes Phase II7.4 yr overdueChampalal Kanhaiyalal Khinvasara · Khinvasara Park, AurangabadP51500003877· 81.8% built
- SHREEJI DREAMS7.4 yr overdueSHREEJI DEVELOPERS · Bhosari, PuneP52100003437· 43.6% built
- OAKWOOD HILLS7.4 yr overdueSHARAD SOPAN SHENDE · Baner, PuneP52100001235· 39.5% built
- LAKE CITY PHASE-17.4 yr overdueSADANAND LAXMANRAO PATIL · Sudhagad, RaigarhP52000001648· 70.6% built
- MITHA NAGAR ARCHANA CHS LTD7.4 yr overdueDHANSHREE DEVELOPERS PVT LTD · Borivali, Mumbai SuburbanP51800013116· 67.5% built· 3 complaints
- UMIYA DARSHAN7.4 yr overdueSHREE UMIYA GROUP · Badlapur (M Cl), ThaneP51700008860· filed Jun 2018 → now Jun 2019· 70.5% built· 2 complaints
- VASANT ELITE7.4 yr overdueM/S VASANT BUILDERS AND DEVELOPERS · Kalyan, ThaneP51700003400· filed Jun 2018 → now Jun 2019· 90.9% built
- AMRITA PRIVE7.4 yr overdueSKREE KRISHNA PROPERTIES · Kurla, Mumbai SuburbanP51800001593· 66.8% built
- ABHINANDAN HEIGHTS7.4 yr overdueABHAY CHANDMAL JAIN · MAKHAMALABAD, NashikP51600015311· 73.2% built
- NYATI EVARA I7.4 yr overdueNYATI BUILDERS PRIVATE LIMITED · UNDRI, PuneP52100000455· 89.2% built· 2 complaints
- SIDDHICITY7.4 yr overdueSiddhitech Homes Private Limited · Ambarnath, ThaneP51700001597· filed Jun 2018 → now Jun 2019· 85.2% built· 24 complaints
- ARTEMIS7.4 yr overdueCALYX ESTATES · Wadgaon Bk, PuneP52100002256· filed Jun 2018 → now Jun 2019· 90.9% built
- MAITRI HILLS7.4 yr overdueESHWAR ENTERPRISES · Badlapur (M Cl), ThaneP51700011254· 54.5% built
- OZONE7.4 yr overdueAMMA BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600011883· filed Jun 2018 → now Jun 2019· 90.9% built
- Swastik7.4 yr overdueAditya Infrastructure · Karjat, RaigarhP52000009322· filed Jul 2018 → now Jun 2019· 47.3% built
- Prudentia - Phase 17.4 yr overdueVilas Javdekar Eco Shelters Private Limited · Wakad, PuneP52100000114· 66.7% built
- Rolling Hills7.4 yr overdueSHIVNERI ASSOCIATES · Haveli, PuneP52100001755· 81.8% built
- SAIKRUPA CHS7.4 yr overdueHASMUKH R HIRANI · Borivali, Mumbai SuburbanP51800008274· 29.5% built
- SAISHA RESIDENCY7.4 yr overdueSAISHA DEVELOPERS · Panvel, RaigarhP52000011420· filed Jun 2018 → now Jun 2019· 90.9% built
- COSMOS ENCLAVE7.4 yr overdueASHIRWAD DEVELOPERS · Thane, ThaneP51700001476· 33.9% built· 1 complaint
- NAVKAR - B building7.4 yr overdueMAJESTIQUE LIFESPACES LLP · Kondhwa BK, PuneP52100001335· 99.5% built
- Eastwoods7.4 yr overdueSRS PROJECTS JV · kondhwa khurd, PuneP52100001430· filed Jun 2018 → now Jun 2019· 90.9% built
- Star City7.4 yr overdueYasmeen Gulaam Tandel · Shringartali, RatnagiriP52800008558· 51.8% built
- Eco Roshni - Redevelopment of Nai Roshni CHSL7.4 yr overdueEcohomes Constructions Pvt. Ltd. · Andheri, Mumbai SuburbanP51800002116· 80.9% built· 1 complaint
- SRI HERITAGE7.4 yr overdueFOURWAY REALTY · Ambarnath, ThaneP51700004111· 77.3% built· 1 complaint
- Eves Garden Phase V7.4 yr overdueSancheti Properties · Mundhwa, PuneP52100004610· 50% built
- 1 Hallmark Avenue Phase I7.4 yr overdueRajHeramb Properties · Ravet, PuneP52100002760· filed Jun 2018 → now Jun 2019· 89.1% built
- KK SHRIRAM7.4 yr overdueKOKANE BUILDERS · Pimpri Chinchawad (M Corp.), PuneP52100011061· 90.9% built
- RIDDHI NAGRI WING A7.4 yr overdueVIBHA RAJESH THAKUR · Kosara, ChandrapurP50900014207· 82.2% built
- MORYA PARK PHASE II7.4 yr overdueHARSIDDHI BUILDERS · HARSUL, AurangabadP51500015005· 22.7% built
- Vertical Oriana Phase II7.4 yr overdueVertical Infra · Mundhwa, PuneP52100003699· 33.9% built
- JAI RESIDENCY7.4 yr overdueRAJWADE DEVELOPERS · Ambegaon Budruk, PuneP52100010647· 90.9% built
- NEELKANTH JYOT7.4 yr overduePRAPTI ENTERPRISES · Sape, ThaneP51700010769· 90.9% built
- Sari Oshiya Park7.4 yr overdueVijaykumar Fulchand Bafna · kondhwa BK, PuneP52100011977· 78.2% built
- S3 PRIME7.4 yr overdueS-3 PROPERTIES · Sus, PuneP52100002314· 60% built
- BHAIRAAV SIGNATURE7.4 yr overdueSHARPMIND INFRASTRUCTURE PRIVATE LIMITED · Thane, ThaneP51700003768· filed Jun 2018 → now Jun 2019· 98.2% built
- UNIQUE GREEN7.4 yr overdueMADHU HARSHAD DOSHI · Thane (M Corp.), ThaneP51700009563· filed Jun 2018 → now Jun 2019· 90.9% built· 11 complaints
- Twin Tower7.4 yr overdueRoyal Unicorn · Bhumkar Vasti, PuneP52100008672· 90.9% built
- PRISTINE VILLAS PHASE II7.4 yr overdueATHARV DEVELOPERS · Karla, PuneP52100004703· 23.6% built
- INFINITY TOWER - B WING7.4 yr overdueTULIP DEVELOPERS · Punawale, PuneP52100004824· 77.7% built
- SUVIRA NEST7.4 yr overdueSUVIRA GROUP ·P52100011278· 72.1% built
- SAMARTH ANGAN7.4 yr overdueSAMARTH KRUPA DEVELOPERS · Malwan (M Cl), SindhudurgP52900010854· 90.9% built
- SRISHTI ELEGANCE7.4 yr overdueSWASTIK REALTORS · Kurla, Mumbai SuburbanP51800000568· 90.9% built
- SINDHU SRUSHTI7.4 yr overdueSHREE VIGHNAHAR PROMOTERS AND BUILDERS PVT LTD · Junnar, PuneP52100005663· 78% built
- APPLE AROMA7.4 yr overdueAPPLE BUILDCON · Man, PuneP52100001186· 8.6% built
- Sahajeevan Residency Bldg 2, C-Wing7.4 yr overduePappu Developers & Group · Kalyan, ThaneP51700010437· 81.8% built
- SWAPNASHILP7.4 yr overdueSHREEJI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100011002· 86.4% built
- SONA ESTATE7.4 yr overdueGHARKUL DEVELOPERS · Baramati (M Cl), PuneP52100013167· 68.3% built
- XRBIA HINJEWADI ROAD/RIVERFRONT-PH-17.4 yr overdueXrbia North Hinjewadi Developers Private Limited · Bebad Ohol, PuneP52100012738· 90.9% built· 2 complaints
- HEAVEN HILLS7.4 yr overdueXL REALTORZ · Palghar, PalgharP99000002974· filed Jun 2018 → now Jun 2019· 81.8% built· 2 complaints
- Nishant iken Phase 17.4 yr overdueGanesh kashiram ahire · Nashik (M Corp.), NashikP51600004851· 76.1% built
- FLORIDA RIVER BANK7.4 yr overdueONE EARTH · Mundhawa, PuneP52100000236· 90.9% built
- Nakshatra Primus7.4 yr overdueJSB Dream Homes Private Limited · Vasai, PalgharP99000006041· filed Jun 2018 → now Jun 2019· 87.3% built· 1 complaint
- Navkar A building7.4 yr overdueMAJESTIQUE LIFESPACES LLP · Kondhwa BK, PuneP52100001901· 99.5% built
- Shree Balaji Nagar7.4 yr overduePradip Badrinarayan Mundada · Kopargaon (M Cl), AhmednagarP52200013077· 78.2% built
- Venkatesh Galaxy7.4 yr overdueVenkatesh Associates · Tilekar Nagar, PuneP52100006088· 51.1% built
- IMPERIAL MEADOWS PHASE 17.4 yr overdueTALWARE BUILDERS PRIVATE LIMITED · Nashik, NashikP51600014067· 38.5% built
- SHUBH NAKASHTRA7.4 yr overdueSHUBH DEVELOPERS · RAHU HOTEL, NashikP51600010875· 63.6% built
- KARMAA PINNACLE7.4 yr overdueKARMAA BUILDERS · Nashik Road, NashikP51600001393· 90.9% built· 4 complaints
- CRYSTAL TOWER7.4 yr overdueASIF SATTAR PATHAN · Solapur (M Corp.), SolapurP52600010080· 49.1% built
- Krishna Kunj7.4 yr overdueRajendra Dinkar Phatarpekar · Kasai, SindhudurgP52900004075· 24.5% built
- MAJESTIC PARADISE7.4 yr overdueBURHANI BUILDER AND LAND DEVELOPERS · Palakwadi (Wardha), WardhaP50400002111· 47.3% built
- SAI GANESH APARTMENT7.4 yr overdueSHRI DATTAKRUPA DEVLOPERS · Lanja (CT), RatnagiriP52800004959· filed Jun 2018 → now Jul 2019· 72.7% built
- SHOPPERS SQUARE7.4 yr overdueYUSUF JAMAL SHAIKH · Solapur (M Corp.), SolapurP52600004287· 68.2% built
- SHREE GANESH IMPERIAL7.4 yr overduePRAKASH RAMAN CHAUDHARI · Shahade (r), NandurbarP49700008973· 77.3% built
- HOLLYHOCK CITY7.4 yr overdueKate Moze Associates · LOHGAON, PuneP52100013107· 70.2% built
- AMBAI RESIDENCY7.4 yr overdueVASANT MUKUNDAS SHEDJI · Sangli Miraj Kupwad (M Corp.), SangliP53100000353· 58.6% built
- PUSHPVIHAR7.4 yr overdueA K ENTERPRISES · Aurangabad (CB), AurangabadP51500006569· 68.4% built
- NAVNATH APARTMENT7.3 yr overdueAARTI ESTATES · Ward FSouth, Mumbai CityP51900012813· filed Jul 2018 → now Jul 2019· 90.9% built
- SHIVNERI7.3 yr overdueAAVISHKAR ASSOCIATES · Kalyan, ThaneP51700008705· filed Dec 2018 → now Jul 2019· 90.9% built
- SHIV OM PLAZA7.3 yr overdueSHIVSHAKTI ENTERPRISES · Khedshi, RatnagiriP52800001921· 44.5% built
- VISHWA LAXMI7.3 yr overdueSANTOSH RAMCHANDRA JAGTAP · Trishul Housing Society, PuneP52100010518· 90.9% built
- CENTURY PLAZA7.3 yr overdueSURABHI DEVELOPERS · Ichalkaranji (M Cl), KolhapurP53000002854· 90.9% built
- SHANTI VIJAY7.3 yr overdueNavkar Infra Projects · Borivali, Mumbai SuburbanP51800000790· 90.3% built
- GOVIND PLAZA7.3 yr overdueG P DEVELOPERS · NEAR COURT BUILDING WANLESWADI, SangliP53100008021· 59.1% built
- SHIVSAMBO NILAYAN7.3 yr overdueSHUBHANGI PRAMOD RISAWADE · Sangli Miraj Kupwad (M Corp.), SangliP53100007152· 81.8% built
- ADIRAJ RESIDENCY7.3 yr overdueKHORJUVEKAR BUILDERS & DEVELOPERS · Sawantwadi (M Cl), SindhudurgP52900007870· 77.3% built
- WATER EDGE7.3 yr overdueRAYKAR MARATHE DEVELOPERS · PUNE, PuneP52100008074· 11.8% built
- THE CROWN7.3 yr overdueABC DEVELOPERS · Hingoli, HingoliP51200012404· 53% built
- SAI SIDDHI7.3 yr overdueDHARMENDRA SINGH PARIHAR · SAPHALE, PalgharP99000014781· 52.7% built
- ARIHANT VILLA7.3 yr overdueDEEPA MAHAVEER KABADGE · Sangli Miraj Kupwad (M Corp.), SangliP53100006413· 78.2% built
- MAHADKAR RESIDENCY7.3 yr overdueP.V,Mahadkar and Associates · Kothrud, PuneP52100006972· 99.9% built
- MARUTI DARSHAN7.3 yr overdueKOMAL DREAM BUILDERS PRIVATE LIMITED · Thane, ThaneP51700002727· 73.4% built
- MAHALAXMI SANYOG PARK7.3 yr overdueMAHALAXMI BUILDERS AND DEVELOPERS · Besa, NagpurP50500006225· 71.7% built
- PEARL RESIDENCY - WING-A, RESIDENTIAL PHASE - I7.3 yr overdueGIRIRAJ ENTERPRISES · Andheri, Mumbai SuburbanP51800009344· 94.1% built· 2 complaints
- GOVIND SMRUTI7.3 yr overdueB.Kalyanji Realty · Khalapur, RaigarhP52000002247· 82.3% built
- PEARL RESIDENCY - WING-A, COMMERCIAL PHASE-II7.3 yr overdueGIRIRAJ ENTERPRISES · Andheri, Mumbai SuburbanP51800004037· 69.5% built
- Shiv Elite Phase III7.3 yr overdueOm Shivam Buildcon Private Limited · Shankarpur, NagpurP50500005732· 89.1% built
- Guru Villa7.3 yr overdueAllwin Infrastructure · Nashik (M Corp.), NashikP51600011745· 81.8% built
- SAI VISHWANGAN7.3 yr overdueAB Reality · Shirwal, SataraP52100006939· 90.9% built
- KARMAA PINNACLE7.3 yr overduePINNACLE HABITATS LLP · Nashik, NashikP51600009298· 73.6% built
- Nakshatra I-Land - 27.3 yr overdueEllora Homemakers Pvt. Ltd. · Moshi, PuneP52100007078· 90.9% built
- SHAH ARCADE III7.3 yr overdueSHAH HOUSECON PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003642· filed Jul 2018 → now Jul 2019· 95.9% built· 3 complaints
- Shivmudra Darshan Appartment7.3 yr overdueShivmudra Builders and Developers · Nashik, NashikP51600012624· filed Jul 2018 → now Jul 2019· 65.5% built
- Shubhankar Heights7.3 yr overdueSurekha Landmarks Private Limited · Haveli, PuneP52100003406· 31.8% built
- CELLO DECENT HOMES PHASE 27.3 yr overdueDECENT HOMES · PALGHAR, PalgharP99000008582· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.