RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 31 of 59
- Gayatri CHSL 8th 9th floor4.6 yr overdueKhushi Associates · Borivali - West, Mumbai SuburbanP51800024958· 90.9% built
- SAMRUDDHI SANKUL4.6 yr overdueBUILD TECH DEVELOPERS & BUILDERS · Karanje Tarf Satara (CT), SataraP52700011303· 90.9% built
- STKANWARRAMPALACIOPHASE24.6 yr overdueVINOD PREMCHAND CHANDWANI · chikhli, PuneP52100000386· 90% built
- SHIRKE AND PATIL ASSOCIATES4.6 yr overdueSHIRKE AND PATIL ASSOCIATES · PIMPLE SAUDAGAR, PuneP52100016444· 68.2% built
- NEW PRAKASH APARTMENT CHS4.6 yr overdueJASMINE REALTY · Thane, ThaneP51700007828· filed Dec 2019 → now Dec 2021· 58.2% built· 1 complaint
- Q Residences R14.6 yr overdueAurum RealEstate Developers Limited · Thane, ThaneP51700001722· 95.1% built· 4 complaints
- GANRAJ HEIGHTS4.6 yr overdueBHUDHAN CONSTRUCTION · Haveli, PuneP52100004465· filed Dec 2019 → now Dec 2021· 90.9% built
- SHAHS GARDEN RESIDENCY PHASE II4.6 yr overdueSHAH BUILDERS AND DEVELOPERS · Bhagur Rural, NashikP51600001356· 63% built
- ABRI NEST4.6 yr overdueABUFAIZ RABBANI KHAN · SECTOR 06, RaigarhP52000016347· 63.6% built
- MANNAT4.6 yr overdueJayshree Builders · Kalyan, ThaneP51700014298· 90.9% built
- SAISH APARTMENT4.6 yr overdueANIKET CHAVAN AND ASSOCIATES · Songaon Tarf Satara, SataraP52700008293· 72.7% built
- LAIJAI NAGARI 14/A/14.6 yr overdueKAMLESH BACHEWAR · Wadi Bk., NandedP51100002964· 63% built
- Mango Homes4.6 yr overdueAshirvad Projects · SHANKAR NAGAR, RaigarhP52000006969· 63.3% built
- SANDHU PALACE A WING4.6 yr overdueSANDHU BUILDERS · Andheri, Mumbai SuburbanP51800001610· 90.9% built· 1 complaint
- SHRI SAI DARSHAN4.6 yr overdueOM SAI BUILDERS AND DEVELOEPRS · Palghar, PalgharP99000013904· 90.9% built
- Horizon Estate4.6 yr overdueGreenscape Kalpana Struct-Con · Uran, RaigarhP52000000107· 90.9% built
- GULMOHAR PARK4.6 yr overdueSIDDHIVINAYAK DEVELOPERS · Haveli, PuneP52100006529· filed Dec 2020 → now Dec 2021· 24.5% built
- Hansprit Residancy4.6 yr overdueHPDEVELOPERS · Warasgaon, RaigarhP52000011732· 48.6% built
- PARAS-VISTA4.6 yr overduePARAS DEVELOPERS · WAKAD, PuneP52100010721· 81.4% built
- Ganraya Mall phase1 wing B4.6 yr overduePrakash Realty · Daund (M Cl), PuneP52100005707· filed Dec 2019 → now Dec 2021· 72.7% built
- Atrium Skyward4.6 yr overdueATRIUM HOMES LLP · Hole Vasti, PuneP52100002923· 90.9% built· 1 complaint
- Anmol Nayantara City One phase 44.6 yr overdueBafna Realtors Pvt Ltd · Nashik, NashikP51600000299· filed Dec 2019 → now Dec 2021· 71.2% built
- Shhraddha Ellegance Building B4.6 yr overdueShhraddha Properties · Solapur (M Corp.), SolapurP52600000096· filed Dec 2019 → now Dec 2021· 90.9% built· 1 complaint
- STAR CITY4.6 yr overdueCITY ENTERPRISES · MAMDAPUR, RaigarhP52000015102· 81.8% built
- PANKAJ RESIDENCY4.6 yr overduePANKAJ HOMES · KARJAT, RaigarhP52000007097· 90.9% built
- AASARA CO-OP. HOUSING SOCIETY LTD.4.6 yr overdueSHREE SAIBABA GRIHANIRMITI PRIVATE LIMITED · Thane, ThaneP51700012205· filed Dec 2019 → now Dec 2021· 44.8% built· 1 complaint
- SAI PARADISE4.6 yr overdueSHIV CONSTRUCTIONS · Punavale, PuneP52100002193· 94.5% built· 4 complaints
- AADITYA GURUKRUPA4.6 yr overdueARVIND MAHADEV SAWLEKAR · NEAR PARAMOUNT HOSPITAL, RaigarhP52000014717· 90.9% built
- NARAYANI PARK4.6 yr overdueSHIV CONSTRUCTION · NAGESHWAR COLONY, JalgaonP49900017375· 9.8% built
- Redevelopment of Sultanabad Darshan CHS Ltd4.6 yr overdueAFTAB CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800011533· filed Dec 2017 → now Dec 2021· 90.9% built
- 212 RIVERWALK4.6 yr overdueRAMESH BUILDERS (INDIA) · Haveli, PuneP52100001010· filed Dec 2019 → now Dec 2021· 85.5% built
- Irene4.6 yr overdueANGAL & CO · Erandwane, PuneP52100015640· 90.9% built
- Ameya Woods4.6 yr overdueAmeya Squares · Vasai, PalgharP99000006892· 90.9% built
- Bhoomi Acres M wing4.6 yr overdueV R Constructors Private Limited · Thane, ThaneP51700019235· 48.4% built
- Maple Terraces Building No. B-104.6 yr overdueMessrs. Axis Dwellings LLP · shelwali, PalgharP99000008935· filed Mar 2018 → now Dec 2021· 90% built
- embassy4.6 yr overdueKukreja embassy AOP · Nagpur (M Corp.), NagpurP50500009891· 53.6% built
- FORTUNE PARADISE4.6 yr overdueDARSHAK BHUPATRAI SHAH · Daman, DamanP49500000002· filed Dec 2019 → now Dec 2021· 81.8% built
- NEELKANTH INDUSTRY4.6 yr overdueSurendra Ramanlal Patel · Vasai East, PalgharP99000024700· 39.8% built
- REGENT GALAXY4.6 yr overdueREGENT CONSTRUCTIONS · Borivali, Mumbai SuburbanP51800001438· filed Dec 2018 → now Dec 2021· 99.1% built
- DIVINE TOWERS4.6 yr overdueKABRA ESTATE AND INVESTMENT CONSULTANTS · MALAD WEST, Mumbai SuburbanP51800016392· 98.6% built
- GAURI-PREM ARCADE4.6 yr overduePATIL AND MANURE ASSOCIATES · MANRAJ PARK,JALGAON, JalgaonP49900018809· 90.9% built
- RAM VILLA4.6 yr overdueSHREE RUDRA ENTERPRISES · Uran, RaigarhP52000014853· 90.9% built
- Siddhivinayak Solitaire4.6 yr overdueAshok Motiram Jaidhara · Ulwe, RaigarhP52000008999· 90.9% built
- ANANDI DREAMS4.6 yr overdueANANDI INFRASTRUCTURE (INDIA) PRIVATE LIMITED · NAVSARI, AmravatiP50300019945· 27.3% built
- VISTAS CENTREPOINT4.6 yr overdueCavalcade Properties Private Limited · MOHAMMADWADI, PuneP52100016359· 81.8% built· 1 complaint
- YUTHIKA ENCLAVE4.6 yr overdueAJIT DEVELOPERS AND COMPANY · Haveli, PuneP52100024706· 81.8% built
- Tulsi Centre Point4.6 yr overdueNavkar developers · NERAL, RaigarhP52000000571· filed Dec 2019 → now Dec 2021· 52.3% built
- Shree Sukhprada Apartment4.6 yr overdueMilind Vasant Vani · Kalyan, ThaneP51700015177· 90.9% built
- ANKUR PRIME4.6 yr overdueANKUR DEVELOPERS · Mandlik Compound, RatnagiriP52800001653· 81.8% built
- KANHA SHYAM RESIDENCY 24.6 yr overdueNEW ROYAL ENTERPRISES · KARANJADE, RaigarhP52000015021· 90.9% built
- SPARSH4.6 yr overdueIndiapride Infraspaces · Thane, ThaneP51700001008· 35% built
- KIRANS SHREE SMARAN4.6 yr overdueKIRAN VASANT THANDRE · KASAR VADAVALI, ThaneP51700016457· 73.5% built
- GARDENIA4.6 yr overdueM/S KAMDHENU LIFESPACES · GHOTGAON, RaigarhP52000015108· 89.1% built
- Apana ghar4.6 yr overdueWeston Land Developers · molana azad chowk, AhmednagarP52200026894· 70.6% built
- Nakshatra Greens - Phase II4.6 yr overdueJSB Buildcon LLP · Vasai, PalgharP99000008753· filed Dec 2019 → now Dec 2021· 90.9% built· 1 complaint
- MANGALDEEP APARTMENT4.6 yr overdueVINAYAK PREMISES PRIVATE LTD · PATHARDI PHATA, NashikP51600019914· 81.8% built
- ASHIRWAD CHS LTD4.6 yr overdueASHIRWAD CO-OPERATIVE HOUSING SOCIETY LTD · Andheri, Mumbai SuburbanP51800008610· 81.8% built
- DS VRINDAVAN4.6 yr overdueDSP DEVELOPERS · DHANORIP52100002095· 60.7% built
- NATHANI HEIGHTS REHAB4.6 yr overdueNathani Parekh Constructions Private Limited · Mumbai City, Mumbai CityP51900008587· 90.9% built
- SAI KIRAN4.6 yr overdueUJWALA BABAN GHADGE · NAVI MUMBAI, RaigarhP52000015403· 90.9% built
- CARNATION4.6 yr overdueKANAKLAXMI DEVELOPERS · Nashik, NashikP51600012060· filed Dec 2019 → now Dec 2021· 90.9% built
- Dreams Park - Bliss4.6 yr overdueMohd Khalid Mohd Iqbal Shaikh · Neral Mamdapur Sankul, RaigarhP52000016115· 90.9% built
- AARYA CASA4.6 yr overdueRAJVEER INFRA PROJECTS · Aurangabad (M Corp.), AurangabadP51500008230· filed Jul 2019 → now Dec 2021· 45.5% built· 1 complaint
- KEHKASHAN APARTMENT4.6 yr overdueA M ENTERPRISES · MAMDAPUR, RaigarhP52000016006· 9.1% built
- Royale4.6 yr overdueAshoka Infraways Limited · Wadala, NashikP51600008360· filed Dec 2018 → now Dec 2021· 90.5% built
- Kalpataru Ph-24.6 yr overdueAshoka Infraways Limited · Near Indian Oil Corporation Petrol Pump, Chunchale Shiwar, NashikP51600018371· 54.5% built
- SHIV SAI DARSHAN4.6 yr overdueSAI BALAJI DEVELOPERS · Kalyan-Dombivali (M Corp.), ThaneP51700009348· filed Dec 2019 → now Dec 2021· 56.4% built
- CHARKOP JINPREM CO OP HOUSING SOCIETY LTD4.6 yr overdueCHARKOP JINPREM CO. OP. HOUSING SOCIETY LTD · KANDIVALI WEST, Mumbai SuburbanP51800014718· 56.8% built
- MAPLE4.6 yr overdueSHREEJI DEVELOPERS · Thane, ThaneP51700005148· filed Dec 2019 → now Dec 2021· 79.4% built
- green vally4.6 yr overdueLAXMIKANT PRABHAKAR JOSHI · SAI NAGAR, AmravatiP50300014652· 81.8% built
- JP SYNERGY4.6 yr overdueAASHVI DEVELOPERS · Ambarnath(M Cl), ThaneP51700013804· 21.6% built
- RIVER VIEW APARTMENTS WING C4.6 yr overdueMs Babubhai Construction Co · Khalapur, RaigarhP52000007803· 90.9% built
- Mateshwari Regency Wing A104.6 yr overdueKrupa Mateshwari Home Makers · Karjat, RaigarhP52000006464· 68.6% built
- SHIV ORNATE4.6 yr overdueSHIVSHAKTI DEVELOPERS · Ulawe, RaigarhP52000004492· 55.5% built
- ADINATH ARADHANA4.6 yr overdueSHREE RIDDHI SIDDHI CONSTRUCTIONS · SECTOR 2A, RaigarhP52000014700· 90.9% built
- PARITOSH A,B,C4.6 yr overdueSHARADA ALLIANCE SHELTERS · Balewadi, PuneP52100004530· 76.1% built
- Shri Audumbar Plaza4.6 yr overdueTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS · KBP College Chowk, SolapurP52600025199· 90.9% built
- IMPERIAL OASIS4.6 yr overdueImperial Developers · Ulawe, RaigarhP52000003298· 90.9% built
- Ramkrishna Heights4.6 yr overduePOOJA ENTERPRISES · Kurla, Mumbai SuburbanP51800005327· filed Dec 2018 → now Dec 2021· 99.1% built· 1 complaint
- DAFFODIL4.6 yr overdueBUILDARCH LAND DEVLOPERS PVT. LTD. · Ward GNorth, Mumbai CityP51900008175· 90.9% built
- ELEGANCE4.6 yr overdueSHRUSHTI DEVELOPERS · Palghar, PalgharP99000014549· 90.9% built
- EMEZEKA PARK4.6 yr overdueINDRA PROPERTIES · Jadhavwadi, PuneP52100002604· 90.9% built· 1 complaint
- Nakshatra Ozone4.6 yr overdueJSB Homes LLP · Tivari, PalgharP99000009297· filed Dec 2019 → now Dec 2021· 90.9% built
- KOHINOOR BEGONIA PHASE III4.6 yr overdueKOHINOOR ASSOCIATES · varale phata, PuneP52100008679· filed Dec 2019 → now Dec 2021· 90.9% built· 1 complaint
- COSMOS SQUARE4.6 yr overdueSHRIPAL DEVELOPERS · Vasai, PalgharP51900010992· 32.7% built
- GHARKUL4.6 yr overdueAJITKUMAR CHS LTD · Borivali, Mumbai SuburbanP51800014246· filed Dec 2019 → now Dec 2021· 27.3% built
- HARINIWAS4.6 yr overdueSHREE BALAJI CORPORATION · GOREGAON WEST, Mumbai CityP51900016435· 90.9% built
- CHAITRA MOHOR APARTMENT4.6 yr overdueG. K. INFRA · PANCHVATI, NashikP51600015023· 90.9% built
- SONIGARA PRATIK4.6 yr overdueSHANKHESHWAR CONSTRUCTIONS AND DEVELOPERS · KIWALE, PuneP52100013672· 90.9% built
- JINENDRA ESTATE4.6 yr overdueOSWAL DEVELOPERS · SAUBHAGYA NAGAR, NashikP51600016250· 0% built· 1 complaint
- FIA ORION4.6 yr overdueNIMISH LAXMICHAND PASAD · PALGHAR, PalgharP99000015786· 90.9% built
- THANEKAR PARADISE4.6 yr overdueAJAY MADHUKAR THANEKAR · Ambarnath, ThaneP51700001024· filed Dec 2019 → now Dec 2021· 27.9% built
- JEWEL RESIDENCY PHASE 14.6 yr overduePKDEVELOPERS · Nere, RaigarhP52000006943· 45.5% built· 3 complaints
- AMRUT PUSHP4.6 yr overdueMORAYA REALITY GROUP · DUDULGAON, PuneP52100011364· filed Dec 2019 → now Dec 2021· 65.7% built· 2 complaints
- INDUSTRIAL PROJECT4.6 yr overdueSUVIDHA BUILDERS AND DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000009165· 81.8% built
- Manjusha Regalia4.6 yr overdueSubhash Motiram Kasulkar · Nagpur (M Corp.), NagpurP50500002805· 73.3% built
- AMARDEEP MAHAL CHS LTD4.6 yr overdueNITIN HARSHADRAI MANIAR · Andheri, Mumbai SuburbanP51800000995· filed Dec 2019 → now Dec 2021· 72.7% built
- DEEP DEVANSH - 44.6 yr overdueSAMBHAV ABODE · PUSHPAK NEW NAVI MUMBAI, RaigarhP52000016452· 79.5% built
- APEX VILLA4.6 yr overdueAPEX GROUP · KARANJADE, RaigarhP52000015666· 90.9% built
- Maple Terraces Building No. A-154.6 yr overdueMessrs. Axis Dwellings LLP · Palghar, PalgharP99000005233· filed Mar 2018 → now Dec 2021· 80.9% built
- ZEE SWASTIK4.6 yr overdueZEE RPM BUILDERS AND DEVELOPERS LLP · Andheri, Mumbai SuburbanP51800010732· 19.7% built· 1 complaint
- Samiya4.6 yr overdueSaurabh Surendra Tatke · Madhali aali, SataraP52700019562· 90.9% built
- SATYAM ROSE4.6 yr overdueOMSATYAM BUILDCONS PRIVATE LIMITED · ZINGABAI TAKLI, NagpurP50500014447· 90.9% built
- MILLENNIUM PARAMOUNT4.6 yr overdueMillennium Superstructures LLP · CHIKHALI, PuneP52100018086· 81.8% built
- Green city Phase 14.6 yr overdueGreencity Phase 1 · Godoli (CT), SataraP52700002543· filed Dec 2019 → now Dec 2021· 71.8% built
- LJTANNA PANORAMA C WING4.6 yr overdueLJTANNA REALTY LLP · Kalyan, ThaneP51700023193· 90.9% built
- Building A2 Eon Homes4.6 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100006888· 81.8% built
- ISHAN ENCLAVE4.6 yr overdueSHREE CHAITANYA DEVELOPERS · jarandeshwar naka, SataraP52700014534· 91.4% built
- HAYAAT GALAXY4.6 yr overdueM M Enterprises · Vasai, PalgharP99000003445· filed Dec 2019 → now Dec 2021· 90.9% built
- EPIC PHASE 14.6 yr overdueSHIVSAGAR PROMOTERS & DEVELOPERS · Wagholi, PuneP52100016456· 50% built
- Madhoor Maitri4.6 yr overdueMadhoor Mangal Associates · Mahatma Nagar, NashikP51600001608· filed Dec 2019 → now Dec 2021· 85.9% built
- AVALON CITY C-34.6 yr overdueClassic Promoters and Builders Private Limited · Haveli, PuneP52100003105· filed Dec 2019 → now Dec 2021· 81.8% built· 1 complaint
- FIA IMPERIA4.6 yr overdueFIA LUXURY HOME DEVELOPERS · Palghar, PalgharP99000006476· 90.9% built
- CROWN PHASE 14.6 yr overdueSHREE SAMARTH REALITY · Karjat, RaigarhP52000013990· 90.3% built
- Mohan Waters Edge I4.6 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700002550· 89.1% built
- Imperial Heights Wing C and D4.6 yr overdueEPITOME RESIDENCY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003270· filed Jun 2019 → now Dec 2021· 97.1% built· 34 complaints
- SUNDAR RESIDENCY G WING4.6 yr overdueNAVADITYA DEVELOPERS · Kalyan-Dombivali (M Corp.), ThaneP51700007150· filed Dec 2019 → now Dec 2021· 49.1% built
- LODHA AMARA - TOWER 26, 27, 28, 30, 34, 354.6 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700001031· 78.2% built· 18 complaints
- Nirman - Dinesh4.6 yr overdueNirman Construction · Roha Ashtami (M Cl), RaigarhP52000000597· 90.9% built
- FIA SAPPHIRE4.6 yr overdueNIMISH LAXMICHAND PASAD · PALGHAR, PalgharP99000014626· 90.9% built
- INDRAA PARK4.6 yr overdueS K BUILDCON · AADARSH NAGAR, PuneP52100004605· 90.9% built
- BHAGY-PRABHA4.6 yr overdueBHAGYASHRI CONSTRUCTION · KANCHANWADI, AurangabadP51500014401· 20% built
- VINAYAK HEIGHT4.6 yr overdueVINAYAK PREMISES PRIVATE LTD · NASHIK, NashikP51600020006· 81.8% built
- NEW GLOBAL E-BUILDING4.6 yr overdueCLASSIC CONSTRUCTION · Bhiwandi, ThaneP51700010601· 90.9% built
- Dream Savera4.6 yr overdueMOZE PROPERTIES · LOHGAON, PuneP52100009621· 81.8% built
- SHIV AMRUT4.6 yr overdueSHIVA AMRUT ENTERPRISES · DIVA STATION, ThaneP51700021065· 44.4% built
- BHAKTI DARSHAN4.6 yr overdueVISHAL ENTERPRISES · ULWE, RaigarhP52000016425· 81.8% built
- DURVANKUR ENCLAVE4.6 yr overdueNIRAJ MADHUKAR RAHATE · SOMALWADA, NagpurP50500015502· 36.4% built
- NOTTING HILL PHASE I4.6 yr overdueJaikul Associates · CHARHOLI, PuneP52100001939· 81.8% built· 4 complaints
- JABINDA RESIDENCY TYPE-I4.6 yr overdueJAWANDHA CONSTRUCTION PRIVATE LIMITED · Aurangabad (M Corp.), AurangabadP51500007851· 81.8% built
- Suvan Cresta - Phase B4.6 yr overdueL M Bafna · BIBVEWADI, PuneP52100000453· filed Dec 2019 → now Dec 2021· 90.9% built
- YUVAANSH APARTMENT4.6 yr overdueMANVI CONSTRUCTION · KON, ThaneP51700014634· 90.9% built
- SAI VISHWA4.6 yr overdueSai Reality · Anandvalli, NashikP51600019370· 90.9% built
- IONIA4.6 yr overdueAmit Developers · -, PuneP52100001255· filed Dec 2019 → now Dec 2021· 81.8% built
- PHASE I VISION CITY4.6 yr overdueSHUBBAN PROPERTIES VISION CITY · jambhul, PuneP52100011209· filed Dec 2018 → now Dec 2021· 89.1% built· 9 complaints
- CORNER VIEW RESIDENCY4.6 yr overdueKACHA BUILDERS & DEVELOPERS · BEHIND VISHAL LAWNS, PuneP52100022330· 90.9% built
- VISION FLORA4.6 yr overdueSiddhivinayak Namrata Developers · PIMPLE SAUDAGAR, PuneP52100009594· filed Dec 2018 → now Dec 2021· 61.8% built· 1 complaint
- TWIN TOWER4.6 yr overdueShraddha Spaces · Wakad, PuneP52100003875· 90.9% built
- MULIK LUXURIA - E WING4.6 yr overdueTUKARAM SOPANRAO MULIK · WAGHOLI, PuneP52100017442· 41.8% built
- Gulmohar Park A Wing4.6 yr overdueJay Nanaso Patil · Baramati, PuneP52100016095· 90.9% built
- VANAMALA4.6 yr overdueNAVINKUMAR SUBHASH CHORGHE · Vasai, PalgharP99000006045· 90.9% built
- SAI ANGAN4.6 yr overdueWALMIK RAGHUNATH KHAIRNAR · Nevali, RaigarhP52000004010· filed Dec 2019 → now Dec 2021· 48.4% built· 1 complaint
- MANE G CREATION4.6 yr overduePRADEEP GAJANAN MANE · Kudal (CT), SindhudurgP52900009747· 43.2% built
- Mahindra Happinest Palghar Phase - I4.6 yr overdueMAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) · Nandore, PalgharP99000014911· 81.8% built· 37 complaints
- Ruturaj Appartment4.6 yr overdueOmprakash Muniraj Yadav · Nashik, NashikP51600019017· 90.9% built
- HARSH RESIDENCY AND THE CORPORATE LOUNGE4.6 yr overdueHARSH REAL ESTATE PRIVATE LIMITED · Kashimira, ThaneP51700005806· 60.7% built
- SAI RESIDENCY4.6 yr overdueSAI KRUPA PROMOTER AND DEVELOPER PRIVATE LIMITED · Kopargaon (M Cl), AhmednagarP52200014015· 72.7% built
- METRO RESIDENCY G WING4.6 yr overdueMETRO CONSTRUCTION · Badlapur (M Cl), ThaneP51700011345· filed Dec 2020 → now Dec 2021· 90.9% built
- RIDDHI SIDDHI AVENUE4.6 yr overdueR R LUNKAD BUILDCON · Kaspate Vasti, PuneP52100015078· 90.9% built
- sai vijay4.6 yr overduekhapare and kokate constructions · pragaticolony, SangliP53100020428· 69.1% built
- SHAGUN CORNER4.6 yr overdueJETHALAL RANCHHOD PATEL · Ulawe, RaigarhP52000002987· 50.9% built· 1 complaint
- Kwality Plaza4.6 yr overdueGhodawat Developers LLP · Jaysingpur (M Cl), KolhapurP53000000233· filed Dec 2019 → now Dec 2021· 47.3% built
- Devayani Residency4.6 yr overdueYashodhan Associates · Bibwewadi, PuneP52100002412· filed Dec 2019 → now Dec 2021· 90.9% built· 13 complaints
- FALAK NUMA4.6 yr overdueNAVID MOHAMMED HUSSAIN CHINDE · Vasai, PalgharP99000008662· 72.7% built
- Patel Complex4.6 yr overdueAMRUTBHAI DURLABHBHAI PATEL · Moti Daman, DamanP49500000014· 81.8% built
- CHANDAN CHS LTD4.6 yr overdueAUM G M HEIGHTS · Andheri, Mumbai SuburbanP51800004733· 90.9% built
- SUYOJIT GREENS4.6 yr overdueCITADEL GREENS PVT. LTD · Lavate Nagar, Nashik Road, Nashik, NashikP51600002051· filed Mar 2019 → now Dec 2021· 79.5% built
- EMH - 14.6 yr overdueVISTACORE LIFESPACE DEVELOPERS INDIA PVT LTD · Yadrav, KolhapurP53000010504· filed Jun 2018 → now Dec 2021· 59.1% built· 2 complaints
- JAK CELEBRITY4.6 yr overdueJAK INFRA · Thane, ThaneP51700009203· 63.6% built
- Rajgad apartment4.6 yr overduePioneer Builders · snehal nagar, WardhaP50400015681· 90.9% built
- SYMPHONY4.6 yr overdueGIRIRAJ PROMOTERS AND DEVELOPERS · Satara Parisar, AurangabadP51500002685· 68.2% built
- RITU RAYYAN4.6 yr overdueRITU INFRASTRUCTURE PVT LTD · Thane, ThaneP51700003099· 50% built
- Soham Residency A Wing4.6 yr overdueKhushbu Realties Pvt. Ltd. · Haveli, PuneP52100019635· 81.8% built
- DAKSH ATRIUM4.6 yr overdueDAKSH CONSTRUCTION · INDIRA NAGAR, NashikP51600017429· 45.4% built
- Aquaria Grande, Wing B Floor 33-384.6 yr overdueClub Aquaria Enterprises · Borivali, Mumbai SuburbanP51800007959· 54.5% built
- HYDE PARK RESIDENCY F6 BUILDING PHASE4.6 yr overdueNEXUS BUILDERS AND DEVELOPERS PVT LTD · Thane, ThaneP51700018185· 90.9% built
- PEARL SQUARE4.6 yr overduePearl Developers · Hadapsar, PuneP52100007357· filed Dec 2018 → now Dec 2021· 90.9% built
- SUVARNAGODA SANKUL4.6 yr overdueSAMRUDDHI DEVELOPERS · SARAF BAZAAR, NashikP51600025825· 81.8% built
- Shah Business Centre4.6 yr overdueSHAH HOUSECON PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800002825· filed Dec 2019 → now Dec 2021· 60% built· 2 complaints
- Paarijaat Blossoms4.6 yr overdueM/s. Bedekar Developers limited Liability Partnership · Kolhapur (M Corp.), KolhapurP53000002381· 90.9% built
- OM VRUNDAVAN4.6 yr overdueRANVEER BUILDERS AND DEVLOPERS · Tisgaon, AurangabadP51500003613· filed Dec 2019 → now Dec 2021· 75% built
- ACHRAJ RIVIERA4.6 yr overdueRatan Constructions · Nagpur (M Corp.), NagpurP50500007301· 95.5% built
- SAI SAFALYA4.6 yr overduePRASAD ESTATE · OLD POST OFFICE PANVEL, RaigarhP52000016178· 9.1% built
- Nakshatra4.6 yr overdueAshwini Anil Lokhande · Baner, Pune, PuneP52100016234· 90.9% built· 1 complaint
- NAVKAR CITY Phase I part 34.6 yr overdueNavkar Estate and Homes Pvt.Ltd. · Vasai, PalgharP99000004573· 89.7% built
- ALLURE WINGS A TO E4.6 yr overdueAADI PROPERTIES LLP · Kurla, Mumbai SuburbanP51800008521· 63.6% built· 9 complaints
- ORANGE AURA4.6 yr overdueORANGE REALTORS · Thane, ThaneP51700004783· 61.8% built
- KESHAV VATIKA4.6 yr overdueUDAY INFRA · MAVAL, PuneP52100007032· filed Mar 2019 → now Dec 2021· 78.8% built
- LILIUM4.6 yr overdueJayshree Builders · Andheri, Mumbai SuburbanP51800000938· 90.9% built
- SHIV ZEN WORLD - PHASE I4.6 yr overdueShubh Housing · MANJARI Bk, PuneP52100007579· 54.5% built
- BABJI ENCLAVE4.6 yr overdueFAKHRI INFRAVENTURES · Near Beltarodi Bus stop, NagpurP50500001888· 90.9% built
- POONAM PALLAZO4.6 yr overduePOONAM SHANTI DEVELOPERS · Vasai, PalgharP99000007365· filed Dec 2019 → now Dec 2021· 90.9% built
- Saurabh Arcade4.6 yr overdueM/s Krishna Builders & Developers · Badlapur (M Cl), ThaneP51700014233· 56.8% built
- The Crown Greens4.6 yr overdueInternational Biotech Park Limited · Maan, Hinjawadi, PuneP52100001864· 99.9% built· 1 complaint
- Bhagyoday Residency - A4.6 yr overduePrashant Developers (Mumbai) · Pimpri Chinchawad (M Corp.), PuneP52100010887· filed Dec 2019 → now Dec 2021· 63.2% built
- Pushp Vinod - 154.6 yr overdueVas Infrastructure Ltd. · Borivali, Mumbai SuburbanP51800007682· 50% built
- Rajgruhi Residency Tower B4.6 yr overdueWellbuild Merchants Private Limited · Kondhwa, PuneP52100006651· filed Dec 2019 → now Dec 2021· 88.3% built· 1 complaint
- MADHUMALTI PRESTIGE4.6 yr overdueVIKAS DEVLEKAR · Natraj naka, RatnagiriP52800010287· 90.9% built
- Imperial Blue4.6 yr overdueKesar Infra · DIGHIP52100015034· 90.9% built
- NAVKAR CITY PHASE II PART 34.6 yr overdueNAVKAR ESTATE AND HOMES PVT LTD · naigaon, PalgharP99000009716· 89.6% built
- SAHIL VIGHNESH RESIDENCY4.6 yr overdueVAISHNAVI PROMOTERS AND DEVELOPERS · Wakad, PuneP52100005542· filed Dec 2019 → now Dec 2021· 90.9% built
- Anmol Nayantara City One Phase 54.6 yr overdueBafna Realtors Pvt Ltd · Nashik, NashikP51600001252· filed Dec 2019 → now Dec 2021· 56.7% built· 1 complaint
- SAI MANNAT4.6 yr overdueSWARAJ HOMES BUILDERS AND DEVELOPERS · KARANJADE, RaigarhP52000006287· 72.7% built
- OLIVE RESIDENCY4.6 yr overdueGOODWILL PROPERTIES · Thane (M Corp.), ThaneP51700013056· 81.8% built
- Majestique Venice4.6 yr overdueMajestique Nirman LLP · Dhayari Pune, PuneP52100000130· 95.5% built
- Omega Paradise Wing L Phase 24.6 yr overdueGarve Buildcon · WAKAD, PuneP52100004943· filed Dec 2019 → now Dec 2021· 90.9% built
- PARADISE HOMES4.6 yr overduePARADISE MAKER · MAWAN, PuneP52100008042· 90.9% built
- Apostrophe, Moshi4.6 yr overdueApex Builders · Moshi, PuneP52100000905· 81.8% built
- Grande View 7 Phase III Building K4.6 yr overdueChirag Developers · AMBEGAON bk, PuneP52100013947· 90.9% built
- Courtyard - Florence4.6 yr overdueCOURTYARD REAL ESTATE PRIVATE LIMITED · Thane, ThaneP51700000831· 86.9% built· 2 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.