RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 32 of 59
- MOUNT BLISS4.6 yr overdueRANJANA BUILDERS AND DEVELOPERS · Nardas Nagar, Mumbai SuburbanP51800014154· 90.9% built
- Vishwakrupa Sankul4.6 yr overdueVISHWAKRUPA DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000002686· filed Dec 2019 → now Dec 2021· 65.7% built
- Sanghvi Evana4.6 yr overdueSanghvi Premises Private Limited · Ward GSouth, Mumbai CityP51900007455· 74.5% built· 1 complaint
- YUDHAN HIGH RISE4.6 yr overdueSonawane Patil Construction · Aurangabad (M Corp.), AurangabadP51500004283· filed Dec 2019 → now Dec 2021· 57.3% built
- SAI PEARL4.6 yr overdueHAJARE BUILDERS · SATURNA, AmravatiP50300025747· 1.8% built
- Sea Jewel4.6 yr overdueSea Jewel Property Developers LLP · Borivali, Mumbai SuburbanP51800009552· 36.8% built
- Earth Terrace4.6 yr overdueM/s. Earth Graphics · Goregaon, Mumbai SuburbanP51900004900· filed Dec 2019 → now Dec 2021· 39% built
- KABRA CENTROID A Redevelopment of GOP CHSL4.6 yr overdueKABRA AND ASSOCIATES · Andheri, Mumbai SuburbanP51800000307· 90.9% built· 1 complaint
- SUBWAY RESIDENCY4.6 yr overdueRAJ ASSOCIATES · VIRAR, PalgharP99000010520· 41.4% built
- TANISH PLATINUM4.6 yr overdueTANISH ASSOCIATES · CHARHOLI, PuneP52100004292· 43.3% built
- Crystal Tower4.6 yr overdueKSHITIJ PROMOTERS AND DEVELOPERS · Pashan, PuneP52100000082· filed Dec 2019 → now Dec 2021· 90.8% built· 1 complaint
- VASTUVAIBHAV4.6 yr overduemaheshdada devlopers · CHIKHALI, PuneP52100014728· 55.9% built
- Dreams Park - Blossom4.6 yr overdueDreamz Realty · Mamdapur, RaigarhP52000002069· 90.9% built
- Aaradhya Apartment4.6 yr overdueAnuraj Buildcon · Dwarka Nashik, NashikP51600014697· 90.9% built
- Akshar Business Park- Phase I4.6 yr overdueAkshar Developers · Thane, ThaneP51700009578· 78.2% built· 13 complaints
- YAMUNA HEIGHTS4.6 yr overdueSAINATH ENTERPRISES · Kurla, Mumbai SuburbanP51800002016· filed Dec 2019 → now Dec 2021· 46.2% built
- VIVAAN HEIGHTS4.6 yr overdueMAHAVIR PROPERTIES · Vasai, PalgharP99000009840· filed Dec 2019 → now Dec 2021· 90.9% built
- MADHUKUNJ4.6 yr overdueADPLUS IMPRESSION PRIVATE LIMITED · 421308, ThaneP51700015121· 44.2% built
- GOVIND NIILYAM4.6 yr overdueSHRI GOVIND BUILDCON · Amravati (M Corp.), AmravatiP50300013405· 73% built
- PRIDE PALMS QUEENS B2 PHASE 34.6 yr overdueLARKINS REALTORS · Thane, ThaneP51700007071· 80% built· 2 complaints
- Suvan Forett4.6 yr overdueL M Bafna · Haveli, PuneP52100001907· filed Dec 2019 → now Dec 2021· 90.9% built
- RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING4.6 yr overdueKEYSTONE INFRASTRUCTURE PRIVATE LIMITED · AVENUE D1, PalgharP99000018043· 81.8% built
- Treeline 54.6 yr overdueLuxora Infrastructure Private Limited · Mauza, NagpurP50500002936· filed Dec 2019 → now Dec 2021· 90.9% built· 2 complaints
- SWARGANDHAR PHASE 1 A4,A5,A6,A7,B6,B74.6 yr overdueVAIBHAV CLASSIC BUILDERS AND DEVELOPERS · Uruli Kanchan, PuneP52100004071· filed Dec 2019 → now Dec 2021· 78.2% built
- Pearl Crest4.6 yr overdueRISHIRAJ DEVELOPERS PRIVATE LIMITED · Mumbai City, Mumbai CityP51900002961· filed Dec 2019 → now Dec 2021· 38.6% built· 2 complaints
- PRIDE PHOENIX BUILDING D4.6 yr overdueABAD ESTATE AOP · Chikalthana, AurangabadP51500000852· 90.9% built
- Geras Isle Royale Tower 2 and 34.6 yr overdueGera Developments Private Limited · Bavdhan, PuneP52100009870· 77.7% built
- MAITRY POOJA BUILDING NO.34.6 yr overdueMAITRY POOJA BUILDERS & DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000008122· 90.9% built
- SAMRUDHA COMPLEX4.6 yr overdueRAVI SOMJIBHAI PATEL · Junnar, PuneP52100021049· 81.8% built
- VINAYAKAM RESIDENCY4.6 yr overdueREGENCY BUILDER · CHIKHALI, PuneP52100012783· filed Mar 2020 → now Dec 2021· 81.8% built
- SKY POINT-PHASE I-A WING4.6 yr overdueShubh Enterprises · KESHAVNAGAR, PuneP52100009213· 69.1% built
- ATRIA GRANDE PROJECT B4.6 yr overdueAtria Constructions · Handewadi, PuneP52100015620· 72.7% built
- RICH COUNTY- C & D WING4.6 yr overdueSWASTIK PROMOTERS & BUILDERS · PUNE, PuneP52100006337· filed Jun 2019 → now Dec 2021· 92.1% built
- SANSKRITI INFRA4.6 yr overdueSANSKRITI INFRA · Uran, RaigarhP52000004608· 90.9% built
- MARUTI SANKUL4.6 yr overdueOM SAI DEVELOPERS · Bopele, RaigarhP52000004469· filed May 2019 → now Dec 2021· 87% built
- Govind Wing In Golden Park - I4.6 yr overdueGOLDEN PARK-I · Nagpur (M Corp.), NagpurP50500013586· filed Dec 2018 → now Dec 2021· 90.9% built
- WHISTLINGWOODSPARK4.6 yr overdueVELANI DEVELOPERS · SHELU, RaigarhP52000012731· 89.1% built
- Golden Treasures Wing A4.6 yr overdueVINAYAK KISHOR GARVE · Punawale, PuneP52100001868· filed Dec 2019 → now Dec 2021· 90.9% built
- SAI GANESH APARTMENT4.6 yr overdueNILESH PADMAKAR VAIDYA · Neral, RaigarhP52000014048· filed Dec 2018 → now Dec 2021· 27.3% built
- AERO EAST4.6 yr overdueM/S MIRACLE GURUKRUPA DEVELOPERS · Undri, PuneP52100015149· 72.7% built
- Building D3 Eon Homes4.6 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100001860· 81.8% built
- REDEVELOPMENT OF DIVYA JYOTI CO-OPERATIVE HOUSING SOCIETY LIMITED4.6 yr overdueD V DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800013943· 81.8% built
- THE PALMGROVE PHASE II4.6 yr overdueBEDEKAR BUILDERS AND DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000000720· 90.9% built
- SADGURU HARMONY PH-1 WING A4.6 yr overdueSADGURU ASSOCIATE · BADLAPUR, ThaneP51700004904· filed Dec 2019 → now Dec 2021· 36.8% built
- THE ADDRESS-PHASE-14.6 yr overdueDARSHAK SHAH AND DHARMENDRA TANDEL · NEAR COAST GUARD, DamanP49500000006· 76.3% built
- SIDDHIVINAYAK MAHIMA4.6 yr overdueSIDDHIVINAYAK HOMES · Panvel, RaigarhP52000000840· 90.9% built
- DB Commercial Phase II4.6 yr overduePune Buildtech Private Limited · Yerawada, PuneP52100003455· filed Dec 2019 → now Dec 2021· 60.9% built· 2 complaints
- SAI DARSHAN4.6 yr overdueSAI DARSHAN · GHATKOPAR KIROL, Mumbai SuburbanP51800015047· 86.4% built
- Green Avenue 1B4.6 yr overduePARAM DEVELOPERS · Thane, ThaneP51700006081· 90.9% built
- POWER BOULEVARD4.6 yr overdueSAPRA PROPERTIES & INVESTMENTS · GANESH BAUG, PuneP52100002004· 81.8% built
- Vrindavan4.6 yr overdueGiriraj Associates · Pimpri Chinchawad (M Corp.), PuneP52100004464· filed Dec 2019 → now Dec 2021· 45.5% built
- RUTURANG SHRAVAN BUILDING G4.6 yr overdueA.K.SURANA DEVELOPERS-G · PARVATI, PuneP52100003075· 99.9% built
- PARADISO BAY4.6 yr overdueATHARVA REALTY PRIVATE LIMITED · -, RaigarhP52000012241· 28.8% built
- Acropolis 14.6 yr overdueBhoomi & Arkade Associates · Virar West, PalgharP99000007415· 89.1% built· 29 complaints
- BHAGYALAXMI VISHWA4.6 yr overdueBHAGYALAXMI BUILDERS AND DEVELOPERS · OPP DHRUV NAGAR BUS STOP, NashikP51600014237· 72.7% built
- Kiarah Terrazo4.6 yr overdueWellwisher Apartment · Haveli, PuneP52100002327· filed Dec 2019 → now Dec 2021· 57.7% built· 4 complaints
- Nine Star Landmark Ph-I Bldg-1 ASTER4.6 yr overdueNINE HOMEMAKERS · Palghar, PalgharP99000009255· filed Dec 2019 → now Dec 2021· 9.1% built
- Kalpataru Waterfront4.6 yr overdueKalpataru Plus Sharyans · Panvel, RaigarhP52000002819· 90.5% built· 1 complaint
- Primus - A4.6 yr overdueKumar Construction and Properties Pvt Ltd · Hadapsar Industrial Estate, PuneP52100004518· filed Dec 2019 → now Dec 2021· 81.8% built
- REDEVELOPMENT OF STATE BANK OF INDIA EMPLOYEES SHREE CO-OP HOUSING SOC LTD4.6 yr overdueORRA REALTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800010979· 53.6% built
- SHREE SAMARTH KRUPA4.6 yr overdueJITENDRA SURYAKANT MANE · Mahad, RaigarhP51900009929· 72.7% built
- LALBAG PRESTIGE BUILDING B4.6 yr overdueRELIABLE CONSTRUCTION · Ambegaon, PuneP52100010952· filed Dec 2019 → now Dec 2021· 81.8% built
- KILBIL RATAN4.6 yr overdueR P COMBINES · MULUND, Mumbai SuburbanP51800012507· 90.9% built
- NISARG GREENS- Phase II A4.6 yr overdueNND Ambernath LLP · Morivali, ThaneP51700008839· 68.6% built
- PALKHI AURA4.6 yr overdueKCD AND SYNERGY VENTURES · Borivali, Mumbai SuburbanP51800009045· filed Dec 2019 → now Dec 2021· 87% built
- SHYAM-KAMAL4.6 yr overdueManvaibhav Constructions · Thane, ThaneP51700014557· 90.9% built
- DIVYA JYOT COMPLEX4.6 yr overdueSHREE ADITI DEVELOPERS · Ambarnath, ThaneP51700001599· 57% built
- BHUVI GHARKUL4.6 yr overdueBhuvi Landmarks LLP · NARALIBAG, AurangabadP51500014339· 90.9% built· 2 complaints
- AARYA4.6 yr overdueRAJA BUILDERS · Andheri, Mumbai SuburbanP51800006434· 67.3% built· 1 complaint
- SUYOG ABHILASHA4.6 yr overdueSUYOG ADINATH · Jalochi, PuneP52100012264· filed Dec 2019 → now Dec 2021· 74.1% built
- KANTI REGENCY4.6 yr overdueMAHAVIR PROPERTIES · Vasai, PalgharP99000010163· filed Dec 2019 → now Dec 2021· 90.9% built
- VENKATESH JYOT BLDG NO 54.6 yr overdueSHREE BALAJI BUILDERS AND DEVELOPERS · Thane, ThaneP51700006779· 90.9% built
- KRISHNA LANDMARK4.6 yr overdueSHREE HARI CONSTRUCTION · Ulawe, RaigarhP52000013703· 81.8% built
- Sara Metroville C phase III4.6 yr overdueSara Infrastructures · Punawale, PuneP52100004198· 89.1% built
- 24K ATRIA4.6 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · Haveli, PuneP52100000428· 45.5% built
- OMSHREE4.6 yr overdueJAY GANESH DEVELOPERS · Charholi Budruk, PuneP52100013484· 45.5% built
- SHREE SAIDATTA4.6 yr overdueSHREE SAIDATTA DEVELOPERS · Baramati (M Cl), PuneP52100011346· 27.9% built
- Mahavir Kalpavruksha - Oak, Tulip, Alcacia, Almond4.6 yr overdueDamji Shamji Realty Private Limited · Thane, ThaneP51700009513· 93% built· 1 complaint
- SHIV VIHAR4.6 yr overdueROYAL CONSTRUCTION · CHARHOLI KHURD, PuneP52100016068· 18.2% built
- ASHWAMEDH CAPITAL14.6 yr overdueASHWAMEDH SPACES PRIVATE LIMITED · Chahurana Budruk, AhmednagarP52200021637· 50.9% built
- KAPILA4.6 yr overdueSAI DEVELOPERS · TALOJA, RaigarhP52000017737· 60% built
- BLUE BELLS4.6 yr overduePREMCHAND BUILDERS AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500006113· filed Dec 2019 → now Dec 2021· 90.9% built
- SHREE BALAJI RESIDENCY4.6 yr overdueANAND ASSOCIATES · BALAJI TOWNSHIP, Dadra & Nagar HaveliP49600000050· 90.9% built
- Radhakrishna Residency Phase II4.6 yr overdueSAKSHI BUILDERS · Mitmita, AurangabadP51500006840· 90.9% built
- MULSHI VAIBAHV4.6 yr overdueYUVRAJ ASSOCIATES · Pirangut, PuneP52100011020· filed Dec 2019 → now Dec 2021· 76.4% built
- Bella Casa4.6 yr overdueVEER REALITY · Haveli, PuneP52100002786· 90.9% built
- Bhagyoday Residency Wing B4.6 yr overdueK C B Builders · Pimpri Chinchawad (M Corp.), PuneP52100001551· filed Dec 2019 → now Dec 2021· 50% built
- Shree Laxmi Residency4.6 yr overdueKSHITIJA INFRASTRUCTURE PVT LTD · Ward E, Mumbai CityP51900008576· 99.1% built· 1 complaint
- CONSTRUCTION OF 49 TS MIG4.6 yr overdueNASHIK HOUSING AND AREA DEVELOPMENT BOARD · Nashik, NashikP51600013395· 90.9% built
- Shree Venkatesh Nagar - Rosewood4.6 yr overdueIshanya Buildcon · Shree Venkatesh Nagar, NashikP51600014751· 83.6% built
- LUIZA HOMES4.6 yr overdueLUIZA HOMES · Vasai-Virar City (M Corp), PalgharP99000008748· filed Dec 2019 → now Dec 2021· 15.9% built
- SUDHANSHU IMPERIA4.6 yr overdueSUDHANSHU INFRASTRUCTURES PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800003303· filed Feb 2020 → now Dec 2021· 81.8% built
- MANOMAY RESIDENCY4.6 yr overdueGayatri Developers · Gut No 58, AurangabadP51500008163· 90.9% built
- THE WOODS MAPLE AVENUE B WING4.6 yr overduePIMENTA DEVELOPERS · Vasai, PalgharP99000005658· 90.9% built
- KRUSHNAPURAM APARTMENT4.6 yr overdueSAMADHAN KRUSHNA GODSE · KRUSHNABAN COLONY, NashikP51600018546· 70.9% built
- SANTOSH DREAMS4.6 yr overdueMANAS PROMOTERS & DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100006993· filed Dec 2019 → now Dec 2021· 81.6% built
- BALAJI SAMRUDDHI4.6 yr overdueBALAJI BUILDCON · Uran Islampur (M Cl), SangliP53100013033· 72.7% built
- KATEELESHWARI APARTMENT4.6 yr overdueKATEELESHWARI DEVELOPERS PRIVATE LIMITED & RAMANI BROTHERS · Mulund Check naka, Mumbai SuburbanP51800011873· 90.9% built
- DATTA RAMANAND CHS LTD4.6 yr overdueDISHA CONSTRUCTION · Andheri, Mumbai SuburbanP51800001236· filed Dec 2019 → now Dec 2021· 89.1% built
- THE WOODS JUNIPER B WING4.6 yr overduePLATINUM REALTY · Vasai, PalgharP99000009479· 90.9% built
- QN GREENS PHASE 14.6 yr overdueQUALITAS NAMAN HOME MAKERS LLP · Panvel, RaigarhP52000007707· filed Dec 2019 → now Dec 2021· 81.1% built· 1 complaint
- Nirmaldhara4.6 yr overdueHAZEL ENTERPRISE · Bhiwandi, ThaneP51700006777· 90.9% built
- GEETABAN RESIDENCY4.6 yr overdueBHAISHREE VENTURES · Near Railway Station, AurangabadP51500016327· 81.8% built
- AARAMBH4.6 yr overdueYashada Nivasa Associates · DUDULGAON, MOSHI, PuneP52100019333· 81.8% built
- SHREE GANESH LUXURIA4.6 yr overdueSHRINIVAS BUILDWELL · PRASHANT NAGAR, PATHARDI PHATA, NashikP51600022205· 71.8% built
- DELLA VILLA PHASE 44.6 yr overdueDELLA ENCLAVE PRIVATE LIMITED · LONAVALA, PuneP52100006680· 72.7% built· 1 complaint
- Parinee Adney4.6 yr overduePARINEE REALTY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800001852· filed Dec 2019 → now Dec 2021· 90.9% built· 31 complaints
- CASITA ENCLAVE4.6 yr overdueBHOIR ENTERPRISES · Vasai-Virar City (M Corp), PalgharP99000012590· 90.9% built
- SANSKRITI-NAVYANGAN4.6 yr overdueM/S. AVIOR MERLIN BUILDCON LLP · Mulshi, PuneP52100000213· filed Mar 2020 → now Dec 2021· 87.9% built· 2 complaints
- ARKADE RISE4.6 yr overdueArkade Paradigm · Mumbai City, Mumbai CityP51900015795· 54.9% built
- MORAJ MAA SMRITI4.6 yr overdueMORAJ BUILDING CONCEPTS PRIVATE LIMITED · Khalapur, RaigarhP52000005053· 72.1% built
- Alpinia4.6 yr overdueAcme Housing India Private Limited · Thane, ThaneP51700000778· filed Dec 2019 → now Dec 2021· 91.3% built· 10 complaints
- Goldmine4.6 yr overdueUdaysinh vijaysinh Nimbalkar · Kolhapur (M Corp.), KolhapurP53000012274· 81.8% built
- Chitamani Nivas4.6 yr overdueKrishna Haribhau Lohokare · NEAR STATE BANK COLONY, PuneP52100014967· 90.9% built
- REGAL SQUARE PHASE II BUILDING NO 4 AND 54.6 yr overdueSQUAREFEET INFRASTRUCTURE LLP · Bhadwad Temghar Pada, ThaneP51700008143· 90.9% built· 1 complaint
- Yash Enclaves Bldg 34.6 yr overdueRACHANA ENTERPRISES · Kalyan, ThaneP51700004472· filed Dec 2019 → now Dec 2021· 66.4% built
- THE WOODS- MAPLE AVENUE A WING4.6 yr overdueSURE DWELL DEVELOPERS · Vasai, PalgharP99000005435· 90.9% built
- Ambika Niwas4.6 yr overdueLumbaram Modaram Patel · Pushpak Node, RaigarhP52000018656· 90.9% built
- PARADISE RESIDENCY4.6 yr overduePARIKH INVESTMENT AND DEVELOPMENT PVT. LTD. · Vasai, PalgharP99000004196· filed Dec 2019 → now Dec 2021· 40.9% built
- BLUE OCEAN ROW HOUSES APPARTMENT4.6 yr overdueBLUE OCEAN BUILDERS AND DEVELOPERS · Near Jain Mandir, NashikP51600013997· 63.6% built
- Kanchan Vastu Phase I4.6 yr overdueSudhir Vasant Karnataki · PAUD ROAD, PuneP52100005551· 45.5% built
- JUIE4.6 yr overdueVERSATILEREALTORSPRIVATELIMITED · Vasai, PalgharP99000012019· filed Dec 2019 → now Dec 2021· 90.9% built
- RAMESHWARAM PALACE-B4.6 yr overduePYARELAL BHRIGUNATH SINGH · Titwala, ThaneP51700007432· filed Dec 2019 → now Dec 2021· 50% built
- HYDE PARK RESIDENCY F4 BUILDING PHASE4.6 yr overdueNEXUS BUILDERS AND DEVELOPERS PVT LTD · Thane, ThaneP51700018186· 90.9% built
- DAHISAR SUMATI CHS LTD4.6 yr overdueBHATIA BUILDERS AND DEVELOPERS PVT LTDC · Borivali, Mumbai SuburbanP51800003975· filed Dec 2019 → now Dec 2021· 53.6% built
- AIR MONT4.6 yr overduePRAGATI SPACES · Gahunje, PuneP52100005751· 75.5% built· 1 complaint
- ANANDA RESIDENCY4.6 yr overduePARADIGM AMBIT BUILDCON · Borivali, Mumbai SuburbanP51800000204· filed Dec 2019 → now Dec 2021· 95.7% built· 13 complaints
- ULTRA OVATION4.6 yr overdueSANJEEV SITARAM DANGE · Nashik, NashikP51600005527· filed Dec 2020 → now Dec 2021· 34.5% built
- Xpoint Redevelopment of Prem Bhavna CHSL4.6 yr overdueRodium Properties division of Rodium Realty Ltd. · Borivali, Mumbai SuburbanP51800001187· 50% built
- SAI KRUSHNABOOMI APARTMENT4.6 yr overdueR V CONSTRUCTION · CIDCO, NashikP51600021162· 55.5% built
- SAVERA PARK4.6 yr overdueSAVERA DEVELOPERS · Baramati (M Cl), PuneP52100014418· 11.1% built
- SIDDHICITY PHASE-V4.6 yr overdueSiddhitech Homes Private Limited · Ambarnath, ThaneP51700001928· filed Dec 2019 → now Dec 2021· 51.8% built· 42 complaints
- SOMANI DREAM HOME PHASE - 14.6 yr overdueFAST REALTY PVT LTD · Punawale, PuneP52100002272· 32.5% built
- Rustomjee Seasons - Wing C4.6 yr overdueKEYSTONE REALTORS LIMITED · Andheri, Mumbai SuburbanP51800000309· 90.9% built
- SHRI KAMBESHWAR HEIGHTS4.6 yr overdueSHRI KAMBESHWAR & SONS · Vasai, PalgharP99000006801· 90.4% built
- SHREE SADGURU KRUPA4.6 yr overdueMAA PRANAAM VENTURE · Katraj, PuneP52100007899· filed Dec 2019 → now Dec 2021· 60.9% built
- SHREE RAJ TOWER4.6 yr overdueCHANDRASHEKHAR BABURAO KALE · Zingabai Takli, NagpurP50500012734· 81.8% built
- AKASH4.6 yr overdueKay Bee Developers Pvt. Ltd. · Ward GNorth, Mumbai CityP51900001876· 44.5% built
- Imperial Heritage4.6 yr overdueShree Ganesh Ventures · Vasai, PalgharP99000001053· filed Dec 2018 → now Dec 2021· 90.9% built
- Aapla Ghar Lonikand4.6 yr overdueMIA Properties · Haveli, PuneP52100008033· filed Dec 2019 → now Dec 2021· 87.9% built· 4 complaints
- Rukmini Garden Building No 24.6 yr overdueMARUTI RAGHUNATH JADHAV · Titwala East, ThaneP51700003299· filed Dec 2018 → now Dec 2021· 90.9% built
- SAMRUDHHI PLAZA -B4.6 yr overdueSUNITA LAXMAN GOMASE · PATHARDI SHIVAR, NashikP51600020247· 32.7% built
- MAN ITELLIPARK - IT4.6 yr overdueMERINO SHELTERS PRIVATE LIMITED · NERUL, ThaneP51700010714· 6.4% built
- KANCHAN ELEENA PHASE I4.6 yr overdueTRY DEVELOPERS PRIVATE LIMITED · Wakad, PuneP52100009730· 63.6% built
- Vision Vatika4.6 yr overdueVision Developers · Vitthalwadi, PuneP52100009188· filed Dec 2019 → now Dec 2021· 63.6% built
- CASITA ENCLAVE4.6 yr overdueM/S PLATINUM REALTORS · Vasai, PalgharP99000003868· 90.9% built
- AYODHYA PARK4.6 yr overdueRAM GROUP · Kolki (CT), SataraP52700001440· 81.8% built
- ADVIKA PHASE II4.6 yr overdueADVIKA CONSTRUCTIONS PVT.LTD · pisoli, PuneP52100013261· 45.5% built· 1 complaint
- SANSKRUTI PARK4.6 yr overdueSANSKRUTI INFRASTRUCTURE · Malwan (M Cl), SindhudurgP52900001092· filed Dec 2019 → now Dec 2021· 62.7% built
- OMKARESHWAR CHS PROP4.6 yr overdueNEW LAXMI ENTERPRISES · Andheri, Mumbai SuburbanP51800012099· filed Dec 2019 → now Dec 2021· 53.2% built
- Oasis - Tower 24.6 yr overdueAcme Housing India Private Limited · Borivali, Mumbai SuburbanP51800001238· filed Dec 2019 → now Dec 2021· 94.1% built· 22 complaints
- SPH ROYALE4.6 yr overduePARESH RANCHHOD PATEL · Panvel, RaigarhP52000015687· 0.9% built
- PARIJATAK CO OP HSG SOC LTD4.6 yr overdueSUNRISE HOUSING · Kurla, Mumbai SuburbanP51800001974· filed Dec 2019 → now Dec 2021· 80% built
- Bramha Exuberance C4.6 yr overdueBramhacorp Limited · KONDHWA, PuneP52100001076· 90.9% built· 1 complaint
- Juhu Sheetal Co-operative Housing Society Ltd.4.6 yr overdueAmal Realtors Private Limited · Andheri, Mumbai SuburbanP51800000648· 90.9% built
- SWASTIK SHRUSHTI4.6 yr overdueSWASTIK ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100002248· filed Dec 2019 → now Dec 2021· 14.7% built· 1 complaint
- PRESTIGE APARTMENT4.6 yr overdueSAIJAYSHREEBUILDERS · Palghar, PalgharP99000015069· 45.5% built
- GOLDEN WINDS Building A Phase 44.6 yr overdueGOLDEN BRICKS DEVELOPERS · Lohegaon, PuneP52100003838· filed Dec 2019 → now Dec 2021· 76.8% built
- KRUSHANPINGAKSH4.6 yr overdueSHRI SIDDIVINAYAK CONSTRUCTION · PANVEL, RaigarhP52000014527· 37.3% built
- SAI RESIDENCY4.6 yr overdueSAI RAJ DEVELOPERS · kharvai, ThaneP51700013477· 90.5% built
- SHANKHESHWAR DARSHAN TYPE - B4.6 yr overdueRAMESH GHEVARCHAND TATED · Bhiwandi (M Corp.), ThaneP51700013024· 58.2% built
- BLOOM RESIDENCY C BUILDING AND COMMERCIAL4.6 yr overdueBLOOM INFRASTRUCTURE · charholi kh, PuneP52100004126· 23.2% built· 1 complaint
- TRIMURTI CHSL PHASE I - UPTO 15TH FLOOR4.6 yr overdueROMELL REAL ESTATE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800007589· 90.9% built
- RUSTOMJEE VIRAR AVENUE D1 WING C AND WING D4.6 yr overdueKEYSTONE INFRASTRUCTURE PRIVATE LIMITED · AVENUE D1, PalgharP99000017942· 81.8% built· 2 complaints
- Shri Sadashiv CHSL4.6 yr overdueBhoomi Shashwat Estate Pvt. Ltd. · Andheri, Mumbai SuburbanP51800019208· 46.8% built
- Thana Co-Op Housing Society Sopan4.6 yr overdueAditya Associates · Thane, ThaneP51700002433· filed Dec 2019 → now Dec 2021· 20.9% built
- Pradnyaraj Lotus4.6 yr overduePradnyaraj Properties · Near Old Mudhwa RoadP52100007999· 90.9% built
- SHUBH NILAYA4.6 yr overdueSHUBH REALTORS · Lohegaon, PuneP52100015446· 78.2% built
- REGENCY PARK PHASE 14.6 yr overdueSAB VENTURES · Kalyan, ThaneP51700008733· 90.9% built
- PRESTIGE GOLD4.6 yr overdueSHAH PRATHAMESH CONSTRUCTIONS · Mundhawa, PuneP52100001263· 54.8% built
- NEW EKTA CHS4.6 yr overdueADITYA DEVELOPERS · Borivali, Mumbai SuburbanP51800007346· 76.8% built· 9 complaints
- SIDDHIVINAYAK UTOPIA - C WING4.6 yr overdueSIDHIVINAYAK BUILTHOME SPECALITIES PRIVATE LIMITED · Panvel, RaigarhP52000009789· 30% built
- Noble Nivas - Redevelopment4.6 yr overdueSHARADA LIFESPACES · Gultekadi, PuneP52100015411· 67.7% built
- PRISTINE VILLA PHASE III4.6 yr overdueATHARV DEVELOPERS · Karla, PuneP52100006460· filed Dec 2019 → now Dec 2021· 25.9% built
- YOGMALA APPARTMENT WING B4.6 yr overdueSWASTIK ESTATES · Jail Road, NashikP51600006719· filed Dec 2019 → now Dec 2021· 90.9% built
- Palmspring Bungalows - E1 to E64.6 yr overdueKUMAR KERING DEVELOPERS LLP · MOHAMMEDWADI, PuneP52100015961· 78.2% built
- Westen Tower4.6 yr overdueKalbhor and Lanke Birje Associates · Wakad, PuneP52100016419· 90.9% built
- RUSI MEHTA TOWERS4.6 yr overdueANAHITA RUSI MEHTA · Mumbai City, Mumbai CityP51900007228· filed Jul 2018 → now Dec 2021· 81.8% built
- GOKUL GIRDHAR HEIGHTS4.6 yr overduePANKAJ CONSTRUCTIONS · Nagpur (M Corp.), NagpurP50500006975· 39.7% built
- SILVER PALACE4.6 yr overdueHARE KRISHNA ENTERPRISES · ULWE, RaigarhP52000016353· 90.9% built
- Vaishnavi Park4.6 yr overdueKundnani Associates · Chakan (CT), PuneP52100005505· filed Dec 2019 → now Dec 2021· 90.9% built
- OMKAR PARK4.6 yr overdueOMKAR BUIDCON · Nashik (M Corp.), NashikP51600014305· 90.9% built
- AVENUE WING A4.6 yr overdueDharmesh Constructions Private Limited · Borivali, Mumbai SuburbanP51800002030· filed Dec 2019 → now Dec 2021· 80.6% built· 21 complaints
- MILLENNIUM ICON4.6 yr overdueMILLENNIUM INFRA · Ulawe, RaigarhP52000008226· 69.7% built
- ANNAPURNA JYOTI4.6 yr overdueANNAPURNA ASSOCIATES · Thane, ThaneP51700000957· 90.9% built
- PARVATARA PHASE 14.6 yr overdueSaakshi Constructions · Haveli, PuneP52100002385· 92.7% built
- NIRAJ RIVIERA - SHIRISH4.6 yr overdueShree Samarth Developers · Kalyan, ThaneP51700010779· 90.9% built
- Om Amitesh Apartment4.6 yr overdueINFINITI INFRAVENTURES · Godhni (Railway), NagpurP50500017883· 90.9% built
- Kamalraj Datta Vihar A Bldng4.6 yr overdueKAMALRAJ ESTATE · MOSHI, PuneP52100002971· filed Dec 2019 → now Dec 2021· 90.9% built
- Panache4.6 yr overdueTRIMURTI SAI NATH INFRAS LLP · KATRAJ, PuneP52100016181· 9.1% built
- EPITOME PHASE I4.6 yr overdueKasturi Developers · Near Bhumkar Chowk, PuneP52100000703· 81.8% built· 1 complaint
- NAVKAR CITY PHASE I PART 14.6 yr overdueNavkar Estate and Homes Pvt Ltd · don bosco, PalgharP99000011999· 90.2% built· 5 complaints
- Shree Balaji Hieghts4.6 yr overdueRAJENDRA SITARAM SAWANT · Roha Ashtami (M Cl), RaigarhP52000005765· 43.9% built
- DWARKAMAI4.6 yr overdueJ P ASSOCIATES · Pune City, PuneP52100004258· 29.8% built
- Mohan Nano Estates I4.6 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700003948· filed Dec 2019 → now Dec 2021· 89.1% built
- BRAMHA SKY ONE4.6 yr overdueB & G DEVELOPERS · UNDRI, PuneP52100012500· filed Dec 2019 → now Dec 2021· 90.9% built
- DBR Classic4.6 yr overdueDBR CONSTRUCTIONS PVT LTD · Badlapur, ThaneP51700008402· 90.9% built
- JANAI - BALAJI APARTMENTS4.6 yr overdueUNIQUE DEVELOPERS · Chhatrapati nagar, NagpurP50500007644· filed Dec 2018 → now Dec 2021· 84.5% built
- BHOOMI CELESTIA B-WING4.6 yr overdueSASHWAT CONSTRUWELL PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800004768· 61.3% built
- Golden Treasures Wing D4.6 yr overdueVINAYAK KISHOR GARVE · Punawale, PuneP52100001147· filed Dec 2019 → now Dec 2021· 76.4% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.