- Majestique Towers East Phase 30 mo overdueM/s. Sharad Shree Enterprises, Sachin Date, Jayshree Date · Haveli, PuneP52100028815· filed Jun 2026 → now Oct 2026· 65% built· 15 complaints
- SADGURU HARMONY PHASE - 3 WING C0 mo overdueSADGURU ASSOCIATE · Badlapur, ThaneP51700034459· filed Jun 2025 → now Oct 2026· 81.9% built
- IMPERIAL ATRIA TOWER 20 mo overdueMERIDIAN · Haveli, PuneP52100016407· filed Apr 2022 → now Oct 2026· 68% built· 1 complaint
- DATTA SAMARTH0 mo overduePANDURANG ARJUN CHAWAN · Thane, ThaneP51700050343· filed Jun 2024 → now Oct 2026· 77% built
- MORYA HEIGHTS0 mo overdueMORYA DEVELOPERS · Vashind, ThaneP51700053294· filed Jun 2026 → now Oct 2026· 45.5% built
- SHUBHANKAR0 mo overdueITCON BUILDERS AND DEVELOPERS · Pendse Nagar, ThaneP51700056238· filed Jun 2026 → now Oct 2026· 58.6% built
- MEGHA EDGE- RED ROSE0 mo overdueMEGHA LAKSHMI ENTERPRISE · Borivali, Mumbai SuburbanP51800046888· filed Sept 2025 → now Oct 2026· 90.9% built
- JP Eminence0 mo overdueJ. P. INFRA (MUMBAI) PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026524· filed Jun 2026 → now Oct 2026· 90.9% built· 1 complaint
- DURGA VIHAR0 mo overdueSatkar Reality · Haveli, PuneP52100048316· filed Oct 2025 → now Oct 2026· 72.3% built
- VISHAKHA HEIGHTS AND VISHAKHA REGENCY0 mo overdueM/s Keytech · Kurla, Mumbai SuburbanP51800046013· filed Dec 2025 → now Oct 2026· 62.7% built
- SHREERAM SHIVALAY EAST0 mo overdueRohit Skylines · Haveli, PuneP52100048271· filed Jun 2025 → now Oct 2026· 81.8% built
- Shubham Atlanta0 mo overdueAVVAD HOUSING LLP · Kurla, Mumbai SuburbanP51800051726· filed Jun 2026 → now Oct 2026· 90% built
- LAMBODAR RESIDENCE0 mo overdueVIGHNAHARTA LANDMARKS · Haveli, PuneP52100054922· filed Jun 2026 → now Oct 2026· 56.4% built
- NAKSHATRA C to G0 mo overduePramukh realty · SAMARVANI AREA, Dadra & Nagar HaveliP49600000069· 90.9% built
- Pioneer Residency0 mo overduePioneer Developers · Near Govindbaug Society, PuneP52100051111· filed Jun 2026 → now Oct 2026· 79.1% built
- New Saket Co-operative Housing Society Ltd.0 mo overdueSM Magnate Construction · Andheri, Mumbai SuburbanP51800049992· filed Jun 2026 → now Oct 2026· 90.9% built
- Sai Manas0 mo overdueSai Smaran infra and Developers · Pashane, RaigarhP52000008081· filed Dec 2018 → now Oct 2026· 49.1% built· 1 complaint
- KRISHNA DARSHAN0 mo overdueKRISHNA BUILDCON · BADLAPUR EAST, ThaneP51700049959· filed Dec 2025 → now Oct 2026· 87.3% built
- ROYAL PARK0 mo overdueGAIKWAD HAPSE ASSOCIATES · KIWALE, PuneP52100049775· filed Apr 2026 → now Oct 2026· 81.8% built
- AAKRUTI AASHVI APARTMENT0 mo overdueAakruti Aashvi Developers · Kurla, Mumbai SuburbanP51800003018· filed Jun 2022 → now Oct 2026· 81.4% built
- TOWER 280 mo overdueShiv Shakti Builders And Developers · Borivali, Mumbai SuburbanP51800009511· filed Jun 2022 → now Oct 2026· 62.1% built· 80 complaints
- VARDHAN HEIGHTS0 mo overdueVARDHAN HOUSING · Kurla, Mumbai SuburbanP51800014198· filed Dec 2022 → now Oct 2026· 58% built· 12 complaints
- AVIGHNA COMPLEX PHASE I0 mo overdueAVIGHNAA INFRA BUILDCON LLP · MIRA ROAD EAST, ThaneP51700027284· filed Jun 2026 → now Oct 2026· 90.5% built· 1 complaint
- Aarambh0 mo overdueSeven Star Properties · Mulshi, PuneP52100013050· filed May 2019 → now Oct 2026· 83.6% built
- Mangeshi Dhara0 mo overdueMangesh Dashrath Gaikar · Thakurli, ThaneP51700047990· filed Jun 2026 → now Oct 2026· 25.5% built· 1 complaint
- Om Prathamesh Co-op HSG Society LTD0 mo overdueSHREE SAI INFRA · Dombivli West, ThaneP51700050676· filed Jun 2026 → now Oct 2026· 81.8% built
- MERAKI0 mo overdueTHE GEN GROUP OF CONSTRUCTIONS · Haveli, PuneP52100030495· filed Dec 2025 → now Oct 2026· 90.9% built
- SAI WORLD RETREAT0 mo overdueParadise Leisure Homes · Behind lucky celebrity wax museum, PuneP52100020452· filed Dec 2024 → now Oct 2026· 79.7% built
- Swami Residency0 mo overdueManik Sadashiv Mohite · Haveli, PuneP52100028342· filed Dec 2024 → now Oct 2026· 86.4% built
- VENKATESHWARA HEIGHTS0 mo overdueSHREE VENKATESHWARA DEVELOPERS · BADLAPUR, ThaneP51700053286· filed Dec 2025 → now Oct 2026· 80.9% built
- SARA SWAPNAVIHAR0 mo overdueJagrutsara Structures LLP · Khed, PuneP52100019508· filed Jun 2026 → now Oct 2026· 81.5% built
- Dattani Vertex Building No.4 Wing CD Phase-IV0 mo overdueBRIJESH SATISH DATTANI · Sandor, PalgharP99000027866· filed Jun 2026 → now Oct 2026· 90.9% built
- MASS IONICS0 mo overdueMASS BUILDSQUARE STRUCTURE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800027417· filed Jun 2026 → now Oct 2026· 66% built
- Maruti Greens0 mo overdueMARUTI BUILDCON · Village Kharvai, ThaneP51700045873· filed Jun 2026 → now Oct 2026· 77.3% built
- DAISY GARDENS SURVEY NO 110 mo overdueANKITA BUILDERS · Ambarnath, ThaneP51700005390· filed Dec 2020 → now Oct 2026· 90.9% built
- SAI AASHIYANA - II0 mo overdueSai Sakshi Developers · TISGAON, ThaneP51700026248· filed Jun 2026 → now Oct 2026· 90.9% built
- Trimbac0 mo overdueTrimbac · Kurla, Mumbai SuburbanP51800055483· filed Jun 2026 → now Oct 2026· 81.8% built
- HARE KRISHNA KUNJ0 mo overdueB G PROMOTERS AND BUILDERS · Haveli, PuneP52100031579· filed Dec 2025 → now Oct 2026· 80.9% built
- Saurabh Residency0 mo overdueAshiana Builders & Developers · Karjat, RaigarhP52000007458· filed Dec 2019 → now Oct 2026· 90.9% built
- BHAVANI VIEW0 mo overdueBhavani Construction · Virar West, PalgharP99000007598· filed Dec 2019 → now Oct 2026· 90.9% built
- SUNSHINE SQUARE0 mo overdueVIKRAMADITYA REALTY PRIVATE LIMITED · KARANJADE, NAVI MUMBAI, RaigarhP52000050875· filed Dec 2024 → now Oct 2026· 70.9% built
- SHRI SIDDHIVINAYAK BY DEM0 mo overdueDEM Realty LLP · Borivali, Mumbai SuburbanP51800049306· filed Feb 2026 → now Oct 2026· 90.9% built
- SHREYA0 mo overdueBHARAT NAVINCHANDRA GALA · Borivali, Mumbai SuburbanP51800002243· filed Dec 2018 → now Oct 2026· 36.2% built· 1 complaint
- The Residency0 mo overdueLak & Hanware Realty LLP · Andheri, Mumbai SuburbanP51800004331· filed Jun 2021 → now Oct 2026· 93.2% built· 4 complaints
- Arihant Sakshi0 mo overdueDharmesh Vasantrai Shah · Pune City, PuneP52100032532· filed Jun 2024 → now Oct 2026· 54.5% built
- Shree Sai Aangan0 mo overdueMahesh Enterprises · Near Ramchndra Talkies, ThaneP51700055090· filed Jun 2026 → now Oct 2026· 90% built
- Millat Arcade0 mo overdueR K Buildcon · Bhiwandi, ThaneP51700080861· filed Jun 2026 → now Oct 2026· 79.1% built
- PRIME AURA0 mo overduePRIME GROUP · Borivali, Mumbai SuburbanP51800046359· filed Dec 2025 → now Oct 2026· 90.9% built
- Olive - Phase III - Pranjee Garden City0 mo overduePranjee Properties Pvt. Ltd · Katrap, ThaneP51700025487· filed Jun 2024 → now Oct 2026· 79.6% built
- Dattani Linear Building No.3 Wing ABC Phase-II0 mo overdueBRIJESH SATISH DATTANI · SANDOR, PalgharP99000027867· filed Jun 2026 → now Oct 2026· 90.9% built
- ARCADIA0 mo overdueACME SAWANT VENTURES · Haveli, PuneP52100013508· filed Dec 2022 → now Oct 2026· 49.8% built· 2 complaints
- RAJDEEP CHS LTD0 mo overdueCHINNAPAN SWAMY ANTHONY · Borivali, Mumbai SuburbanP51800049463· filed Dec 2025 → now Oct 2026· 90.7% built
- Ashapuri Vrundavan Phase II0 mo overdueAshapuri Developers · Mulshi, PuneP52100050898· filed Jun 2026 → now Oct 2026· 34.5% built
- Kuteer construction0 mo overdueKuteer Construction · Vasai, PalgharP99000028174· filed Jun 2026 → now Oct 2026· 34.8% built
- Krishna Aura0 mo overdueQualitas Lifespaces LLP · Kharghar, RaigarhP52000051708· 90.5% built
- RAMASHANKAR CHS LTD0 mo overdueSAI PRASAD BUILDERS AND DEVELOPERS · KHARKAR ALI, ThaneP51700023241· filed Jun 2023 → now Oct 2026· 72.3% built
- ANANDAM PHASE - II0 mo overdueTODAY GLOBAL HOMES · PANVEL, RaigarhP52000021559· filed Dec 2024 → now Oct 2026· 87.7% built· 46 complaints
- SHREE SANTOSH APPARTMENT0 mo overdueBHARAT NAVINCHANDRA GALA · Borivali, Mumbai SuburbanP51800007795· filed Dec 2018 → now Oct 2026· 75.9% built· 4 complaints
- PLANET RIVERFRONT0 mo overdueHABIB UMER KHAN · TALOJA, RaigarhP52000027205· filed Jul 2025 → now Oct 2026· 92.6% built
- PLUTONIUM BUSINESS PARK0 mo overduePLUTONIUM BUSINESS SOLLUTION PRIVATE LIMITED · Thane, ThaneP51700025606· filed Jun 2026 → now Oct 2026· 74.1% built
- Suyash Greens0 mo overdueSuyash Promotors & Developers · Mawal, PuneP52100003942· filed Dec 2018 → now Oct 2026· 85% built· 1 complaint
- Sahara City Homes Phase 1 Nagpur0 mo overdueSAHARA PRIME CITY LTD · Gawasi Manapur, NagpurP50500013486· 50.8% built· 47 complaints
- SHREEYANSH PARK0 mo overdueSHREEYANSH PARK · Haveli, PuneP52100019134· filed Sept 2020 → now Oct 2026· 0.5% built
- GAURAV LEGEND0 mo overdueMonarch and Querish Builders · Andheri, Mumbai SuburbanP51800010967· filed Dec 2023 → now Oct 2026· 52.2% built· 50 complaints
- O AND S BUSINESS SUITES0 mo overdueSUCHITA ORANGE HDM PROJECT · Kurla, Mumbai SuburbanP51800006703· filed Dec 2025 → now Oct 2026· 81.8% built
- SILVENIA0 mo overdueAssociated Recons LLP · SUVARNABAUG COLONY, PuneP52100053357· filed Jun 2026 → now Oct 2026· 50% built
- Arvind Niwas0 mo overdueArvind Niwas · Borivali, Mumbai SuburbanP51800052356· filed Jun 2025 → now Oct 2026· 75% built
- JITO NAGAR0 mo overdueJAIN ASHAPURI DEVELOPER UNIT II · Haveli, PuneP52100047920· filed Sept 2025 → now Oct 2026· 65.6% built
- GEETA PLAZA0 mo overdueROYAL DEVELOPERS · MAHAGIRI THANE, ThaneP51700028915· filed Jun 2026 → now Oct 2026· 68.2% built
- EKATVA ONYX0 mo overdueVERTICAL REALTORS PRIVATE LIMITED · Thane, ThaneP51700047272· filed Dec 2025 → now Oct 2026· 62.3% built
- Crystal Palladian 2070 mo overdueSri Sai Nidhi Realtors Private Limited · GHATKOPAR WEST, Mumbai SuburbanP51800031122· filed Dec 2025 → now Oct 2026· 63.6% built· 1 complaint
- Eakadanta Sankul Phase-II0 mo overdueEAKADANTA REALTORS · Kondale, RaigarhP52000004401· filed Jun 2023 → now Oct 2026· 67.3% built· 1 complaint
- Riverdale Grove0 mo overdueDuville Estates Private Limited · Haveli, PuneP52100029023· filed Jun 2026 → now Oct 2026· 50.5% built· 9 complaints
- Koyna Villa0 mo overdueBadar Group Builder and Developer · Ghotcamp- Koynavela, RaigarhP52000077199· filed Jun 2026 → now Oct 2026· 46.8% built
- ROOPNIKETAN CO.OPERATIVE HOUSING SOCIETY LTD.0 mo overdueSHREE SHINGAR CONSTRUCTIONS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800051469· filed Dec 2025 → now Oct 2026· 76.8% built
- Vivaana Heights0 mo overdueN K BUILDERS & DEVELOPERS · Andheri, Mumbai SuburbanP51800025788· filed Jun 2026 → now Oct 2026· 44.3% built· 1 complaint
- Ambika Vrundavan0 mo overdueAmbika Buildcon · Amrutdham Panchavati, NashikP51600049995· filed Oct 2025 → now Oct 2026· 72.7% built
- Chistiya Palace0 mo overdueRensar Infra Pvt.Ltd · Ward E, Mumbai CityP51900005473· filed Jul 2022 → now Oct 2026· 98% built· 6 complaints
- Sai Heights0 mo overdueAMAZE BUILDCON INDIA LIMITED · Pushpak New, RaigarhP52000027957· filed Jun 2023 → now Oct 2026· 53.6% built
- SADGURU HARMONY PHASE 4 WING D0 mo overdueSADGURU ASSOCIATE · Badlapur, ThaneP51700034703· filed Jun 2025 → now Oct 2026· 76.4% built
- AVYUKT0 mo overdueSUNSHINE DEVELOPERS · Mahim Road Near Swami Samarth Temple, PalgharP99000050491· filed Jun 2026 → now Oct 2026· 38.6% built
- LA Arihant Harmony0 mo overdueAshiana Builders & Developers · Ukrul, RaigarhP52000004069· filed Dec 2022 → now Oct 2026· 60.6% built
- SAWAN MAJESTY0 mo overdueHARNAMSINGH KULBIRSINGH MAKER · NAVI MUMBAI, RaigarhP52000024591· filed Jun 2026 → now Oct 2026· 80.9% built
- FLORA GRANDVIEW0 mo overdueIMAGE SPACE INCORPORATED · MAJAREWADI, SolapurP52600048738· 76.8% built
- SHUBHAM RESIDENCY0 mo overdueG D JAIN INFRA PROJECTS · Sudhagad, RaigarhP52000009136· filed Dec 2019 → now Oct 2026· 68.9% built
- RATNADEEP HEIGHTS0 mo overdueRATNADEEP HEIGHTS · Kurla, Mumbai SuburbanP51800052154· 80.1% built
- SAI ADINATH MAJESTIC0 mo overdueA V ASSOCIATES · SATARA PARISAR AURANGABAD, AurangabadP51500031247· 72.7% built
- Pride Heritage0 mo overdueBHAKTI INFRA · Chinchwad, PuneP52100052501· filed Dec 2025 → now Oct 2026· 89.5% built
- WOODSTOCK GARDENS0 mo overdueWOODSTOCK GARDENS · Andheri, Mumbai SuburbanP51800053552· 95.5% built
- EXCEL CELESTIA RESIDENCY E AND F AND MHADA0 mo overdueEXCEL HOUSING · Haveli, PuneP52100024681· filed Dec 2022 → now Oct 2026· 98.2% built· 1 complaint
- Aspire0 mo overdueM/s Radheshyam Developers · Borivali, Mumbai SuburbanP51800012142· filed Dec 2023 → now Oct 2026· 70.9% built· 2 complaints
- FLORA ICON0 mo overdueIMAGE SPACE INCORPORATED · MAJAREWADI, SolapurP52600048657· 90.9% built
- ANANTAM SKYONE0 mo overdueRAJSHREE LANDMARK LLP · DUDULGAON, PuneP52100049675· filed Dec 2025 → now Oct 2026· 81.8% built
- THE BUSINESS GATE0 mo overdueKesar Vasudev Properties · MOSHI, PUNE, PuneP52100029275· filed Mar 2024 → now Oct 2026· 81.8% built· 1 complaint
- Ayodhyanagar0 mo overdueGokhale Constructions · Kothrud, PuneP52100032277· filed Aug 2025 → now Oct 2026· 72.7% built
- PRAJOL AASHIYANA B WING0 mo overdueRAJESH MARUTI KADAM · PIMPRI CHINCHWAD, PuneP52100046787· filed Aug 2024 → now Oct 2026· 81.8% built
- Govind Ameya0 mo overdueMansarovar Constructions · Pushpak Node-Vadghar, RaigarhP52000052924· filed Dec 2025 → now Oct 2026· 77.7% built
- SAI PALACE0 mo overdueVARDHAMAN DEVELOPERS · SHAHAPUR, ThaneP51700033001· 90.9% built
- Ramchintan Park0 mo overdueMewani Infrstrcture · Aurangabad, AurangabadP51500006207· filed Sept 2022 → now Oct 2026· 53.8% built
- Eknath Gruh0 mo overdueEknath Gruh · Borivali, Mumbai SuburbanP51800077854· 81.8% built
- PRATHAM YASH VRINDAVAN II0 mo overduePRATHAM YASH BUILDERS · CHOVISAWADI, PuneP52100026265· filed Jun 2023 → now Oct 2026· 81.8% built· 1 complaint
- AJINKYATARA RESIDENCY0 mo overdueKRUSHNA AAVISHKAR REALTIES · PRASHANT NAGAR PARISAR, DhuleP49800033990· 56.4% built
- Laxmina Krishna Niwas0 mo overdueLaxmina Krishna Niwas · Kurla, Mumbai SuburbanP51800052240· filed Mar 2026 → now Oct 2026· 90.9% built
- AURA BLUE0 mo overdueFORTUNE REALTY GROUP · Mulshi, PuneP52100032711· filed Oct 2024 → now Oct 2026· 70.5% built
- Vogue 250 mo overdueGOODBRICK REALTY PRIVATE LIMITED · Kunenama, PuneP52100048304· filed Oct 2025 → now Oct 2026· 78.2% built
- SILVER WOODS0 mo overdueNilesh Vilas Dhumal · A ward Ayodhya colony, KolhapurP53000030911· filed Dec 2024 → now Oct 2026· 90.9% built
- YES CENTRAL GALLERIA 10 mo overdueYES ENTERPRISES · SONKHAR MUMBRA, ThaneP51700049599· 54.5% built
- SAMARTH COUNTY0 mo overdueD A BORADE AND SONS · Haveli, PuneP52100029698· filed Dec 2025 → now Oct 2026· 84.1% built
- DREAM CITY -A BUILDING0 mo overdueTANAJI SADASHIV PANSARE · JALOCHI, PuneP52100053419· 81.8% built
- AMEY APARTMENTS0 mo overdueAMEY REALTY AND CONSTRUCTION LLP · ANDHERI EAST, Mumbai SuburbanP51800045221· filed Dec 2025 → now Oct 2026· 73.6% built
- NICE GARDEN 20 mo overdueABHA BUILDERS · SHIL, ThaneP51700023376· filed Dec 2025 → now Oct 2026· 90.9% built
- PATELS PEARL0 mo overduePRAMUKH DEVELOPERS · DOMBIVLI, ThaneP51700076936· 71.4% built
- Ashiana Malhar Phase I and Commercial Block0 mo overdueAshiana Housing Limited · Mulshi, PuneP52100046049· 64.2% built· 1 complaint
- YES CENTRAL GALLERIA0 mo overdueNOBLE ENTERPRISES · SONKHAR MUMBRA, ThaneP51700049210· 60.9% built
- SAVA ARCADE0 mo overdueSAVA DEVELOPERS · At Post Asangaon, ThaneP51700078381· filed Mar 2026 → now Oct 2026· 50.9% built
- AMANN HIGHLAND PARK0 mo overdueMS RELLIANCE CONSTRUCTION CO · Borivali, Mumbai SuburbanP51800028085· filed Jun 2025 → now Oct 2026· 62.7% built· 1 complaint
- Prathamesh Sanskruti building of Abhinav Apartments Association0 mo overduePrathamesh Constructions · Sadashiv Peth, PuneP52100034849· filed Dec 2025 → now Oct 2026· 90.9% built
- SAFAL SAI AND SAFAL SAINATH0 mo overdueMANGALNATH DEVELOPERS PVT LTD · KELKARWADI, Mumbai SuburbanP51800009799· filed Dec 2023 → now Oct 2026· 65.2% built· 16 complaints
- Gami and Jaydeep Ventura Commercial Hub0 mo overdueM/S REAL INFRASTRUCTURE CO · Borivali, Mumbai SuburbanP51800052432· filed Dec 2025 → now Oct 2026· 89.6% built· 5 complaints
- HARSH TULIP0 mo overdueHARSH DEVELOPERS & INFRASTRUCTURE LLP · Ward FNorth, Mumbai CityP51900051870· 81.8% built
- HEXA TOWERS WING D0 mo overdueDML ASSOCIATES · DUDULGAON, PuneP52100046361· filed Dec 2024 → now Oct 2026· 90.9% built
- BHAKTI WINDSOR0 mo overdueBHAKTI REALTORS · KALYAN WEST, ThaneP51700033913· 90.9% built
- BHAGIRATH PARK0 mo overdueSHREE CONSTRUCTION · SR CTS GAT NO 450/1/1 SATPUR, NashikP51600049007· 64.7% built
- ASAVARI CO OP HSG SOC LTD0 mo overdueTrimity Constructions · NAUPADA, ThaneP51700045809· filed Dec 2024 → now Oct 2026· 90.9% built
- ACE ARISTO0 mo overdueGAURAV LAND CORPORATION · THANE WEST, ThaneP51700053626· 81.8% built
- TIRUPATI APARTMENTS CHSL0 mo overdueTIRUPATI APARMTNETS CO OPERATIVE HOUSING SOCIETY LIMITED · Kurla, Mumbai SuburbanP51800048581· filed Oct 2025 → now Oct 2026· 72.7% built
- YUGANDHAR SUDAMA0 mo overdueChaturthi Vastu Developers · Kalyan, ThaneP51700009697· filed Jul 2026 → now Nov 2026· 47.3% built
- Solitaire Business Hub Baner0 mo overdueAtul Builders · Baner, PuneP52100008740· filed Jun 2023 → now Nov 2026· 81.8% built