The Promise Ledger — Maharashtra
Every brochure quotes one possession date. MahaRERA is the only place that also keeps the date the builder originally filed. This page is the gap between the two — recomputed live from official disclosures for every project we track, so each number is checkable against the registration it came from.
- 21,384 projects have pushed their possession date by 3 months or more. The typical slip is 0.3 years; the average is 1.2.
- 55% of the projects still building are already past the date they filed — and another 27% are short of the pace needed to hit it.
- Those slips add up to 9.8 L buyer-years of extra waiting across 7.4 L homes that were already sold.
Can they still hand over on the date they're selling?
Every under-construction project that discloses both a possession date and a construction percentage, placed by how much time it has left and how much of the build is done. The red line is the pace a site must sustain from here to finish on time — anything below it is being sold on a date its own filing doesn't support.
Swipe the plot sideways for the rest of the timeline.
The end columns are catch-alls: 6,219 projects more than 5 years overdue sit in the first column, and 62 due more than 7 years out sit in the last.
Where each year's promises actually went
Projects grouped by the possession year their builder first filed — only years that have already arrived — and how much of each cohort has since moved the date.
- 201723% moved · avg +1.5 yrs
- 201829% moved · avg +2.3 yrs
- 201934% moved · avg +3.3 yrs
- 202047% moved · avg +2.4 yrs
- 202141% moved · avg +2.8 yrs
- 202228% moved · avg +2.8 yrs
- 202328% moved · avg +2.9 yrs
- 202432% moved · avg +2.3 yrs
- 202543% moved · avg +1.7 yrs
- 202656% moved · avg +0.7 yrs
When a date moves, how far does it move?
Distribution of the 21,384 slips on record. The longest single slip here is 15.9 years.
- 3–12 months14,098
- 1–2 years3,299
- 2–3 years1,354
- 3–5 years1,594
- 5+ years1,039
Which builders keep the date they filed
Share of each developer's dated projects that never pushed possession, over developers with 5 or more such projects here — a perfect record on two projects isn't a record. A kept date and a low PropPin Score can sit together: the score also carries complaints, warrants, litigation and mortgages, so a builder who hits every deadline can still be answering for everything else.
Best kept-date record
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Karnataka Slum Development Board | 37 | 100% | 100 · A+ |
| Rajiv Gandhi Housing Corporation Limited | 23 | 100% | 100 · A+ |
| Bhavisha Properties | 14 | 100% | 100 · A+ |
| NIMISH LAXMICHAND PASAD | 13 | 100% | 63 · C |
| H RISHABRAJ REALTY | 11 | 100% | 33 · D |
| ROMELL REAL ESTATE PRIVATE LIMITED | 11 | 100% | 54 · C |
| Sattva Resi Private Limited | 11 | 100% | 100 · A+ |
| SWARA CONSTRUCTION | 10 | 100% | 69 · B |
| GAURAV VISHVANATH AWATI | 10 | 100% | 63 · C |
| GOVINDA CONSTRUCTION | 9 | 100% | 72 · B |
Most moved dates
| Developer | Proj. | Kept | Score |
|---|---|---|---|
| Ashdan Developers Private Limited | 16 | 0% | 30 · D |
| TEERTH DEVELOPERS AND TEERTH REALTIES JV | 15 | 0% | 43 · D |
| Pune Projects LLP | 11 | 0% | 27 · D |
| PATIL BUILDERS | 8 | 0% | 83 · A |
| Nirmal Lifestyle (Kalyan) Private Limited | 8 | 0% | 19 · D |
| Sanjivani Integrated Township LLP | 8 | 0% | 38 · D |
| MADHU HARSHAD DOSHI | 7 | 0% | 17 · D |
| STRAWBERRY CONSTRUCTIONS PVT. LTD. | 7 | 0% | 58 · C |
| RajHeramb Properties | 7 | 0% | 54 · C |
| Godrej Skyline Developers Limited | 7 | 0% | 14 · D |
Selling a date the build pace can't reach
Possession promised within two years, with more construction left than that time can cover at 2.5% a month. Projects reporting 0% are left out — on MahaRERA that is indistinguishable from “not disclosed”. These are the hardest questions to ask before booking.
- NEPTUNE ELEVE WING C · NEPTUNE VENTURES AND DEVELOPERS PRIVATE LIMITED0.9% built, due Dec 2026 · needs ~40 mo, has 2
- AMAR INFINITY · AMAR HARISHCHANDRA MANJREKAR0.6% built, due Dec 2026 · needs ~40 mo, has 2
- VAIBHAV CHOWK SRA CHS LTD · SUNIL MOHAN JOSHI3.6% built, due Dec 2026 · needs ~39 mo, has 2
- INA APARTMENT CO-OPERATIVE HOUSING SOCIETY LIMITED · YASH REALTORS2.3% built, due Dec 2026 · needs ~39 mo, has 2
- Venkatesh Pushpakala · SANJAY DNYNOBA JAGTAP1.5% built, due Dec 2026 · needs ~39 mo, has 2
- SADASHIV VISHNU · SADASHIV VISHNU1.5% built, due Dec 2026 · needs ~39 mo, has 2
- VIJAYA COMPLEX · PADMAVATI ENTERPRISES2.7% built, due Dec 2026 · needs ~39 mo, has 2
- VASANT PARK · S S R DEVELOPERS4.5% built, due Jan 2027 · needs ~38 mo, has 2
- MEGH MALHAR · VENUS AND DUSANE DEVELOPERS1.8% built, due Jan 2027 · needs ~39 mo, has 3
- Serenity- Bldg 1 · JVPD Properties Private Limited7.3% built, due Nov 2026 · needs ~37 mo, has 1
The longest single slips on record
Originally filed date → the date the same registration quotes today.
- TRANQUILITY ANNEXE PHASE 22026 → 2041 +15.9 yrs
- INDRADHANU-Phase-52020 → 2035 +15.9 yrs
- GOKULPARK TOWER NO 12018 → 2033 +15 yrs
- SHREE HARIKRISHNA PLAZA2019 → 2032 +12.7 yrs
- Treeline 62019 → 2032 +12.3 yrs
- IMPERIAL HEIGHTS2023 → 2036 +12.3 yrs
- Neuleaf Techd2021 → 2033 +12.3 yrs
- NANDANVAN2016 → 2029 +12.3 yrs
- THE DESTINATION2023 → 2035 +12 yrs
- BLOSSOM GARDEN2019 → 2031 +11.9 yrs
What buyers did about it
Complaints, misc. applications and recovery warrants disclosed per project. 34,455 projects here have a clean record; 3,513 disclose pending litigation and 2,315 are mortgaged to a lender.
- Serenity- Bldg 1392 records
- Ruparel Optima Ph I322 records
- Alta Monte and Signet310 records
- Ruparel Skygreens I272 records
- Gaurav Discovery180 records
- VAASTU IMPERIAL Wing A151 records
- Godrej Meadows130 records
- SUBURBIA ESTATE PHASE 1129 records
- Godrej Hill Retreat129 records
- Lawns And Beyond - Phase 2, Omkar International District127 records
How these numbers are made
Source. Official MahaRERA portal disclosures for every project we track, recomputed 31 Oct 2026. Nothing here is our estimate of a project — it is the promoter's own filing, re-read.
"Moved the date". The currently proposed completion date is 3 calendar months or more after the original completion date in the same registration. A shorter gap is filing noise, not a broken promise. Slips are measured in calendar months, so a date pushed by exactly two years reads as exactly two years.
The pace line. The feasibility frontier assumes a site can sustain 2.5% of its total build per month — roughly foundation to finish in 40 months. A project below the line isn't doomed; it is claiming a pace faster than a tower typically holds, and that is worth asking about.
Buyer-years. Each delayed project's slip in years multiplied by the homes it had already sold, summed. It measures waiting created, not compensation owed.
Complaints. Disclosed records, not adjudicated outcomes. A complaint is a buyer filing, not a finding of fault. Recovery warrants are MahaRERA's strongest enforcement action and are counted separately.
Developers. Promoter names are grouped by a fuzzy canonical key (stripping "Pvt Ltd", "Developers", "Realty" and the like), so the same builder filing under slightly different names lands in one row.