RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 44 of 59
- LOTUS COURT2.6 yr overdueKRISHNA CONSTRUCTIONS · KharadiP52100008752· filed Dec 2022 → now Dec 2023· 90.9% built· 3 complaints
- AASHVI HEIGHTS2.6 yr overdueAASHVI GROUP · Panvel, RaigarhP52000019874· 27.3% built
- 173 West Oaks2.6 yr overdueSigma Housing · Wakad, PuneP52100024201· 79.6% built
- HIRA KUTIR CHS LTD2.6 yr overdueH RISHABRAJ PROJECTS · Borivali, Mumbai SuburbanP51800005267· 9.1% built
- AKASH PRESTIGE2.6 yr overdueDEEPAK ANANDA DHANOKAR · KARMYOGI NAGAR, NashikP51600023118· 84.5% built
- PANCHAVATI PALACE2.6 yr overdueCHINTAMANI CONSTRUCTION · BHUSAWAL, JalgaonP49900021412· 0.1% built
- MAHAVIR SADAN B2.6 yr overdueRajesh Construction · Palghar, PalgharP99000028787· 90.9% built
- AASAWARI CO. OP. HSG.SOCIETY2.6 yr overdueVYAS BUILDCON PVT. LTD. · IDEAL COLONY, PuneP52100024235· 81.8% built
- DAMODARPRIYA2.6 yr overdueSHREE CHAMUNDA REALTY · NAVI MUMBAI, RaigarhP52000023284· 98.5% built
- 39 PART PLUS 40 PART WADGAON KH TAL HAVELI DIST PUNE PHASE I2.6 yr overduePMAY CELL,PUNE MUNICIPAL CORPORATION · WADGAON KH, PuneP52100023682· 90.9% built
- Horizons at Wakad, Phase-22.6 yr overdueADI REALTIES · Wakad, PuneP52100024872· 70.9% built
- ASHOK ODYSSEY - B WING2.6 yr overdueSANYAM REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800004418· 90.9% built· 5 complaints
- Annapurna Aquarius2.6 yr overdueAnnapurna Properties · BHAYANDER WEST, ThaneP51800002185· 90.9% built
- GREEN SQUARE2.6 yr overdueRASKAR REALTORS THROUGH ITS PROPRIETOR VIJAY NIVRUTTI RASKAR · BORHADEWADI MOSHI, PuneP52100018311· 81.1% built
- Prakash Pratima2.6 yr overdueAnant Developers · GARIBACHA WADA, ThaneP51700022999· 43.6% built
- Orange City Wholesale Market - Phase II2.6 yr overdueORANGE CITY MALLS PRIVATE LIMITED · Danagunj, NagpurP50500014989· 27.3% built
- Green Heights2.6 yr overdueGreen Environment Constructions · Thane, ThaneP51700004561· 90.9% built
- PEARL PLATINUM2.6 yr overdueCHANDIWALA ENTERPRISES · Andheri, Mumbai SuburbanP51800004462· 42.7% built
- ORION WEST2.6 yr overdueGIRISH & ASSOCIATES · Andheri, Mumbai SuburbanP51800023726· 90.9% built
- EMPIRE HEIGHTS2.6 yr overdueMAHADEV LIFESPACES LLP · NODE DRONAGIRI, RaigarhP52000016430· 88% built
- Orange City Wholesale Market-Phase I2.6 yr overdueORANGE CITY MALLS PRIVATE LIMITED · Danaganj, NagpurP50500015077· 27.3% built
- RAJ RESIDENCY2.6 yr overdueSUMAN ASSOCIATES · RADHESHWARI NAGAR CO-OPERATIVE HOUSING SOCIETY, PuneP52100015150· 90.9% built
- YOGI MILAN PHASE IV2.6 yr overdueSHIV BUILDERS · SILVASSA, Dadra & Nagar HaveliP49600000084· 90.9% built
- MAN RESIDENCES2.6 yr overdueMERINO SHELTERS PRIVATE LIMITED · NERUL, ThaneP51700008980· 31.4% built
- Mateshwari Altura B and C Wing2.6 yr overdueMateshwari Realtors · Kalyan, ThaneP51700010188· 64.1% built· 27 complaints
- ARKADE EARTH - EBONY2.6 yr overdueArkade Developers Private Limited · Kanjurmarg East, Mumbai SuburbanP51800008953· 88.5% built· 1 complaint
- CHINTAMANI HABITAT DAFFODILS TYPE A1 - D2.6 yr overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · Shahapur (CT), ThaneP51700001558· 46.1% built
- Kunal Iconia -commercial phase 12.6 yr overdueKunal Sulakshan Associates · mamurdi, PuneP52100006222· 81.8% built
- Samraat Apna Ghar Phase-II2.6 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Someshwar Satpur Link Road Near DJ Reva Meadows, NashikP51600020657· 89.1% built
- K K HEIGHTS2.6 yr overdueK K DEVELOPERS · Nanded Waghala (M Corp.), NandedP51100014171· 27.3% built
- ONE Gangapur2.6 yr overdueCHARUSHILA SUNIL KHUNE · near Jehan circle, NashikP51600025974· 27.3% built
- DESHBHAKTA HARINARAYAN SONI CITY D-WING2.6 yr overdueSoni Somani Infrastructure · Laxmi Peth, SolapurP52600021721· 81.8% built
- AURUM2.6 yr overdueKAMAL DEVELOPERS · NAVI MUMBAI, RaigarhP52000024006· 90.9% built
- GEETANJALI RESIDENCY2.6 yr overdueSwami Samarth Builders and Developers · Tisgaon, AurangabadP51500014296· 90.9% built
- Goodwill Fabian Phase 12.6 yr overdueChoice Developments · lohgaon, PuneP52100019512· 98.2% built
- KONARK ALPHA2.6 yr overdueTreon Developers LLP · KHARADI, PuneP52100023108· 72.7% built
- PARISHRAM RESIDENCY CO-OP HSG SOC LTD2.6 yr overduePARISHRAM RESIDENCY CO OPERATIVE HOUSING SOCIETY LIMITED · NR COMFORT ZONE, NashikP51600020643· 81.8% built
- NABHA NAYAN APARTMENT2.6 yr overdueGAURAV CONSTRUCTION · PATHARDI SHIVAR, NashikP51600015193· 90.9% built
- 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati2.6 yr overdueAmravati Housing And Area Development Board Amravati · Akoli, AmravatiP50300023822· 13.6% built
- VISION HEIGHTS WING D2.6 yr overdueFIONA REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800010431· filed Jun 2021 → now Dec 2023· 81.8% built
- MINAKSHI MAHADEV VILLA2.6 yr overdueSHARMILA DILIP THAKUR · Ulwe Node Navi Mumbai, RaigarhP52000024608· 73.2% built
- ANIRUDHA SAI2.6 yr overdueSHANKAR SHIMGYA PATIL · Ulawe, RaigarhP52000006099· filed Dec 2018 → now Dec 2023· 90.9% built
- FIA EKDANTA2.6 yr overdueMYSTIQUE DEVELOPERS · NEAR NEST HOTEL, PalgharP99000020344· 90.9% built
- Shree Datta Leela Apartment2.6 yr overdueYADUNATH BABURAO VIBHUTE · Rane Nagar, NashikP51600015635· 90.9% built
- Kalpataru Radiance D2.6 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800000579· filed Jun 2022 → now Dec 2023· 97.2% built· 47 complaints
- ANUSAYA HERITAGE2.6 yr overdueM/S Sudip Developers · DUDULGOANP52100016207· 1.6% built
- Kohinoor Square Phase 22.6 yr overdueKohinoor CTNL Infrastructure Company Private Limited · Ward GNorth, Mumbai CityP51900012308· 81.8% built· 2 complaints
- Building A3 Eon homes2.6 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100013714· 54.4% built· 2 complaints
- Bhavani Heights2.6 yr overdueKalyani Enterprises · Badlapur (M Cl), ThaneP51800003594· 59.1% built· 9 complaints
- SHREE SAI GOPALKRISHNA BABA INDUSTRIAL PREMISES2.6 yr overdueNEWLOOK ELECTRONICS CENTRE PVT LTD · Atgaon, ThaneP51700005758· 45.5% built
- BA Swadesha- Phase 12.6 yr overdueSpectrum Realty · Moshi Borhadewadi, PuneP52100024275· 71.4% built· 1 complaint
- Venkatesh Paradise B wing2.6 yr overdueSANJAY DNYANOBA JAGTAP · BUND GARDEN ROAD, PuneP52100001428· 37.5% built
- RUDRAKSHA BUILDING NO 112.6 yr overdueRAJ UNIVERSAL · DAHISAR EAST, Mumbai SuburbanP51800021545· filed Dec 2022 → now Dec 2023· 90.9% built· 1 complaint
- SHIVRAJ RESIDENCY2.6 yr overdueSHREE SAI DEVELOPERS · PIRANGUTE, PuneP52100022479· 81.8% built
- Emerald Isle - T152.6 yr overdueLarsen & Toubro Ltd. (Realty Division) · Kurla, Mumbai SuburbanP51800013214· 90.2% built· 5 complaints
- YashONE Hinjawadi - Phase 12.6 yr overdueVilas Javdekar Eco Shelters Private Limited · Hinjawadi, PuneP52100019468· 99.2% built
- DEEP CITY2.6 yr overdueDEEP MILAN ENTERPRISES · Panvel, RaigarhP52000010544· 89.1% built
- RIOLAND A WING2.6 yr overdueWAMAN KALATE INFRASTRUCTURE · WAKAD, PuneP52100024033· 72.7% built
- Sunrise B2.6 yr overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000922· 93.9% built· 1 complaint
- SHRIDATTADARSHAN APARTMENT2.6 yr overdueSAHYADRI BUILDCON · DAMODAR NAGAR, NashikP51600023976· 90.9% built
- GOPALKRISHNA SANKUL2.6 yr overdueMAAD CONSTRUCTION · NAIGAON EAST, PalgharP99000010352· 87.3% built
- SHREE SHASWAT BUILDING NO 152.6 yr overdueWHITE HEAVEN REALTY · PLEASANT PARK, ThaneP51700021222· 63.6% built
- RAJ BAUG2.6 yr overdueNEHALDHARA REALTORS · Neral, RaigarhP52000000813· 28.5% built
- VISION STARWEST PHASE - 22.6 yr overdueVISION CREATIVE DEVELOPERS · TATHAWADE, PuneP52100026625· 90.9% built
- MAYANK2.6 yr overdueRANADE REALTORS LLP · GHORPADI, PuneP52100022751· 73.2% built
- ECO HEIGHTS2.6 yr overdueETCO BUILDERS PRIVATE LIMITED · NITYANAND NAGAR, Mumbai SuburbanP51800002429· 90.9% built· 9 complaints
- The Universe II2.6 yr overdueG.E.CONSTRUCTIONS · Thane (M Corp.), ThaneP51700006721· 90.9% built
- ARKADE EARTH-DAFFODIL2.6 yr overdueArkade Developers Private Limited · Kanjurmarg East, Mumbai SuburbanP51800004440· 88.5% built
- ATHARVA2.6 yr overdueKedar Vikasrao Deshpande · Baner, PuneP52100022966· 90.9% built
- KRISHNA KUNJ2.6 yr overduePRANIT VASANT SHEDJI · OTHONIAL COLONY, SangliP53100021380· 81.8% built
- Sunrise A2.6 yr overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000635· 98.5% built· 1 complaint
- The Cliff Garden2.6 yr overdueVH Township Private Limited · Maan, Hinjawadi, PuneP52100015759· 90.9% built
- BHOOMI CELESTIA -A1 WING2.6 yr overdueSASHWAT CONSTRUWELL PRIVATE LIMITED · Librity Garden, Opp. S.N.D.T. Girls Collage, Mumbai SuburbanP51800010810· filed Dec 2022 → now Dec 2023· 63.6% built
- KINGSBURY PHASE II2.6 yr overdueJaikul Associates · D Y PATIL COLLEGE AREA, PuneP52100019148· 90.9% built
- REDEVELOPMENT OF PUSHPAWADI CHSL2.6 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800028108· 43.6% built
- MANORAMA HEIGHTS2.6 yr overdueMAULI KRUPA DEVELOPERS · SECTOR NO 9, PuneP52100024419· 28.2% built
- Majestique Rhythm County Phase I2.6 yr overdueMAJESTIQUE RISINGSUN LLP · Autade Handewadi, PuneP52100019616· 90.9% built
- BHAWANI CONSTRUCTION2.6 yr overdueBHAWANI CONSTRUCTIONS · Mira-Bhayandar (M Corp.), ThaneP51700012204· 27.3% built
- DEV SAI GARDEN2.6 yr overdueDEV HOMES · Navade, RaigarhP52000014142· 90.9% built
- INDRAPRASTHA RESIDENCY2.6 yr overdueYASHWARDHAN CONSTRUCTIONS PVT LTD · Railway Lines, SolapurP52600022139· 4.5% built
- Runwal Bliss Wing - A2.6 yr overdueEvie Real Estate Private Limited · Kurla, Mumbai SuburbanP51800001670· 98% built· 9 complaints
- Shree Krishna Residency2.6 yr overduePanchala Builders & Developers · Ambernath, ThaneP51700014692· 90.9% built
- ARUN AION2.6 yr overduecelesta developers · Chinchwad, PuneP52100018655· 90.9% built· 1 complaint
- FENNEL H2.6 yr overdueROYALE URBANSPACE LLP · SHAHAPUR, ThaneP51700003652· 78.7% built
- RACHANA ETERNIA2.6 yr overdueAthang Spaces LLP · BANER, PuneP52100024077· 81.8% built· 1 complaint
- GAMI REAGAN2.6 yr overdueSHRI GAMI INFOTECH PVT LTD · Thane, ThaneP51700013200· 93% built
- MARATHON NEXZONE AURA -22.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000669· 72.7% built· 6 complaints
- Dream Opal2.6 yr overdueD D Constructions · Ulawe, RaigarhP52000013656· 90.5% built
- EKJYOT SANMAAN2.6 yr overdueDHEERAJ P VOHRA · Kurla, Mumbai SuburbanP51800011782· 90.9% built· 1 complaint
- Altus2.6 yr overdueArham Lifespace Realty · Balewadi, PuneP52100020726· 81.8% built
- CHANDRABHAGA PLAZA2.6 yr overdueVINAYAK GANPAT OWALEKAR · ULWE NODE NAVI MUMBAI, RaigarhP52000024226· 73.4% built
- NAV-VISHWADHAM CHSL2.6 yr overdueWOLFPACK HOUSING CORPORATION · Andheri, Mumbai SuburbanP51800001669· 90.9% built
- DAFFODILS K BUILDING2.6 yr overdueVISHHRAM DEVELOPERS · SOMATANE, PuneP52100011485· 81.8% built· 1 complaint
- PATELS ELYSIUM - 62.6 yr overdueAPACE REALTY · Ambarnath(M Cl), ThaneP51700009032· 35.5% built
- Royal Sandesh Dawa Bazar2.6 yr overdueGARG HOTELS & REAL ESTATE PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500009211· 73.9% built
- Metro Life Maxima Residences Phase II2.6 yr overdueRAMA SYNERGY SPACES · Next to Indira College of Commerce and Science, PuneP52100023984· 75.3% built· 11 complaints
- GOODWILL FABIAN PHASE 22.6 yr overdueChoice Developments · LOHGAON, PuneP52100027517· 99.1% built
- SANDESH CITY APARTMENTS- 42.6 yr overdueSandesh Infrastructures Pvt Ltd · Jamtha, NagpurP50500010124· 81.2% built· 1 complaint
- MANGAL PUSHP HEIGHTS2.6 yr overdueSUNIL MANGILAL JAIN · Thane, ThaneP51700009090· 33.2% built
- ASEEM2.6 yr overdueRANADE REALTORS LLP · GHORPADI, PuneP52100023060· 82.5% built
- DATTANI LINEAR WING ABC PHASE I2.6 yr overdueBRIJESH SATISH DATTANI · Vasai, PalgharP99000008218· 81.4% built· 1 complaint
- SHATRUNJAY GIRIRAJ2.6 yr overduePRAMUKH REALTORS · Kurla, Mumbai SuburbanP51800009451· filed Dec 2022 → now Dec 2023· 82.9% built
- HILLVEW RESIDENCY PHASE I PROJECT III BLDG N AND O2.6 yr overdueKUMAR BEHARAY PROPERTIES LLP · BEHIND MAHATMA SOCIETY KOTHRUD, PuneP52100014885· 90.9% built
- MANAHIL HEIGHTS2.6 yr overdueK D CONSTRUCTION · Chiplun (M Cl), RatnagiriP52800011982· 52.7% built
- Gingelia Residential2.6 yr overdueAcme Housing India Private Limited · Thane (M Corp.), ThaneP51700001033· filed Dec 2022 → now Dec 2023· 51.7% built· 8 complaints
- Terraform Dwarka2.6 yr overdueMoney Magnum Nest Pvt Ltd · Kurla, Mumbai SuburbanP51800002826· 91.2% built· 1 complaint
- Lotus Pearls2.6 yr overdueSwayambhu Properties · Mamurdi, PuneP52100002516· 14.5% built
- HYDE PARK RESIDENCY F1 BUILDING PHASE2.6 yr overdueNEXUS BUILDERS AND DEVELOPERS PVT LTD · Thane, ThaneP51700008542· 90.9% built
- Lotus Paradise2.6 yr overdueDREAMHOMES DEVELOPERS · DighiP52100023815· 89.1% built
- Pushpak Paradise2.6 yr overdueKrishna Developers · Kala Nagar, NashikP51600024537· 90.9% built
- SOHAM HEIGHTS APARTMENT2.6 yr overdueHRUTURAJ BUILDERS AND DEVELOPERS · SHRAMIK NAGAR SATPUR, NashikP51600019461· 90.9% built
- BHALCHANDRA VIHAR PHASE - I / A and B2.6 yr overduePOLITE BUILDTECH · RAVET, PuneP52100015399· 82.7% built· 1 complaint
- SHRINIVAS PARK2.6 yr overdueSHRINIVAS BUILDCON · CIDCO WALUJ MAHANAGAR 1, AurangabadP51500022271· 90.9% built
- RADHA KRISHNA NIVAS PHASE 12.6 yr overdueNITIN GAJANAN KALE · Bhiwandi (M Corp.), ThaneP51700013772· 90.9% built
- GANPATI RESIDENCY2.6 yr overdueGANPATI RESIDENCY · Badlapur (M Cl), ThaneP51700011720· 49.5% built
- SAI KAMAL2.6 yr overdueACE DEVELOPER · NEXT TO KAUSHAL BUNGLOW, PuneP52100018894· 90.9% built
- SWAPNAPURTI2.6 yr overdueJ J REALTIES · RAHATANI PCMC, PuneP52100025050· 90.9% built
- SHAURYA SAMRUDDHI2.6 yr overdueSHAURYA DEVELOPERS · SHINDEWADI, SataraP52700008325· 5.7% built
- EKTA TRIPOLIS PHASE I2.6 yr overdueEKTA EVERGLADE HOMES PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800000947· filed Jun 2021 → now Dec 2023· 88.5% built· 75 complaints
- NAMRATA GLORIA2.6 yr overdueNAMRATA CONSTRUCTION · RAVET PUNE, PuneP52100003691· 72.7% built
- VARDHAN CITY2.6 yr overdueSATVASHIL DNYANDEV KADAM · SAIDAPUR KARAD, SataraP52700015384· 78.2% built
- PATELS ELYSIUM - 72.6 yr overdueAPACE REALTY · Ambarnath, ThaneP51700005803· 33.2% built
- SDPL Greens II2.6 yr overdueSANDEEP DWELLERS PVT. LTD. · Wanjara, NagpurP50500007483· 45.6% built
- GANGA LEGEND A4 AND B1..2.6 yr overdueLegends County Landmark Pvt Ltd · Bavdhan, PuneP52100000196· 76.9% built
- BAUG-E-MOHAMMED2.6 yr overdueRIZWAN HABIB MALIK · Ward E, Mumbai CityP51900010538· filed Dec 2022 → now Dec 2023· 90.5% built
- VAIBHAVI HEIGHTS2.6 yr overdueYASHPAL DEWANAND KHOBRAGADE · Datala, ChandrapurP50900008437· 87.9% built
- Millennium Manor2.6 yr overdueMillennium Developers · Chikhali, PuneP52100021632· 81.8% built
- Essgee Options One Phase I2.6 yr overdueGMJ BUILDERS & DEVELOPERS · Ward GNorth, Mumbai CityP51900017841· 81.1% built
- DAFFODIL GREENS F BUILDING2.6 yr overdueVISHHRAM NLP ASSOCIATES · DAUND, PuneP52100011911· 64.1% built· 2 complaints
- MAHAVIR KUNJ D WING B TYPE C2.6 yr overdueRajesh Realtors · Palghar, PalgharP99000028618· 90.9% built
- DATTANI VERTEX WING CD PHASE III2.6 yr overdueBRIJESH SATISH DATTANI · Vasai, PalgharP99000005990· 90.5% built
- GALAXY APARTMENT2.6 yr overdueORCHID CONSTRUCTION · Vasai-Virar City (M Corp), PalgharP99000011081· filed Dec 2018 → now Dec 2023· 90.9% built
- Kalpataru Radiance C2.6 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800000482· filed Jun 2022 → now Dec 2023· 97% built· 37 complaints
- Shivalik Sky2.6 yr overdueYogeshwar Realty · Wasan Nagar, NashikP51600014843· 90.9% built
- NAVDURGA SHIV COMPLEX - B WING2.6 yr overdueNAVDURGA SHIV COMPLEX - B WING · SAMISHRA NAGAR,, RaigarhP52000020317· 4.5% built
- Menlo Homes Hinjewadi Phase I2.6 yr overdueMenlo Homes LLP · Hinjewadi, PuneP52100014732· 81.8% built
- AMRUT TARA2.6 yr overdueShree Ram Buildeers · KANDIVALI WESTP51800015444· 90.9% built· 2 complaints
- ASHOK ODYSSEY - C WING2.6 yr overdueSANYAM REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800004602· 90.9% built· 10 complaints
- AUDUMBER SHRUSHTI2.6 yr overdueKATHOD DAMA BHOIR · NEAR ST LAWRENCE INTERNATIONAL SCHOOL, BEFORE MUTHA COLLEGE, MHASOBA NAGAR, UMBARDE, ThaneP51700015962· 30% built
- Bellezon2.6 yr overdueVivek Patrick Pimenta · Khopwadi, PalgharP99000022464· 20% built
- SIDDHIVINAYAK SANKUL2.6 yr overdueSHREE SAI BUILDERS AND DEVELOPERS · SAMARTHA NAGAR, BH NAIVADYAM HOTEL, NASHIK, NashikP51600021221· 97.3% built
- VARAD GARDEN2.6 yr overdueTRIMITI DEVELOPERS · NEAR CHINMAY GARDEN, SangliP53100030939· 90.9% built
- GALAXY2.6 yr overdueASWANI PARADISE · WAKAD, PuneP52100017540· 79.1% built· 3 complaints
- PALM SPRINGS PHASE - I2.6 yr overdueArvel Developers · ALIYALI VILLAGE, PalgharP99000016750· 89.1% built
- AGARWAL PALAZZO2.6 yr overdueBALAJI DEVELOPERS · BORIVALI WEST, Mumbai SuburbanP51800017406· 98.6% built
- Meghdoot Tower2.6 yr overdueV R Kulkarni & Associates · Haveli, PuneP52100020133· 90.9% built· 1 complaint
- VASANT OASIS ZINNIA BLDG 172.6 yr overdueNEEPA REAL ESTATES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000980· 40.9% built· 7 complaints
- Dominion Park2.6 yr overdueAmalfi Realty Pvt Ltd · Near PCMC water tank, PuneP52100024698· 10.5% built
- Vaiga2.6 yr overdueSOHANLAL SHANKARLAL VISHNOI · Chinchwad, PuneP52100022419· 99.8% built
- VARAD VINAYAK RESIDENCY2.6 yr overdueHIMANSHU SHAM TENDULKAR · MAHADEV ALI, PalgharP99000019232· 90.9% built
- Redevelopment of JUHU ANKUR CHS LTD2.6 yr overdueKDI HOLDINGS PVT. LTD. · Andheri, Mumbai SuburbanP51800004899· 90.9% built· 2 complaints
- Sandesh City Apartment 12.6 yr overdueSandesh Infrastructures Pvt Ltd · Jamtha, NagpurP50500006822· 91.1% built
- TAJ HERITAGE2.6 yr overdueFAYAZ AHMAD TAJODDIN MUJAHID · SECTOR 20, RaigarhP52000014777· 88.6% built· 1 complaint
- Siya Ram Residency2.6 yr overdueMakarand Madhav Kulkarni · Dharmadhikari Mala, AhmednagarP52200018653· 90.9% built
- OMKAR ENCLAVE2.6 yr overdueOMKAR ENTERPRISES · Kalyan, ThaneP51700007523· 90.9% built
- SNEH PARK2.6 yr overdueAssociated Recons LLP · KOTHRUD, PuneP52100027499· 72.7% built
- Shanti Enclave Phase II2.6 yr overdueSadguru Builders and Developers · Agashi, PalgharP99000024526· 44.1% built
- PRATHMESH DARSHAN2.6 yr overdueJAYDEEP MAHALAXMI CONSTRUCTION · Kurla, Mumbai SuburbanP51800009248· 72.2% built· 4 complaints
- ROMAN RESIDENCY2.6 yr overdueShantee Housing · Vasai, PalgharP99000021827· 90% built
- Nirman Altius Wing B2.6 yr overdueNIRMAN ASSOCIATES · KHARADIP52100020177· 90.9% built
- SDPL Paradise II2.6 yr overdueSANDEEP DWELLERS PVT. LTD. · Dabha, NagpurP50500006021· 90.9% built
- N B OPAL PHASE -I2.6 yr overdueNanasaheb Bhintade Spacess Pvt. Ltd. · Near Podar international school, PuneP52100023516· 98.2% built· 1 complaint
- Madhu Vasant CHS Ltd.2.6 yr overdueAmal Realtors Private Limited · Andheri, Mumbai SuburbanP51800000264· 78.2% built
- Dattaprasad Residency2.6 yr overdueVAASTU VAIBHAV CONSTRUCTIONS · Aagartakli, NashikP51600027844· filed Dec 2022 → now Dec 2023· 90.9% built
- Whista 1st Street2.6 yr overdueNarang & Mahaveer Developers LLP · Andheri, Mumbai SuburbanP51800013101· 35.7% built
- KRISHNAKALP2.6 yr overdueSHIVAM ENTERPRISES · KATRAP BADLAPUR, ThaneP51700022665· 90.9% built
- PEACE PLAZA2.6 yr overdueMOHAMMED NAJIB CHAWRE & OTHERS · NEAR ASHOKA KANISHKA, PalgharP99000021979· 36.4% built
- Bharat Ecovistas Phase II2.6 yr overdueBHARAT REALTY VENTURE PRIVATE LIMITED · Shilphata Junction, Thane, ThaneP51700000111· 95.5% built· 10 complaints
- Kyan Resorts And Clubs Private Limited Phase 32.6 yr overdueKyan Resorts & Clubs Private Limited · Mothe Wengaon, RaigarhP52000009821· 69.1% built
- SRISHTI OASIS PH 2 WING B SANDS2.6 yr overdueSHIV KRUPA ENTERPRISE · Kurla, Mumbai SuburbanP51800005548· filed Dec 2022 → now Dec 2023· 90.9% built· 1 complaint
- INDUSTRIAL BUILDING NO 12.6 yr overdueSHREE NARAYAN INDUSTRIAL DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000011126· filed Dec 2021 → now Dec 2023· 57.1% built
- SHREERAM CO OP SOCIETY2.6 yr overdueRAHUL ENTERPRISES · KPARKHAIRANE, ThaneP51700024549· 90.9% built· 1 complaint
- KABRA PRIMERA2.6 yr overdueKABRA ESTATE AND INVESTMENT CONSULTANTS · JVPD SCHEME, Mumbai SuburbanP51800015963· 94.5% built· 1 complaint
- REVELL ORCHID PHASE IV BUILDING F2.6 yr overdueABHAY INDRABHAN FULFAGAR · LOHEGAON, PuneP52100015949· 27.7% built
- DEDGAONKAR ARCADE2.6 yr overdueTRINITY FACADES PRIVATE LIMITED · GURUWAR PETH PUNE, PuneP52100021263· 70.9% built
- Siddhachal - A42.6 yr overdueViraj Properties (Now known as Viraj Properties & Real Estate Pvt Ltd) - Amogh Construction JV · Marketyard, PuneP52100018775· 90.9% built
- KUKREJA INFINITY2.6 yr overdueKUKREJA INFRASTRUCTURES · CIVIL LINES, NagpurP50500015438· 90% built
- The Cliff Garden2.6 yr overdueVH Township Private Limited · Maan, Hinjawadi, PuneP52100004906· 90.9% built
- AKSHAR EMPERIA GARDEN2.6 yr overdueEMPERIA REALTY · RASAYANI PATALGANGA, RaigarhP52000011872· 86.1% built
- New Suraj Tower2.6 yr overdueEkdanta Constructions and Developers · Thane, ThaneP51700015400· 90.9% built
- DLASA HEIGHTS2.6 yr overdueDLASA DEVELOPERS · Vasai, PalgharP99000010299· filed Dec 2018 → now Dec 2023· 95.5% built
- DAJI RESIDENCY2.6 yr overdueVW REALTY · MHATAVLI-URAN, RaigarhP52000015560· 90.9% built
- addressOne - Phase 52.6 yr overduePeninsula Land Limited · Near MCA Stadium Gahunje Pune, PuneP52100018855· 78.2% built· 5 complaints
- Golden Heights2.6 yr overdueGold Coin Builders · Andheri, Mumbai SuburbanP51800001552· 90.9% built
- MAN BUSINESS SPACES2.6 yr overdueMERINO SHELTERS PRIVATE LIMITED · NERUL, ThaneP51700006944· 21.8% built
- DK ELEGANCE2.6 yr overdueATMARAM MANOHAR GORE · RAVET PUNE, PuneP52100017792· 86.5% built
- Aura Grandeur2.6 yr overdueVSR Realty LLP · Pune City, PuneP52100010905· filed Jul 2019 → now Dec 2023· 90.9% built
- THE NATURE2.6 yr overdueANMOL DEVELOPERS · Karjat, RaigarhP52000004480· 90.9% built
- Sunrise C2.6 yr overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000625· 92.9% built
- MAA MAHALAXMI RESIDENCY2.6 yr overdueMAA VAISHNAVI INFRA · SINDHI (MEGHE), WardhaP50400020774· 95.5% built
- Sankalp Siddhi Wing E2.6 yr overdueGarve Patil Associates · Kalambe T. Thane (CT), KolhapurP53000004632· 30.5% built
- EWS- Akurdi2.6 yr overduePIMPRI CHINCHWAD MUNICIPAL CORPORATION · Haveli, PuneP52100026117· 23.3% built
- Aapla Ghar Wagholi Annex 2 Phase I2.6 yr overdueMaple Homes LLP · Shiraswadi, PuneP52100006608· 18.2% built
- JEWEL VISTA2.6 yr overdueJEWEL BUILDERS · Sonivali Village, ThaneP51700006876· 83.6% built
- EXCEL CELESTIA RESIDENCY2.6 yr overdueEXCEL HOUSING · PUNE, PuneP52100014266· filed Dec 2021 → now Dec 2023· 87.1% built
- 43 Privet Drive- C Building2.6 yr overdueS S Properties · Balewadi, PuneP52100025169· 70% built
- Sunrise D2.6 yr overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000640· 99.9% built· 3 complaints
- Emerald Park2.6 yr overdueBalasaheb Vyankatrao Gaikwad · Punawale, PuneP52100001532· 69.1% built
- COSMOS ENCLAVE - CHESTNUT2.6 yr overdueMONARCH DEVELOPERS · THANE, ThaneP51700015892· 90.9% built
- RAGHUNATH NAGAR2.6 yr overdueR K BUILDERS & DEVELOPERS · Nanded Waghala (M Corp.), NandedP51100015354· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.