RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 43 of 61
- AARADHANA RESIDENCY - A3.3 yr overdueA C JAIN BUILDERS AND DEVELOPERS LLP · OPP GOPAL NAGAR, NashikP51600025195· filed Dec 2022 → now Aug 2023· 90.9% built
- ALANKAPURI3.2 yr overdueLAIGUDE DEVELOPERS · wadgaon, PuneP52100010797· 67.5% built
- SHIVAAY SQUARE3.2 yr overdueISHANAVI CONSTRUTECH PVT LTD · MEHRUN, JalgaonP49900032755· 76.8% built
- WEST AVENUE3.2 yr overdueRAINBOW CONSTRUCTIONS · PANDI BHIMSEN KALAMANDIR, PuneP52100016725· filed Feb 2023 → now Aug 2023· 38% built
- Mohan Suburbia III3.2 yr overdueMOHAN LIFESPACES LLP · Khoj Kuntawli, ThaneP51700021395· filed Jun 2022 → now Aug 2023· 90.5% built
- NEST-IN3.2 yr overdueSUNIL JYOTIRAO KOKITKAR · NEAR Awati Motors, SangliP53100030183· 90.9% built
- MANGAL VASUDHA3.2 yr overdueMANGAL CONSTRUCTION · Jule Solapur, SolapurP52600034005· 10.1% built
- SULOCHAN PARK3.2 yr overdueASHWAMEDH SPACES PRIVATE LIMITED · Vanaj Paramhansnagar, PuneP52100029020· 90% built
- SUNSET HEIGHTS 23.2 yr overdueALFA CONSTRUCTIONS · BADLAPUR GAON, ThaneP51700018798· filed Jun 2022 → now Aug 2023· 90% built
- TWIN TOWERS3.2 yr overdueGAYATRI PROPERTIES · MANJARI Bk, PuneP52100005036· filed Aug 2022 → now Aug 2023· 81.8% built
- ARIHANT PARK PHASE 93.2 yr overdueMADAN NEMICHAND BAFANA · NEAR GANESH TEMPLE, AhmednagarP52200031254· 90.9% built
- SHREE SANKET GARDEN3.2 yr overdueSHREE SANKET DEVELOPERS · Near Hotel Yash Garden, Nilgavhan Shivar, NashikP51600003519· filed Jan 2022 → now Aug 2023· 90.9% built
- Vishnu krupa Apartment3.2 yr overdueSomnath Shivaji Gaikwad · Choudhary parkP52100019404· 81.8% built
- Shiv-Darshan Residency3.2 yr overdueSomnath Shivaji Gaikwad · Dutta nagar, DighiP52100016219· 81.8% built
- Lodha Patel Estate - Tower G3.2 yr overdueMACROTECH DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800016528· 90.9% built
- Aqua Millennium3.2 yr overdueMILLENNIUM LEGACY DEVELOPERS · RAVET, PuneP52100022420· 81.8% built
- HEMA KUNJ3.2 yr overdueBHADRANKAR ENTERPRISES LLP · Thane, ThaneP51700028739· 41.8% built· 1 complaint
- addressOne - Phase 43.2 yr overduePeninsula Land Limited · Near Maharashtra Cricket Association Stadium Gahunje Pune, PuneP52100015803· 78.2% built· 4 complaints
- Legacy Millennia3.2 yr overdueINFINITY DEVELOPERS · Punawale, PuneP52100022379· 81.8% built
- Ramshraddha Apartment3.2 yr overdueM/S RAM GROUP · -, SataraP52700022388· 81.8% built
- Joyville Virar Phase 53.2 yr overdueJoyville Shapoorji Housing Private Limited · virar, PalgharP99000019531· 99.8% built
- Ceratec Avika3.2 yr overdueAnand Dayanand Agarwal · Yewalewadi, PuneP52100013774· 14.1% built
- DEVESH3.2 yr overdueOM CONSTRUCTION CO · BHAYANDAR, ThaneP51700007526· 36.4% built
- ANCHAL GALAXY3.2 yr overdueCLORIS CONSTRUCTION PRIVATE LIMITED · Palghar, PalgharP99000021893· 0% built· 1 complaint
- KUMAR PALMCREST A4 BUILDING3.2 yr overdueKUMAR PROPERTIES AND PROMOTERS PRIVATE LIMITED · PISOLI, PuneP52100022295· 61.8% built
- LAKHANI ROYALE3.2 yr overdueLAKHANI BUILDERS PVT LTD · Panvel, RaigarhP52000014323· 98.6% built
- SHIV JIVDANI SADAN3.2 yr overdueSHUBHAM BUILDERS & DEVELOPERS · GARIBACHA WADA, ThaneP51700021173· filed May 2022 → now Aug 2023· 19.1% built
- SAI REGENCY3.2 yr overdueSAI DEVELOPERS · NEAR AYYAPPATEMPLE, GAURIPADA, ThaneP51700013647· filed Dec 2018 → now Aug 2023· 89.8% built· 14 complaints
- BHOOMI AVENUE3.2 yr overdueBHOOMI ENTERPRISES · AMBERNATH (E), ThaneP51700029068· 90.9% built
- SAI VILLA3.2 yr overdueBUILT TECH BUILDERS & DEVELOPERS PVT. LTD. · BADALAPUR GAON, ThaneP51700015189· filed Dec 2022 → now Aug 2023· 90% built· 1 complaint
- RISHABRAJ PRIDE3.2 yr overdueRRIL LIMITED · DAHISAR WEST, Mumbai SuburbanP51800031144· 90.9% built
- Rajhans Helix 33.2 yr overdueRajhans Infracon (India) Private Limited · Kurla, Mumbai SuburbanP51800007413· filed Dec 2019 → now Aug 2023· 90.9% built
- VIRAJ HEIGHTS3.2 yr overdueVENKATESH DEVELOPERS · DHANORI, PuneP52100026384· 90.9% built· 1 complaint
- VEDANT RESIDENCY3.2 yr overdueVEDANT BUILDCON · Dhule (M Corp.), DhuleP49800012302· filed Aug 2020 → now Aug 2023· 90.9% built
- INDOSHIVA TOWER3.2 yr overdueINDOSHIVA CONSTRUCTION · VAKHARBHAG, SangliP53100030141· filed Dec 2022 → now Aug 2023· 90.5% built
- Skyi Star Town Commercial3.2 yr overduePate Life Melange Developers Pvt Ltd · Bhukum, PuneP52100013211· filed Feb 2021 → now Aug 2023· 90% built· 4 complaints
- CHANDRA BHAGA3.2 yr overdueVITTHAL MAULI CONSTRUCTION COMPANY · KATEMANEVALI, ThaneP51700010487· filed Jun 2021 → now Aug 2023· 34.5% built
- Shree Prafull CHSL3.2 yr overdueShree Shyam Developers · KANDIVALI WEST, Mumbai SuburbanP51800009183· filed Mar 2021 → now Sept 2023· 90.5% built
- Pankaj Co-Op Housing Society Ltd.3.2 yr overdueAditya Associates · Sahakar Colony, Brahmin Society, Thane (W), ThaneP51700034605· 90.9% built
- SIDDHIVALLABH VASTU3.2 yr overdueASSOCIATED DEVELOPERS · NEAR MARUTI TEMPLE, SangliP53100028655· 81.8% built
- Sai Vishwa3.2 yr overdueGAURAV VISHVANATH AWATI · govind nagar, AhmednagarP52200032441· 90.9% built
- KST AANANDLAXMI3.2 yr overdueSARJERAO ANANDRAO PATIL · AGASHIVNAGAR, SataraP52700021105· 90.9% built
- Hundiwale3.1 yr overdueAditya Associates · Thane, ThaneP51700046290· 90.9% built
- RAHI RESIDENCY3.1 yr overdueSAMRUDDHI ASSOCIATES · LATUR, LaturP52400032536· 90.9% built
- NIRMAL ANAND CHS3.1 yr overdueNirmal Anand CHS LTD · Andheri, Mumbai SuburbanP51800007180· filed Sept 2022 → now Sept 2023· 90.9% built
- SHIV RUDRA APARTMENT3.1 yr overdueCHATURBHAI DHIRUBHAI KACHA · OPP GURUGOVIND SINGH SCHOOL, NashikP51600030020· 76.4% built
- SAIRAJ EMERALD3.1 yr overdueSAIRAJ ENTERPRISES · BADLAPUR WEST, ThaneP51700049097· 71.8% built
- URBAN REALTY3.1 yr overdueJ G ENTERPRISES · Gawade Mala, Bhistbag, AhmednagarP52200032512· 97.3% built
- Dhumravarna Heights3.1 yr overdueKanta Madhusudan Trivedi · Nagpur (M Corp.), NagpurP50500006544· filed Sept 2018 → now Sept 2023· 58.2% built
- FLORACITY3.1 yr overduePREETANSH REALTY LLP · SHENDRA, AurangabadP51500018071· 81.5% built
- BROOKLYN PARK PHASE II3.1 yr overdueEKTA PARKSVILLE HOMES PVT. LTD. · Vasai, PalgharP99000000110· filed Oct 2019 → now Sept 2023· 89.8% built· 13 complaints
- RUDRA HEIGHTS3.1 yr overdueSAGAR MANOJ GORADIA · Andheri, Mumbai SuburbanP51800026165· 90.9% built· 1 complaint
- Indiabulls Sky Forest -A33.1 yr overdueIndiabulls Properties Private Limited · Elphinstone RoadP51900000616· 97.7% built· 29 complaints
- VRINDAVAN HEIGHTS PHASE II3.1 yr overdueKWALITY WORLD DEVELOPERS (AOP) · HADAPSAR, PuneP52100016466· 94.3% built
- AARAMBH WING E - F3.1 yr overdueSATELLITE DEVELOPERS PVT LTD · Borivali, Mumbai SuburbanP51800015057· filed Mar 2023 → now Sept 2023· 72.7% built
- Anand Sagar3.1 yr overdueAkbar Mohamadali Kazi · ULWE, RaigarhP52000003192· filed Dec 2020 → now Sept 2023· 71.8% built
- Sunteck West World 1, Tivri, Naigaon East3.1 yr overdueSunteck Realty Limited · Tivri, PalgharP99000017606· 90.9% built· 29 complaints
- Sai Millenium AS3.1 yr overdueSHIV CONSTRUCTIONS · Punawale, PuneP52100022267· 81.8% built
- SAMRUDDHI GREENS3.1 yr overdueNAGNATH SHIVSHANKAR AKKALKOTE · UMA NAGRI, SolapurP52600000496· 86.4% built
- Joyville Hinjawadi - I, Phase 63.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100018502· 90.9% built
- Lifestyle City Kalyan - Applause B3.1 yr overdueNirmal Lifestyle (Kalyan) Private Limited · Kalyan, ThaneP51700003543· filed Dec 2018 → now Sept 2023· 58.6% built· 26 complaints
- DELTA WOODS3.1 yr overdueDelta venture · MIRA ROAD, ThaneP51700018070· 73.2% built· 2 complaints
- Universal 11 up Apartments3.1 yr overdueUNIVERSAL HOUSE PVT. LTD. · Shivaji Nagar, NagpurP50500022622· 82.9% built
- Upper Thane - Woodlands G,H,I3.1 yr overdueLODHA DEVELOPERS LIMITED · Anjur, ThaneP51700016245· 81.8% built· 5 complaints
- Zinnea Housing and Commercial3.1 yr overdueSURANA BHANSALI NATEKAR · Chandani Chowk, PuneP52100006078· filed Mar 2021 → now Sept 2023· 97.7% built
- Green Residency3.1 yr overdueGreenlife Developers · Hirve Nagar, NashikP51600030462· 90.9% built
- Sunteck Pinnacle3.1 yr overdueSunteck Realty Limited · Borivali, Mumbai SuburbanP51800028821· 81.8% built
- CHINTAMANI RESIDENCY3.1 yr overdueOM PROPERTIES · WARANALI ROAD, SangliP53100021047· 81.8% built
- WATERS EDGE PHASE VI3.1 yr overdueOM SAGAR DEVELOPERS · Pimple Nilakh, PuneP52100001427· filed Sept 2022 → now Sept 2023· 75.5% built
- HYDE PARK RESIDENCY F5 BUILDING PHASE3.1 yr overdueNEXUS BUILDERS AND DEVELOPERS PVT LTD · Thane, ThaneP51700027694· 86.8% built
- SHIVDATTA APARTMENT3.1 yr overdueBHOLEHAR CONSTRUCTIONS · untwadi, NashikP51600013876· 63.6% built
- Lodha Amara - Tower 20, 213.1 yr overdueLODHA DEVELOPERS LIMITED · Kolshet, ThaneP51700016961· 81.8% built· 8 complaints
- The Address3.1 yr overdueAAKASH BUILDCON BUILDERS AND DEVELOPERS · Sundarban Colony, NashikP51600028893· 90.9% built
- SWAPNWEL RESIDENCY3.1 yr overdueSHRI GANESH DEVELOPERS · NEAR PDVP COLLEGE, SangliP53100025432· 90.9% built
- Krishna Kunj Phase III3.1 yr overdueKrishna developr · Buypass Road, JalnaP51400027480· 81.8% built
- Integrated IRS II3.1 yr overdueIntegrated Spaces Limited · Sector No. 21, RaigarhP52000005863· filed Mar 2019 → now Sept 2023· 90.9% built
- Astha Apartment3.1 yr overduePritam Purshottam Patel · Shree Ram Nagar, NashikP51600027221· 81.8% built
- LIGHT HALL F WING3.1 yr overdueGamma Constructions Pvt Ltd · Kurla, Mumbai SuburbanP51800026229· 90.9% built
- ADISHREE3.1 yr overdueMAHALAXMI DEVELOPERS AND BUILDERS · AMBEGAON BK, PuneP52100014388· filed Mar 2021 → now Sept 2023· 65.9% built
- VENKATESH GRAFFITI GLOVER PHASE 3 - MHADA3.1 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100027217· 90.9% built
- T-Villa3.1 yr overduePanchshil Infrastructure Holdings Pvt Ltd · WAGHOLI, PuneP52100010632· 11.4% built
- ROCKINFRA BLOSSOM3.1 yr overdueROCKINFRA CONSTRUCTION LLP · OPP. GOVT. COLONY BUS STOP, SangliP53100022164· 81.8% built
- Upper Thane - Sereno A, B, B13.1 yr overdueLODHA DEVELOPERS LIMITED · Surai, ThaneP51700016243· 81.8% built· 2 complaints
- NALANDA GARDEN B WING3.1 yr overdueM D CONSTRUCTIONS · HAVELI BANER, PuneP52100031155· filed Sept 2022 → now Sept 2023· 81.8% built
- SHREE DATTA RESIDENCY3.1 yr overdueAbhijit Vijaykumar Borgave · NISHANT COLONY, SangliP53100027820· 90.9% built
- Maatr Waters3.1 yr overdueMaatr Enterprises · Village Barave, ThaneP51700026313· 90.5% built
- AKSHAY FLORA3.1 yr overdueASHOK BHANDARI · KharadiP52100031279· 65.5% built
- Shankeshwar Wisdom3.1 yr overdueNitin Chhaganlal Jain · Moshi, PuneP52100023359· 81.8% built
- PRIMUS3.1 yr overdueRANADE BAGADE CONSTRUCTIONS · BANER, PuneP52100026980· 90.9% built
- Nyati Elan West III3.1 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100025599· 88.1% built
- NB Coral3.1 yr overdueGanesh Associates · Saswad, PuneP52100026536· 88.2% built
- GULMOHAR3.1 yr overdueVAASTU VISHWA BUILDCON · Jalochi, PuneP52100020209· 61.8% built
- S. A. Patil Nagar Garden View CHS3.1 yr overdueShree Khodiyar Builders and Developers · Ambarnath, ThaneP51700032102· 70.4% built
- Joyville Hinjawadi - I, Phase 53.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100018500· 90.9% built· 2 complaints
- Trinity Greens3.1 yr overdueRajmata Realty · Near Bhumkar chowk, PuneP52100021005· 75.8% built
- PGD PINNACLE - A WING3.1 yr overduePGD Land LLP · KESHAVNAGAR, PuneP52100024896· 90.9% built
- PRUTHVI SHAKUN3.1 yr overduePRUTHVI ENTERPRISE · VILE PARLE (EAST), Mumbai SuburbanP51800018162· 18.2% built
- Nikunj3.1 yr overdueDMBhosale · Haveli, PuneP52100027080· 47.3% built
- TANISHKA-III3.1 yr overdueDINESH PATNE & VAISHALI PATNE · WANADONGRI, NagpurP50500029959· 40.9% built
- MADHUBAN3.1 yr overdueDB CONSTRUCTIONS LLP · RAJARAM NAGAR, LaturP52400028254· 65% built
- NEXUS GULMOHAR WING C3.1 yr overdueDIAMOND NEXUS ASSOCIATES · CHARHOLI, PuneP52100022264· 81.8% built
- Casa Row Colony3.1 yr overdueCasa Builders · Bolhegoan, MIDC, AhmednagarP52200026735· 63.6% built
- SHREE GANPATI SAHANIWAS3.1 yr overdueAMIT APPASAHEB JAGADALE · NEAR KRUPAMAI HOSPITAL, SangliP53100023589· 81.8% built
- PYRAMID COUNTY BHUKUM3.1 yr overduePRASAD LIFESPACES LLP · BHUGAON, PuneP52100000387· filed Mar 2022 → now Sept 2023· 88.6% built· 1 complaint
- Sai Ashirwad residency3.1 yr overdueGLOBAL CONSTRUCTION SERVICES · RAHATA, AhmednagarP52200026987· 5.5% built
- Upper Thane - Tiara C3.1 yr overdueLODHA DEVELOPERS LIMITED · Bhiwandi, ThaneP51700016437· 81.8% built
- Riverwood Park Building No. 23.1 yr overdueShree Khidkaleshwar Property Developers Pvt. Ltd. · Thane, ThaneP51700004997· filed Apr 2021 → now Sept 2023· 99.1% built
- TRICITY PALACIO3.1 yr overdueTRICITY REALTY LLP · Thane, ThaneP51700002400· 95.5% built
- TRICITY PROMENADE3.1 yr overdueTRICITY REALTY LLP · Thane, ThaneP51700013737· 89.9% built
- NANDALAL RESIDENCY APARTMENT3.1 yr overdueRUSHIKESH BUILDERS & DEVELOPERS · Deolali (CB), NashikP51600009985· filed Jun 2018 → now Sept 2023· 95.5% built
- Krishna Vihar Row-House3.1 yr overdueKrishna Mega Projects LLP · Buypass Road, JalnaP51400027289· 72.7% built
- Login3.1 yr overdueBombay Slum Redevelopment Corporation Pvt. Ltd. · Borivali, Mumbai SuburbanP51800006953· filed Sept 2022 → now Sept 2023· 90.9% built
- Indiabulls Sky Forest -A23.1 yr overdueIndiabulls Properties Private Limited · Ward GSouth, Mumbai CityP51900000467· 97.7% built· 31 complaints
- YASHOBHOOMI3.1 yr overdueRADHESHYAM RAMESHWARDAS AGARWAL · WADMUKHWADI, PuneP52100022916· 55.5% built
- Shreyas Happy Homes3.1 yr overdueShreyas Shelters · Bhor, PuneP52100004564· 83.6% built· 4 complaints
- VASANT VIHAR B WING3.1 yr overdueA R DEVELOPERS · NARHE, PuneP52100022836· 55.5% built
- THE GRENADIERS3.1 yr overdueBhima builders & developers · POST OFFICE, KolhapurP53000023950· 90% built
- Redevelopment of Om Yogeshwar CHS Ltd3.1 yr overdueVAMA LIFESTYLES · Adarsh, Mumbai SuburbanP51800032528· 82.6% built
- SUMAN COMPLEX3.1 yr overduePANKAJ PRAKASH SAWANT · Karjat, RaigarhP52000013923· 90.9% built
- Bharat Ecovistas Phase III3.1 yr overdueBHARAT REALTY VENTURE PRIVATE LIMITED · Shilphata Junction, Thane, ThaneP51700015290· filed Dec 2021 → now Oct 2023· 81.8% built· 3 complaints
- Padmavati Residency3.1 yr overdueSachin Sukumar Dhanal · Mouje Nagdevwadi, KolhapurP53000029649· 63.6% built
- PRIDE PARK3.1 yr overdueGAURAV VISHVANATH AWATI · morage wasti, AhmednagarP52200027233· 90.9% built
- Ambika Annex3.1 yr overdueAmbika Buildcon · Mayur Vihar Colony Karmyoginagar, NashikP51600023402· 81.8% built
- SADHANAA BUILDING3.1 yr overdueSIDAAN ENTERPRISE · Matunga, Mumbai CityP51900023932· filed May 2022 → now Oct 2023· 73.1% built· 2 complaints
- SHAMBHAVI3.1 yr overdueM/S KHARDE PATIL · NEAR WOODS ROYALE, PuneP52100023514· 90.9% built
- PADMAJA AVENUE3.0 yr overduePADMA BUILDCON · Near Happy Hands pay school, NashikP51600023198· 90.9% built
- PARK TITANIUM PHASE II3.0 yr overduePride Purple Properties · WAKAD, PuneP52100001274· filed Oct 2022 → now Oct 2023· 90.9% built· 2 complaints
- JI TOWER3.0 yr overdueJADHAV CONSTRUCTION · BARAMATI, PuneP52100024294· 81.8% built· 2 complaints
- Lodha Patel Estate - Tower E, F3.0 yr overdueMACROTECH DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800014869· 81.8% built· 7 complaints
- SAI SWAMI APARTMENT3.0 yr overdueSUDHAKAR GARBAD MAHAJAN · SHIVAJI NAGAR, NashikP51600022770· 90.9% built
- Anthurium3.0 yr overdueAARTI ESTATES · Thane, ThaneP51700002317· 70% built
- PALAVA MILANO A,B,C,H,I,J3.0 yr overduePalava Dwellers Private Limited · Palava, ThaneP51700015016· 78.2% built· 3 complaints
- SIDDHI ANAND RESIDENCY3.0 yr overdueANAND CONTRACTORS AND DEVELOPERS · BABRAS MALA, PuneP52100018538· 90.9% built
- JAL SRUSHTI3.0 yr overdueKARAD CITY ENTERPRISE PRIVATE LIMITED · Patan Colony, SataraP52700019323· 61.2% built
- RANJEET HEIGHTS CO OP HSG SOCIETY3.0 yr overdueRAJESH DINESH VYAS · RAMBAUG COLONY, PuneP52100026612· 81.8% built
- ASHAR EDGE WING B PHASE III3.0 yr overdueMs ASHAR VENTURES · Thane, ThaneP51700016016· 94.5% built
- Geras Adara3.0 yr overdueGera Realty Estates · Man, PuneP52100000889· 90.9% built
- SIDHIVINAYAK RESIDENCY3.0 yr overdueSWARAJ CONSTRUCTION · Pimpri Chinchawad (M Corp.), PuneP52100007687· filed Dec 2021 → now Oct 2023· 52.7% built
- VIVANTA LIFE VIPUL PHASE 13.0 yr overdueVIVANTA REALTY · Pimpri Chinchawad (M Corp.), PuneP52100001347· 81.8% built
- SHREEJI SPARSH3.0 yr overdueSKY LINE BUILDERS · GOVIND NAGAR, NashikP51600020981· 9.1% built
- VISION ACE PHASE 13.0 yr overdueVISION ACE · TATHAWADE, PuneP52100017748· 95% built
- LEGACY MILLENNIA A3.0 yr overdueMILLENNIUM LEGACY DEVELOPERS · PUNAWALE, PuneP52100027317· 81.8% built
- Riverwood Park Building No. 43.0 yr overdueShree Khidkaleshwar Property Developers Pvt. Ltd. · Thane, ThaneP51700004003· filed Oct 2022 → now Oct 2023· 94.1% built
- ASHAR EDGE GALLERIA- PHASE I3.0 yr overdueMs ASHAR VENTURES · Thane, ThaneP51700016033· 86.4% built
- Bright Aristo3.0 yr overdueBrightera Builders · Dhore Wasti, PuneP52100011377· filed Dec 2020 → now Oct 2023· 81.8% built· 1 complaint
- JEEVAN CHS LTD3.0 yr overdueSHARDA VASTU NIRMITEE PVT. LTD. · PANCHPAKHADI, ThaneP51700023605· 90.9% built
- SAVANNAH AVALON3.0 yr overdueSavannah Real Estate Pvt. Ltd · Andheri, Mumbai SuburbanP51800020465· 81.8% built
- ACE AASTHA BUILDING B3.0 yr overdueSAKSHI DEVELOPERS · OPP. TANISHQ ORCHID SOCIETY, PuneP52100016438· 83.6% built
- Nakshatra A-B3.0 yr overduePramukh Realty · Krishna Company Road, Dadra & Nagar HaveliP49600000067· 90.9% built
- Laxminarayan Arcade - I3.0 yr overdueRajan Namdeo Pore · Wai, SataraP52700019452· 90.9% built
- SUMUKH HILLS3.0 yr overdueM/S.YOGSIDDHI DEVELOPERS · Borivali, Mumbai SuburbanP51800005591· 90% built· 3 complaints
- ASHAR EDGE WING A PHASE II3.0 yr overdueMs ASHAR VENTURES · Thane, ThaneP51700016015· 96.4% built
- SANKESHWAR DARSHAN3.0 yr overdueM/s. Rishabraj Balaji Infra · BORIVALI EAST, MUMBAI, Mumbai SuburbanP51800024086· 82.7% built· 2 complaints
- PATELS ELYSIUM - 23.0 yr overdueAPACE REALTY · Ambarnath, ThaneP51700008491· 87.3% built
- PATELS ELYSIUM - 43.0 yr overdueAPACE REALTY · Ambarnath, ThaneP51700006142· 87.3% built
- REDEVELOPMENT OF MALAD AMBER CHSL3.0 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800025354· 90.9% built
- SAI WORLD RETREAT3.0 yr overdueParadise Leisure Homes · Ulhasnagar (M Corp.), ThaneP51700001566· 24.8% built
- Siddhivinayak Heights3.0 yr overdueShree Siddhivinayak Builders · Satara, SataraP52700015936· 90.9% built
- Lodha Parel Project3.0 yr overdueMACROTECH DEVELOPERS LIMITED · Mumbai City, Mumbai CityP51900014910· 90.9% built
- SAO KAMALABAI DREAM HOME PROJECT RESIDENCY3.0 yr overdueV R CONSTRUCTIONS · NEAR MADHUBAN HOTEL, AurangabadP51500013653· filed Nov 2018 → now Oct 2023· 90.9% built
- RISHABRAJ DIVINE3.0 yr overdueM/s. Rishabraj Balaji Infra · BORIVALI EAST, MUMBAI, Mumbai SuburbanP51800023315· 9.1% built
- NEW FRIENDS SRA CHS LTD3.0 yr overdueM/S. VIRAJ ENTERPRIES · Andheri, Mumbai SuburbanP51800008637· 72.1% built
- RAM-INDU APARTMENTS3.0 yr overdueAKASH CONSTRUCTION CO. · PANDE LAYOUT, NagpurP50500022483· 40.6% built
- SATYAM HEIGHTS APARTMENT3.0 yr overdueRAJU BABULAL KUMAWAT · MAUJE PIMPALGAON BAHULA, NashikP51600022714· 90.9% built
- SHANKAR PALACE3.0 yr overdueShree Ramesh Homes Builders And Developers · Thane, ThaneP51700012469· 90.9% built· 2 complaints
- PALAVA AURORA A,D3.0 yr overduePalava Dwellers Private Limited · Palava, ThaneP51700015090· 77.3% built
- Tokyo Bay Phase - 13.0 yr overduePuranik Tokyo Bay Private Limited · Thane, ThaneP51700000618· 90.9% built· 6 complaints
- MANIK SIGNIA3.0 yr overduePate Siddhashila Developers LLP · Shivajinagar (Bhamburda), PuneP52100022879· 95% built
- VISHNU VATIKA NX WING C1 E1 E2 PHASE 13.0 yr overdueVISHNU GROUP · BADLAPUR, ThaneP51700004777· 88.5% built
- Laxminarayan Arcade3.0 yr overdueRajan Namdeo Pore · Wai, SataraP52700019419· 90.9% built
- PATELS ELYSIUM - 33.0 yr overdueAPACE REALTY · Ambarnath(M Cl), ThaneP51700010280· 87.3% built
- SAHAYOG NILAYAM3.0 yr overdueSAHAYOG CONSTRUCTION · Manda, ThaneP51700008289· 90.6% built· 1 complaint
- NS HEIGHTS3.0 yr overdueNS BUILDERS & DEVELOPERS · Andheri, Mumbai SuburbanP51800002156· filed Mar 2021 → now Oct 2023· 90.9% built· 1 complaint
- SAI DARBAR3.0 yr overdueKAILAS SURESH SATELKAR · PILANKAR WADI, SindhudurgP52900033068· 72.7% built
- Kandivali Sai Prassana CHS Ltd3.0 yr overdueAshwin Enterprise · Kandivali West, Mumbai SuburbanP51800032312· 90.9% built
- VASTUPURTI GALAXY3.0 yr overdueVAIBHAV DATTATRYA MUTRAK · BEHIND UDYOG BHAVAN, NashikP51600047258· 54.5% built
- Ved - Ashritha Phase I3.0 yr overdueYogvinda Promoters & Developers Pvt. Ltd. · Katraj, PuneP52100002175· filed Aug 2019 → now Oct 2023· 40.9% built
- Gokul Aura3.0 yr overdueMehta Ventures · Virar West, PalgharP99000035169· 90.9% built
- RAHMAT ARCADE3.0 yr overdueUNITED CONSTRUCTION CO · CHARATHE, SindhudurgP52900015496· filed Dec 2019 → now Oct 2023· 90.9% built
- MAPLE GREENS3.0 yr overdueTHE SILWANT · Ukrul, RaigarhP52000013794· filed Mar 2021 → now Oct 2023· 90.9% built· 1 complaint
- ELITE 12 PHASE 13.0 yr overdueS and S Associates · Pune City, PuneP52100031737· 90.9% built
- NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.3.0 yr overdueMAVERICK REALTORS · MUMBAI, Mumbai SuburbanP51800012145· filed Jun 2021 → now Oct 2023· 99.1% built
- 41 Estera Phase 23.0 yr overdueSamarttha Trimurti Properties · PUNAWALE, PuneP52100014226· filed Mar 2022 → now Nov 2023· 90.9% built
- KANCHAN VATIKA3.0 yr overdueNovel Build-con · Palghar, PalgharP99000026327· 90.9% built
- SANGAM GARDEN3.0 yr overdueKOUSTUBH RAJENDRA SHAH · Khed (CT), SataraP52700003276· filed May 2018 → now Nov 2023· 90.9% built
- SATRA HARMONY3.0 yr overdueRRB REALTORS PVT LTD. · Kurla, Mumbai SuburbanP51800000726· filed Dec 2019 → now Nov 2023· 90.9% built· 7 complaints
- Adhiraj Samyama Tower 2B3.0 yr overdueAdhiraj Constructions Private Limited · Panvel, RaigarhP52000003039· filed Jun 2021 → now Nov 2023· 80.4% built· 11 complaints
- HRESA - SAINAGAR APARTMENT PVT. LTD.3.0 yr overdueBHOLENATH DEVELOPERS LTD. · Kurla, Mumbai SuburbanP51800004835· filed Nov 2022 → now Nov 2023· 90.9% built
- Laxmi Paradise3.0 yr overdueAshtagandha Construtions · SHIVAJI NAGAR, RatnagiriP52800003415· 90.9% built
- Kartikya Residency3.0 yr overdueSunil Chamanlal Gupta · Adai, RaigarhP52000022323· filed Sept 2023 → now Nov 2023· 90.9% built
- PARITOSH D2.9 yr overdueSHARADA ALLIANCE SHELTERS · BALEWADI, PuneP52100023380· 65.5% built
- Samarth Glory2.9 yr overdueEkdanta Realtors · Near Mandlik Nagar, NashikP51600023373· 90.9% built
- THE ADDRESS PHASE-32.9 yr overdueSOL Developers · OPP. BORATE VASTI, MOSHI, PuneP52100020839· 78.8% built
- REDEVELOPMENT OF PRAVESH CHSL2.9 yr overduePRANAV CONSTRUCTIONS LIMITED · BORIVALI EAST, Mumbai SuburbanP51800020989· 64.1% built
- Omkar2.9 yr overdueOmkar Developers · Vasai, PalgharP99000002389· 86.4% built
- GOBIND REGENCY2.9 yr overdueSUKHMANI CONSTRUCTIONS · Khed, PuneP52100005810· 66.4% built
- TULSI RESIDENCY2.9 yr overdueOM ENTERPRISE · RINGANWADA, DamanP49500000020· 90.9% built
- BHAVESHA CO-OPERATIVE HOUSING SOCIETY LTD2.9 yr overdueBEAUTIFUL PROPERTIES PRIVATE LIMITED · ANDHERI (WEST), Mumbai SuburbanP51800033264· 90.9% built
- MANGALMURTI APARTMENT2.9 yr overdueICCHAMANI DEVELOPERS · WADALA, NashikP51600028875· 90.9% built
- MARBLE ARCH2.9 yr overdueAvvesh Developers LLP · Vasai-Virar City (M Corp), PalgharP99000011971· filed Dec 2019 → now Nov 2023· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.